Coronado Global Resources Inc. 10-K, filed Feb 20, 2024: Technical report summary
Coronado Global Resources Inc. (“Coronado”) Statement of Coal
Resources and Reserves for the Curragh Mine Complex in Accordance
with the JORC Code and United States SEC Regulation S-K 1300 as of
December 31st 2023
Bowen Basin
Queensland, Australia
February 2024
SIGNATURE PAGE
Effective Date of Report:
December 31st, 2023
Qualified Person(s) Preparers:
Name: Barry Lay
Managing Director of Resology Pty Ltd (Prepared Sections: 1.3, 1.4, 1.6, 5.2, 6, 7, 8, 9, 10, 11 , 21,
22, 23, 24, 25, 26)
_/s/ Daniel Millers___________________
Name: Daniel Millers
Superintendent Long Term Planning – Coronado Curragh Pty Ltd (Prepared Sections: 1.1, 1.2, 1.5,
1.7, 1.8, 1.9, 1.10, 2, 3, 4, 5, 12.1, 13.1, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26)
_/s/ Chris Wilkinson __________________
Name: Chris Wilkinson
Director Mining Consultancy Services (Australia) Pty Ltd – Talisman Technical Pty Ltd
Signature Date:
February 15th, 2024
Page 1 of 118
Table Of Contents
Page 2 of 118
Page 3 of 118
Page 4 of 118
LIST OF FIGURES
Page 5 of 118
Page 6 of 118
LIST OF TABLES
Page 7 of 118
1 Executive Summary
1.1 Property Description
This report provides a statement of Coal Resources and Coal Reserves estimates for Curragh mine
(sometimes referred to herein as Curragh or the Property) in Central Queensland, Australia, as defined under
Subpart 1300 of Regulation S-K (Regulation S-K 1300) promulgated by the United States Securities and
Exchange Commission (SEC) and the Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves (JORC Code 2012). This report was also prepared in accordance with the
Australasian Code for Public Reporting of Technical Assessments and Valuations of Mineral Assets (VALMIN
Code 2015).
Coal Resources and Coal Reserves estimates are herein reported and rounded to millions of metric tonnes
(Mt).
Curragh is located approximately 200 kilometres by road west of Rockhampton and approximately 14 km north
of the town of Blackwater (refer to Figure 3-1) within the Central Highlands Regional Council, Queensland
Australia. The coordinates of the mine are 688,561 East, 7,400,933 North in the AMG66 grid system.
The Property is comprised of approximately 25,586 total hectares of approved Mining Leases and Mineral
Development Licences. Underlying these Resource Authorities are various forms of cadastral land with
different ownership arrangements as detailed in section 3.2. Coronado is able to access all the land through
either direct ownership or signed agreements.
1.2 Ownership
Curragh commenced operations in 1983 and was formerly controlled by a consortium of companies. These
companies were bought out by Arco Australia who later sold the Property to Wesfarmers. Coronado acquired
the Property from Wesfarmers in 2018. Further details on ownership are presented in Sections 3.2 to 3.4
1.3 Geology and Mineralization
The Curragh mine extracts seams in the Rangal Coal Measures including the Cancer, Aries, Castor, Pollux,
Orion and Pisces seams. These coals are suitable for beneficiation to metallurgical and thermal products.
Some seams are suitable to bypass direct to product. Further details on the geology of the operations are
provided in Section 6.
1.4 Exploration Status
The Property has been extensively explored, largely by drilling open chip holes as well as core holes, downhole
geophysics is used extensively. The majority of the data was acquired or generated by previous owners of
the Property. These sources comprise the primary data used in the evaluation of the coal Resources and coal
Reserves on the Property.
Ongoing exploration has been carried out by Coronado since acquiring the Curragh mine. The exploration
data acquired by Coronado has been consistent with past drilling activities. Recent exploration has included a
focus on underground exploration including the acquisition of 2D and 3D seismic data. Further details on past
exploration efforts are discussed in Section 7.
1.5 Operations and Development
Curragh operates the open cut using a conventional open cut strip mining technique using draglines and truck
and excavator methods typical throughout the Bowen Basin. Curragh operates 4 large electric draglines, 1
large electric rope shovel and fleets of diesel hydraulic excavators in the open cut. The mine’s annual
production capacity of approximately 185 Mbcm of total movement means it can be ranked as a large open
cut coal operation when compared to producers in Australia and internationally. The open cut operation mines
around 13.5Mt Run of Mine (ROM) coal per annum, producing around 11Mtpa of product coal.
Page 8 of 118
The Curragh mine includes a development underground project at Curragh North currently in operational
readiness phase and planned to commence production in 2025. The selected underground mining method is
Bord and Pillar Mining using the Place Change operating methodology. The Life of Mine (LOM) underground
plan utilises up to four continuous miners over two separate mining levels, entering the target seams directly
from a final open cut highwall. The target seams to be mined using underground methods are the Mammoth
and Mackenzie seams at Curragh North. The Mammoth seam corresponds to the coalesced Aries and Castor
seams in the open cut, and the Mackenzie seam corresponds to the coalesced Pollux, Orion and Pisces seams
in the open cut.
The underground project will add a ROM production profile on top of the existing open cut mine, at around
3Mtpa ROM coal. This takes the total ROM coal feed to the Coal Handling and Preparation Plant (CHPP) to
nameplate capacity of around 16.5Mtpa for the total Curragh mining complex, maximising the production
potential with the existing installed processing infrastructure on site. The product coal profile is targeted to be
around 13.5Mtpa from the combined open cut and underground operations, decreasing over the LOM as the
yield from the open cut coal reduces over the LOM plan. The mine produces coal that is suitable for the export
metallurgical and thermal coal markets, as well as a long term domestic thermal coal supply contract.
There are two coal preparation plants at Curragh, CPP1 and CPP2. CPP1 has a nameplate capacity of 1,100
raw tonnes per hour (tph). CPP2 has a nameplate capacity of 1,200 tph but is capable of 1,350 tph when
processing selected feed types. Processes are typical of those used in the coal industry and are in use at
adjacent coal processing plants. Further details on coal processing and infrastructure are discussed in
Sections 14 and 15 respectively.
1.6 Mineral Resource
Mineral Resources, representing in-situ coal form a portion of which Reserves are derived, are presented
below. The Coal Resource estimate, summarized in Table 1.1, was prepared as of December 31, 2023, for
the Curragh Mine. Further details on the Coal Resource estimate is presented in Section 11 .
Table 1.1: Coal Resources Summary as of December 31, 2023
Area
Measure
d (Mt)
Indicate
d (Mt)
Meas +
Ind (Mt)
Inferred
(Mt)
Total
(Mt)
Ash %
VM
%
Sulphur
%
Opencut
Inclusive of Reserves
217
25
242
-
242
18.7
19.2
0.57
Exclusive of Reserves
167
81
247
54
302
22.9
19.1
0.59
Total Open-cut
383
106
489
54
543
21.0
19.1
0.58
Underground
Inclusive of Reserves
140
44
183
-
183
14.9
18.2
0.39
Exclusive of Reserves
41
62
103
106
209
18.6
18.1
0.39
Total Underground
181
106
286
106
392
16.9
18.2
0.39
Total Resources
564
211
775
160
936
19.2
18.7
0.50
(i) Total Coal Resources (936Mt) are reported inclusive of Reserves
(ii) Coal Resource tonnes are reported on a 5.3% in-situ Moisture basis
(iii) Coal qualities are reported on an air-dried basis
(iv) Underground resources are those that are approximately >15:1 vertical strip ratio or those overlapping underground mining
reserves
(v) The numbers have been rounded and the totals may not add up.
Page 9 of 118
1.7 Mineral Reserve
The Coal Reserve estimate summary for Curragh reported in Table 1.2 has been converted from the Coal
Resource estimate. The Marketable Coal Reserve estimate in Table 1.3 represents beneficiated or otherwise
enhanced coal product where modifications due to mining, dilution and processing have been considered and
is an estimate of the marketable product achievable from the Coal Reserve.
The numbers are based on the results and findings of the Qualified Persons and their application of the relevant
modifying factors to the Coal Resource geological model. The basis for the conversion of Coal Resources to
Coal Reserves including the modifying factors used is discussed in section 12. Inferred Resources are not
included in the Coal Reserve estimate.
Table 1.2: Coal Reserve Estimate Summary as of December 31, 2023 (Mt)
Curragh ROM Tonnes
Proven
Probable
Total
Quality (adb)
Mt
Mt
Mt
Ash (%)
TS (%)
VM (%)
Open Cut
227
22
249
31.3
0.5
16.0
Underground
30
11
41
17.0
0.3
16.4
Curragh Total
257
33
290
Table 1.3: Marketable Coal Reserve Estimate Summary as of December 31, 2023 (Mt)
Demonstrated Coal Reserves
(Wet Tonnes, Washed or Direct Shipped, Mt)
Quality (adb)
Product Tonnes
By Reliability Category
Proven
Probable
Total
Ash%
Sulphur%
VM%
Open Cut
173
16
189
12.2
0.5
19.5
Underground
25
9
34
10.0
0.3
16.9
Curragh Total
198
25
223
a) Coronado's ownership is 100% of the Curragh Mine
b) All tonnes are millions of metric tonnes (Mt).
c) Open Cut ROM Coal Reserves have been stated on a 7.5% Moisture basis. Underground ROM Coal Reserves have been
stated on an 8.0% Moisture basis.
d) Open Cut Marketable Reserves are stated on a product moisture basis of 9.5%. Underground Marketable Reserves are
stated on a product moisture basis of 10%
e) Coal qualities are reported on an air-dried basis.
f) Typical marketable coal products produced range from low-ash, hard coking coal to mid-ash semi-hard coking coal, a variety
of low-volatile Pulverised Coal Injection (PCI) products ranging from low to high ash, and thermal coal
g) Totals may not sum due to rounding.
1.8 Capital and Operating Costs
Capital costs for the Curragh mine are split into development capital for new projects such as the underground
project, X pit and Z pit developments, and Stay in Business (SIB) capital as a requirement to support the
ongoing operations with new infrastructure and equipment as the current installed and operated equipment
reaches its useful operating life. A summary of the estimated capital profile over the LOM for the Property is
provided in Figure 1-1.
Page 10 of 118
Figure 1-1: CAPEX US$ million (nominal)
Mine operating costs include fixed and variable costs for both the open cut and underground operations both
onsite and offsite to Free on Board (FOB) loaded onto a ship at the port for export coal, or Free on Rail (FOR)
loaded onto a train for domestic thermal coal. The open cut costs have been benchmarked off the existing
open cut operation at Curragh. The underground development project operating costs have been supplied by
a third party independently with experience estimating costs for similar underground Bord and Pillar mining
projects in the Rangal seams in the Bowen Basin.
All state regulated and third party contracted royalties payable based on the Curragh coal production profile
are included in the operating costs, as well as indirect business costs backcharged to the Curragh operation
such as a corporate support functions.
A summary of projected operating costs profile over the LOM for the Property is provided in Figure 1-2.
Figure 1-2: Curragh Operating Cost Profile (nominal)
1.9 Economic Evaluation
The financial model prepared for this Technical Report Summary (TRS) was developed to test the economic
viability of the Coal Reserves. The results of this financial model are not intended to represent a bankable
feasibility study, required for financing of any current or future mining operations contemplated for the
Coronado properties, but are intended to establish the economic viability of the estimated Coal Reserves.
Cash flows are simulated on an annual basis based on projected production from the Coal Reserves.
The project cash flows, excluding debt service, are calculated by subtracting direct and indirect operating
expenses, tax payments and capital expenditures from revenue. Customer coal pricing have been estimated
Page 11 of 118
based on industry specialists forecasts and appropriate discounts and adjustments applicable to Curragh’s
products.
Economic outcomes include capital forecasts and government and contracted royalty and rebate payments.
Table 1.4: LOM tonnage, Profit & Loss (P&L) before tax and EBITDA
LOM Clean
LOM
PandL
LOM
EBITDA
Tonnes
Pre-Tax PandL
Per Tonne
EBITDA
Per Tonne
Curragh
253Mt
4.7 billion
18
7.0 billion
28
Clean tonnes produced in LOM plan are greater than Marketable Coal Reserve tonnes due to mine sequencing
required for open pit mine design and operating long strike dragline pit operations to achieve the Marketable
Reserves. Under SEC requirements Inferred Resources cannot be converted to a Coal Reserve, only
Measured and Indicated Resources may be converted to a Coal Reserve.
In order to allow the mine plan to proceed however Inferred Resources must be mined as part of the LOM
plan, these are then excluded for reporting purposes from the marketable tonnes. The majority of Inferred
Resources are mined late in the mine schedule and due to time value of money these have minimal impact on
net present value NPV valuation.
As shown in Table 1.4 the Curragh Mine shows positive EBITDA over the LOM. Overall, Curragh’s operations
show positive LOM P&L and EBITDA of over $4 billion and $7 billion respectively.
Curragh’s cash flow summary, excluding debt service, is shown in section 19.
Consolidated cash flow from operations is positive over the mine life with the post-production years showing
negative cash flows due to end-of-mine reclamation spending.
Cash flow after tax, but before debt service, generated over the life of the project was discounted to NPV at a
10.0% discount rate, which represents the risk adjusted return demanded by a hypothetical investor in
Curragh, also referred as the Weighted Average Costs of Capital (WACC). The assessment of an appropriate
discount rate is a matter of judgement considering market pricing information and the characteristics,
circumstances and risks specific to the asset generating the cash flows subject to discounting.
The NPV of the project cash flows is a point in time estimate of potential economic outcomes with scope for
further projects not exhausted. The NPV amounts to approximately USD 1.1 billion as a base line only with
outcomes highly dependent upon market based pricing, exchange rates, and various other factors. The
financial model prepared for the TRS was developed to test the economic viability of each coal resource area.
The NPV estimate was made for purposes of confirming the economics for classification of Coal Reserves and
not for purposes of valuing Coronado or its Curragh assets. Mine plans may change or be optimised in
increase cashflow/NPV, and actual results of the operations may be different. In all cases, the mine production
plan assumes the properties are under competent management.
1.10 Conclusion and Recommendations
Sufficient data has been obtained through various exploration and sampling programs and mining operations
to support the geological interpretations of seam structure and thickness for coal horizons situated on the
Curragh Property. The exploration data is of sufficient quantity and reliability to reasonably support the Coal
Resource and Coal Reserve estimates in this TRS.
The geological data and LOM Plan in this report consider mining plans, revenue, operating and capital cost
assumptions that are sufficient to support the classification of Coal Reserves provided herein.
Page 12 of 118
2 Introduction
2.1 Registrant and Terms of Reference
This report was prepared for the sole use of Coronado Global Resources Inc. (“Coronado”) and its affiliated
and subsidiary companies and advisors. The report provides a statement of coal Resources and coal Reserves
for the Curragh mine, as defined under SEC Regulation S-K 1300 and the Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves (JORC Code 2012). This report was also prepared
in accordance with the Australasian Code for Public Reporting of Technical Assessments and Valuations of
Mineral Assets (VALMIN Code 2015). This report updates the technical report summary titled, "Coronado
Global Resources Inc. (“Coronado”) Statement of Coal Resources and Reserves for the Curragh Mine
Complex in Accordance with the JORC Code and United States SEC Regulation S-K 1300 as of December 31,
2021 Bowen Basin Queensland, Australia February 202 2," dated February 21, 2022.
The report provides a statement of Coal Resources and Coal Reserves for the Curragh mine. Exploration
results and Resource calculations were used as the basis for the mine planning.
Coal Resources and Coal Reserves are herein reported in metric units of measurement and are rounded to
millions of metric tonnes (Mt). All currency is in USD.
2.2 Information Sources
This TRS is based on information provided by various Curragh employees and external consultants and
reviewed by Barry Lay (Qualified Person Resource) and Daniel Millers (Qualified Person Open Cut Reserve)
and Chris Wilkinson (Qualified Person Underground Reserve). For the evaluation, the following tasks were
completed:
●
geological models;
●
●
●
Reserves which would include:
o
o
o
under the JORC Code and Regulation S-K 1300.
2.3 Personal Inspections
Daniel Millers is a full time employee of Coronado Global Resources in the role of Superintendent Long Term
Planning. Daniel has a thorough understanding of the Curragh mine site and has made numerous site visits
during his 3 years of employment with the organisation .
Barry Lay is an external consultant operating under his own company Resology Pty Ltd and is a former Curragh
employee with years of site experience.
Chris Wilkinson is a Director of Mining Consultancy Services Pty Ltd the Advisory entity of Talisman Technical
Pty Ltd, an independent consultancy company who has been engaged by Coronado Global Resources
throughout the Curragh North Underground Project. Mr Wilkinson visited Curragh Mine and the planned
underground mine location in S-Pit area during 2023.
Page 13 of 118
3 Property Description
3.1 Location
The Curragh Project is located approximately 200 kilometres by road west of Rockhampton and approximately
14 km north of the town of Blackwater (refer to Figure 3-1) within the Central Highlands Regional Council,
Queensland Australia. The coordinates of Curragh are 688,561 East, 7,400,933 North in the AMG66
coordinate system.
Figure 3-1: Location Map
Page 14 of 118
3.2 Titles, Claims or Leases
The Mineral Resources Act 1989 (Qld) (MRA) and the Mineral and Energy Resources (Common Provisions)
Act 2014 (Qld) (MERCPA), together, provide for the assessment, development and utilization of mineral
resources in Queensland to the maximum extent practicable, consistent with sound economic and land use
management. The MRA vests ownership of minerals, with limited exceptions, in the Crown (i.e., the state
government). A royalty is payable to the Crown for the right to extract minerals. The MRA also creates different
tenures for different mining activities, such as prospecting, exploring and mining. A mining lease (ML) is the
most important tenure, as it permits the extraction of minerals in conjunction with other required authorities.
The MRA imposes general conditions on an ML.
Coronado controls the coal mining rights at Curragh under 14 coal and infrastructure ML’s and three Mineral
Development Licences, granted pursuant to the MRA. The ML’s and MDL’s at Curragh are referred to,
collectively, as the Tenements. Renewal of certain Tenements will be required during the mine life of Curragh
and the Queensland government can vary the terms and conditions on renewal. There are a number of
petroleum tenements which overlap with the Tenements. The priority, consent and coordination requirements
under the MRA, MERCPA and the Petroleum and Gas (Production and Safety) Act 2004 (Qld) (as relevant)
may apply with respect to those overlaps. Extensive statutory protocols govern the relationships between
co-existing mining and exploration rights and these protocols are largely focused on encouraging the
overlapping tenement holders to negotiate and formulate arrangements that enable the co-existence of their
respective interests. To date, Coronado has negotiated arrangements in place with all of the overlapping
tenement holders and full access to all of its Tenements.
The respective Curragh ML and MDL tenements are shown in Figure 3-2. Detail on individual tenements are
listed in Table 3.1 for the Mining Leases and Table 3.2 for the Mineral Development Leases. A land ownership
map is shown in Figure 3-3.
Page 15 of 118
Figure 3-2 - Mining Leases and Mineral Development Licenses
Page 16 of 118
Table 3.1: Mining Leases
Mineral Lease
Permit Name
Expires
Hectares
Comments
ML 1878
Curragh
5/31/2024
4,455
ML 80112
Curragh B
9/30/2025
110
Infrastructure
ML 80086
Curragh East
10/31/2025
3,033
ML 1990
Curragh A
5/31/2033
172
ML 80010
Curragh Extended No.1
5/31/2033
24
Infrastructure
ML 80011
Curragh Extended No.2
5/31/2033
6
Infrastructure
ML 80012
Curragh Extended No.3
5/31/2033
43
Infrastructure
ML 80171
Curragh West
7/31/2040
954
ML 700008
Curragh Central Extended
11/30/2040
2,643
ML 700009
Curragh Extended
11/30/2040
797
ML 700006
Curragh South
6/30/2041
1,432
ML 700007
Curragh Central
6/30/2041
1,123
ML 80110
Curragh North
7/31/2044
4,860
ML 80123
Curragh North A
7/31/2044
5
19,658
Table 3.2: Mineral Development Licenses
License
Permit Name
Expires
Hectares
Comments
MDL 328
Curragh West No. 1
8/31/2026
381
MDL 329
Curragh West No. 2
8/31/2026
2,334
MDL 162
Mackenzie
2/29/2028
3,213
5,928
Page 17 of 118
Figure 3-3: Surface landownership details
Page 18 of 118
There are no outstanding disputes or litigation. Only one tenement (ML 80123) required a native title process
for its grant. Curragh undertook the Right to Negotiate process with the then Native Title Parties, the Gaangalu
Nation People, and concluded an ancillary agreement and a section 31 Deed to allow the ML to be validly
granted in compliance with the Commonwealth Native Title Act 1993.There are no material issues relating to
native title for the Curragh operations.
Curragh negotiated a Cultural Heritage Management Plan (“CHMP”) for the project in 2012. There have been
subsequent changes to the registration and composition of the Native Title claim for the relevant Aboriginal
Party. A new CHMP has been prepared for the extended Curragh operations, signed on December 19, 2017.
Cultural heritage is unlikely to pose any material issues to the Curragh operations.
3.3 Mineral Rights
Property control and mining rights at Curragh are entirely expressed in the MLs and MDLs mentioned in the
previous section of this document. Overlapping petroleum tenure exists over the southern and eastern extents
of the Curragh tenements. Under the Mineral and Energy Resource (Common Provisions) Act 2014 legislation
(‘MERCPA 2014”) this requires annual information exchanges including the provision and maintenance of Joint
Information Management Plans with the overlapping petroleum tenement holder. Coronado is compliant with
the legislation and there are no current restrictions to coal mining.
3.4 Encumbrances
There are mortgages on the tenements.
3.5 Other Risks
Risk exists in areas of high environmental significance; these are managed by internal processes as part of
the normal day to day operations of the mine. Areas that have high environmental value that lie outside of the
approved disturbance footprints are not included within the Coal Resource and Reserve estimates.
There are no indications that matters associated with surface rights, mineral rights, or other encumbrances
would deny access to the resources and reserves captured in the current estimates.
Page 19 of 118
4 Accessibility, Climate, Local Resources, Infrastructure and
Physiography
4.1 Topography, Elevation and Vegetation
Curragh coal mine is characterized by a general gently rolling topography, which is the predominant feature
for the Bowen Basin. The principal drainage conduits are the Mackenzie River and the Blackwater Creek and
their tributaries, which represent the upper phase of the hydrologic regime. The mean altitude is between 140
and 150 metres above sea level.
Vegetation at Curragh consists primarily of grass land, with pastures and low intensity cattle grazing being the
primary forms of non-mining land use; the secondary land use is crop farming over dry lands. Most of the
original vegetation was cleared for agricultural exploitation with a relatively small portion remaining along the
two aforementioned waterways.
4.2 Access and Transport
Established sealed roads connect the mine to the towns of Emerald to the west and the port at Gladstone to
the east. Curragh site owns and runs a rail loop, adjacent to product stockpiles with a conveyor system that
feeds train loadout bin. Domestic coal sales are loaded onto train wagons for transportation to the Stanwell
coal fired power station for power generation. While export coal is transported by rail on the Blackwater line
approximately 290km to the RG Tanna or Wiggins Island Coal Export Terminal (WICET) port facilities at
Gladstone. No coal transportation takes place on waterways.
4.3 Availability of Infrastructure
The closest population centre with respect to Curragh is the town of Blackwater approximately 14 km to the
south. The major regional town of Emerald, located 75 km to the west, offers daily flights to the State Capital
of Brisbane and is used extensively by Coronado personnel travelling to and from site.
4.4 Climate and Length of Operating Season
The prevailing climate at Curragh is sub-tropical characterized by warm to hot and wet summers and cool to
mild, dry winters. The highest temperatures are observed in January, reaching an average of 34° C; the coldest
temperatures occur in July at an average of 7°C. Annual rainfall averages 635 mm, with January being the
wettest month with typical rainfalls of +90 mm. July is the driest month with typical precipitation averaging 19
mm.
Page 20 of 118
5 History
5.1 Previous Operation
The coal mine at Curragh was developed in 1983 as a joint venture between the following partners with
respective participation in ownership:
Arco Australia Ltd
30%
Australian Consolidated Industries Ltd
30%
R. W. Miller and Co.
30%
Mitsui and Co. (Australia)
10%
Arco Australia Ltd. bought out the other joint venturers and in 2000 sold the property to Wesfarmers Ltd. In
2014, Wesfarmers acquired MDL 162 from Peabody Budjero Pty Ltd. Coronado acquired all the Tenements
from Wesfarmers Ltd. in March 2018. Since the project’s inception, additional MLs and MDLs were
incorporated into Curragh at different times.
5.2 Previous Exploration
Curragh has been the subject of numerous phases of exploratory drilling programs extending back to the early
1960s. Currently there are some 15,000 boreholes available for geological evaluation of the asset with around
9,000 directly within the current mineral concession borders. The vast majority of these boreholes are of the
non-coring type (open hole) but with a regular spacing cored holes used for coal quality evaluation. Further
details on past exploration efforts are presented in Section 7. Various drilling programmes were conducted by
the Queensland Department of Minerals and Energy (previously known as Mines Department) during the
period 1966-76 over a large area between the Capricorn Highway and the Mackenzie River. The area was
within the Department of Mines Reserved Area 56D (RA56D). From 1976 to 1978 detailed drilling and coal
analysis was carried out by officers of the Geological Survey of Queensland on behalf of the State Electricity
Commission of Queensland (SECQ). During this time the SECQ (SECQ’s interest is now vested in Stanwell
Corporation Limited (Stanwell) was granted Authority to Prospect (ATP) 217C. Extensive exploration of the
Curragh area within ATP 217C occurred between 1976 and 1978.
). The Curragh lease (ML1878) was granted on 27 May 1982 and that part of the area was relinquished from
ATP 217.
In 1982 further exploration was carried out by Geological Survey of Queensland on behalf of SECQ in the
Curragh East area (now ML 80086). A subsequent exploration programme in 1993 was also undertaken in the
area to collect additional coal quality and structural data. Four hundred holes were drilled, comprising 320
open holes with geophysical logs and 80 partially cored holes. ML80086 was granted on 19 October 2000.
In 1996 a large exploration programme was undertaken at the northern end of MDL162 and this work provided
the basis for the Pisces Project feasibility study (Curragh North). In 2001 twenty partially cored holes were
drilled in this northern part of MDL162 to provide samples for bench scale coking coal testing. Another large
drilling programme was commenced in 2003 and the culmination of all this work saw ML80110 (Curragh North)
granted on 22nd July 2004.
Systematic drilling programs (ongoing), conducted since the mine was commissioned, have resulted in
thousands of holes being drilled in the Curragh Lease area.
In the last few years exploration focus has included business as usual open-cut drilling but also an increasing
focus on underground resource evaluation. The underground exploration program has included seismic 2D &
3D surveys and core drilling for gas, geotech, coal quality and spontaneous combustion evaluation. Additional
exploration has included permeability and hydrological assessment.
Page 21 of 118
6 Geological Setting, Mineralization and Deposit
6.1 Regional, Local and Property Geology
Curragh is situated within the Permo-Triassic aged Bowen Basin in Eastern Australia, which covers
approximately 16 million hectares. Its physiographic make-up consists of lowlands, flood plains as well as
rugged plateaus and ridges. The main lithological units derive from continental and marine sedimentation with
limited volcanic and intrusive rocks. The principal Resources are primarily large coal fields and secondarily
natural gas.
The geological setting of the property itself consists of sediments of the Rangal Coal Measures and Burngrove
Formation, both of Permian age which outcrop on the property. These units underlie alluvial Quaternary cover
and minor areas of Tertiary sediments. Alluvial sediments typically have an average thickness of 10 to 15
metres, with locations of up to 30 metres of sand, clay and gravel in northern areas.
The Yarrabee Tuff marker coincides with the present lower limit of Resource estimate. Figure 6-1 shows the
typical stratigraphic column that applies to the property. Five main coal seams groups, primarily of metallurgical
quality with some thermal quality coals, are mined at Curragh, as listed below:
●
●
●
●
●
Mackenzie
and Pisces seams
The Burngrove Formation typically has thick interbedded coal and tuff beds. This coal is typically high ash and
is not included in either the Resources or Reserves.
The structural environment at Curragh can be complex with the observed seam deformation the result of thrust
faulting from the northeast with fault throws up to 30 m. Structural thickening can occur where thrust faults
cause affected seams to be repeated, but in most cases the duplicated seams are not included in the Resource
estimation, although such repeats of coal are often mined and included in the Resource estimation if required.
Thrust faulting can also result in barren areas, where seams have been faulted out. North-south and east-west
trending normal faults also occur but are less common than thrust faulting. The structural geology within the
Resource adds some complexity to the project, as such the mine employs a strong geotechnical program to
manage geotechnical risks.
The major structure that limits mining at Curragh North is the Jellinbah Fault which trends in a northwest,
southeast direction with throw of several hundred metres and various splays of lesser throw (10 to 20m).
Page 22 of 118
Figure 6-1: Blackwater Group Stratigraphic Sequence
6.2 Mineralization
The generalized stratigraphic columnar section in Figure 6-1 demonstrates the vertical relationship of the
principal coal seams and rock formations at Curragh. The property, as in the Bowen Basin as a whole, does
not contain any signs of metamorphic activity; the prevailing lithology is sedimentary rocks with a few igneous
intrusions. The depth of host rock weathering at Curragh is on average in the order of 10 to 15 metres.
6.3 Coal Quality
Coal seams at Curragh are mainly of the low volatile metallurgical grade with a secondary middling thermal
product. Sulphur and phosphorus content is generally low. Insitu ash is in the range of 20% thus necessitating
beneficiation to meet market requirements, which in this case is accomplished through a coal handling and
preparation plant. Metallurgical coal products range from 7-10% product ash.
Page 23 of 118
6.4 Deposits
Figure 6-2 shows a 3D view of the geometry of the coal horizons at Curragh. In portions of the property, a
number of these seams merge to form a single package, without any interburden strata. In the central and
some of the northern part of the property the Aries and Castor seams coalesce into one coal stratum that is
referred to locally as the “Mammoth” seam. The Mammoth Seam is analogous to the Leichardt seam
commonly found in mining operations further north. At Curragh North the Pollux, Orion and Pisces seams
coalesce into one unit which is correctly referred to as the Mackenzie seam, but in some contexts has been
referred to as the “Pisces” seam even though the true Pisces seam is only one of the constituent seams of the
Mackenzie assemblage. The Mackenzie seam is analogous to the Vermont seam which is commonly found in
mining operations further north.
Figure 6-2: Trends in Seam Splitting and Coalescing from North to South
Figure highlights a North-South section from the current geological model through Curragh properties. Seams
of economic interest occur at depths ranging from 15m from surface down to as deep as 400m in the deepest
part of the property.
Interburden host rock typically consists of regular intercalations of siltstones and mudstones, with layers of
variable thicknesses. The rock and coal beds dip gently to East direction at an angle of approximately 3
degrees, with some sections displaying dip angles as high as 10 degrees in association with structural
deformation.
In general, only minor instances of intrusive material have been intercepted in drill holes or mined during
production at the Curragh Mine.
Igneous activity is more prevalent at Curragh North although these are not a major impact on operations. The
intrusive includes rare dykes occurring at the northern end of Curragh North deposit. There was a larger
igneous intrusion approximately 500 metres long and 100 metres wide that impacted the Resources of the
Aries, Castor and Mackenzie seams. Mining has proceeded past the area of impact of this intrusion.
Page 24 of 118
Curragh has been subjected to moderate localized faulting more intense in southern areas that has resulted
in vertical slips (displacements) as high as 20 metres, along with variations in seam thickness. Seam
duplication is also common as a result of the thrust faulting but in most cases the duplicated seams are not
included in the Resource estimation, although such repeats of coal are often mined.
The principal geostructural feature is the Jellinbah regional thrust fault located east of the mine outside the
Resource area. The structural geology within the Resource adds some complexity to the project. The mine
employs a strong geotechnical program to manage geotechnical risks.
Figure 6-3: North South Section through Curragh Tenements showing major seams
Page 25 of 118
7 Exploration
7.1 Nature and Extent of Exploration
The Curragh geological drilling database contains over 19,000 holes drilled over a long history of exploration
and development in the Curragh area. Various drilling programmes were conducted by the Queensland
Department of Minerals and Energy (previously known as Mines Department) during the period 1966-76 over
a large area between the Capricorn Highway and the Mackenzie River. The area was within the Department
of Mines RA56D. From 1976 to 1978 detailed drilling and coal analysis was carried out by officers of the
Geological Survey of Queensland on behalf of the SECQ. During this time the SECQ (SECQ’s interest is now
vested in Stanwell was granted Authority to Prospect (ATP) 217C. Extensive exploration of the Curragh area
within ATP 217C occurred between 1976 and 1978.
In 1982 further exploration was carried out by Geological Survey of Queensland on behalf of SECQ in the
Curragh East area. The Curragh lease (ML1878) was granted on 27 May 1982 and that part of the area was
relinquished from ATP 217. A significant exploration programme was undertaken in 1993 to provide coal
quality information and additional structural data for Curragh East. Four hundred holes were drilled, comprising
320 open holes with geophysical logs and 80 partially cored holes.
In 1996 a large exploration programme was undertaken at the northern end of MDL162, and this work provided
the basis for the Pisces Project feasibility study (Curragh North). In 2001 twenty partially cored holes were
drilled in this northern part of MDL162 to provide samples for bench scale coking coal testing. Another large
drilling programme was commenced in 2003 and the culmination of all this work saw ML80110 (Curragh North)
granted on 22nd July 2004.
Systematic drilling programs (ongoing), conducted since the mine was commissioned, have resulted in
thousands of holes being drilled in the Curragh Lease area.
In the last three years, several strategic holes have been drilled on an ongoing basis to investigate potential
for future underground mining. Geotech, gas, coal quality and spontaneous combustion samples have been
collected as part of this program.
Some geophysical techniques including seismic and aeromagnetics have supplemented the geological
understanding. This work is discussed in the next sections.
7.1.0 Non-Drilling Exploration
Geophysical techniques have been used to supplement the understanding of the Curragh Resource. This work
has been to guide overall understanding of intrusions, seam continuity and sub-surface faults.
The mains surveys are shown in Figure 7-1. The surveys that have been conducted are:
●
tenements to acquire magnetic and radiometric data (31.5km’s of line at 100m spacing).
●
seam splits and sub-surface structure.
●
seam continuity adjacent to Pit S and Pit U
●
operations
●
open-cut operations
●
south of Curragh North operations
Page 26 of 118
Aero-magnetic data has indicated that Resources are largely intrusion free except for one large “plug” body
which was picked up in aero-magnetics and has since been mined out.
The 2D and 3D survey has been very successful to understand larger scale structures that are difficult and
expensive to define with drilling. The seismic data indicated that Resources are largely continuous with some
disruption due to faulting. The Phase I seismic survey was successful in locating the Jellinbah fault, a major
regional fault and to define seam splitting in areas of sparse drilling.
The 3D survey was particularly successful in precisely defining faults and split lines is an
area of underground mining interest.Figure 7-1: Geophysical Surveys
7.1.1 Drilling Exploration
The Curragh deposit has a long history of exploration with over 19000 holes drilled in its properties (Figure 8).
Of these approximately 15,700 holes are deemed suitable for use in the geological model. The remainder have
been excluded due to not meeting strict data quality requirements. Table 7.1 shows the Curragh Property
drilling statistics as used in the Curragh 2023 geological model.
Page 27 of 118
●
●
●
Approximately 7,500 of the 15,700 holes lie in areas of declared coal Resources with the remainder in mined
out areas or areas of Burngrove Formation only. Most of these boreholes are non-coring (open holes), with a
portion as cored holes for coal quality and washability, geotechnical, gas or fugitive emissions purposes.
Predominantly all holes are logged by downhole wireline geophysical techniques.
Table 7.1: Drill hole Statistics
Hole Type
Metres
Number of Holes
Chip
Core
264,544
3217
Total
All drilling and sampling are conducted in accordance with the Curragh Geology Planning system which sets
out standards for acquiring exploration data. A subset of these procedures is shown in Table 7.2.
Table 7.2: Selected Exploration and Data management procedures
Procedure Name
CPS PLN 2.0 Geology System Plan
CPS PRO 2.3 Exploration Planning
CPS PRO 2.4 Exploration Execution
CPS WI 2.51 Drill Site Management
CPS PRO 2.5 Exploration Data Collection
CPS WI 2.21 Establishing Exploration Requirements
CPS WI 2.22 Guide to Exploration Planning
CPS WI 2.23 Core Logging and Sampling
CPS WI 2.24 Minimum Borehole Logging Requirements
CPS WI 2.26 Sampling for Coal Quality Analysis
The procedures specify the processes of planning through business stakeholder engagement through to final
acquisition, validation and safe storage of geological data and adhere to various industry standards where
applicable.
All logging and data management is conducted by qualified geologists. In recent years all geological data is
captured in specialist logging software and imported into the Company’s geological database (Geobank) after
rigorous data validation. The database is maintained by company IT professionals and administered by
company geological staff.
Drilling comprises short term operational drilling designed to reduce geological uncertainty in short-term
planning and long-term strategic drilling to allow for assessment of future mining options.
The primary drilling techniques are chip drilling (non-core) and coring. Chip holes provide ground up (“chip”)
samples that are returned to surface by air or water which provides lithology information down the hole normally
logged at 1m intervals. Down hole geophysics provides detailed lithology and coal thickness data in these
holes for subsequent modelling.
Page 28 of 118
Downhole wireline techniques include calliper (borehole diameter), gamma, density, sonic and borehole
verticality. In some cases optical or acoustic televiewers are run to provide more detailed bedding and defect
orientation data.
Core allows for a more detailed understanding of rock characteristics including lithology fabric, rock defects,
hardness and provides physical intact samples for subsequent laboratory testing. Cored holes of either 63 or
100mm diameter are logged, photographed and sampled by a qualified geologist into company geological
database. Cored holes maybe partially cored or fully cored dependent on the purpose of the hole and samples.
Chip samples may be collected and tested for coal oxidation. Core samples are more common and maybe
taken for several reasons:
●
●
●
●
●
Figure 7-2: Curragh Boreholes as of 31 August 2023 used in Resource Estimate
Page 29 of 118
Large core holes (200mm) are generally drilled at the start of project evaluation to provide detailed sizing and
coal quality and coke characterisation data and form a small part of the Curragh coal quality database. More
frequent are cored holes of either 63mm or 100mm diameter. These holes are logged, photographed and
sampled by a qualified geologist. The sample test data provides information on coal quality, geotechnical, gas,
reactive ground and spontaneous combustion characteristics in addition to data to estimate product yield.
Figure 7-3 shows the sample locations by main sample type.
Figure 7-3: Sample Locations by PrimarySample Type
Page 30 of 118
7.1.2 Drilling, Sampling and Recovery Factors
A number of drilling, sampling and recovery factors can materially affect the accuracy and reliability of results.
These factors are routinely reviewed as part of validation and estimation processes.
Drillhole spacing varies across Curragh properties from as low as 20m to as high as 1-2km. In years prior to
mining, infill drilling occurs with drill hole spacing decreased to the order of 50-100m for chip holes. Cored
sample drilling spacing prior to mining is generally less than 400m.
Core Recovery - The diameter of exploration cores is generally between 50mm and 100 mm, with a few larger
diameter (200 mm) holes used to obtain samples for simulated degradation, washing, combustion, and coking
practices. A minimum core recovery of 90% is used as a criteria for acceptance or rejection of a sample for
subsequent analysis. If a sample fails those criteria, the sample is re-drilled or rejected from subsequent
modelling.
Drillhole Collar Survey – All borehole locations and elevations since the mid-1980’s have been surveyed by a
registered mine surveyor registered under the Surveyors Act 2003. Boreholes are surveyed in a local mine
grid which is within a close approximation to Australian Geodetic Datum (ADG84). Some historical holes drilled
in several decades ago have lower confidence on survey accuracy. Where there is doubt these holes are
excluded or when included tend to lie in lower category resource areas e.g. Inferred
Downhole Verticality - Recent holes in last 5-10 years have been surveyed by downhole verticality tools that
give the holes dip and dip direction at frequent intervals down the hole. Holes prior to this were not surveyed
with verticality tools and it is assumed that these holes are vertical. For Resource and reserve estimation, this
assumption is not material.
7.1.3 Drilling Results and Interpretation
Coronado properties have been drilled at suitable density and sufficient samples have been collected to allow
for construction of a detailed geological model. In areas of wider drillhole spacing, the uncertainty of this model
increases. This uncertainty is captured in Resource confidence polygons in the Resource estimation process
and reported accordingly as Measured, Indicated or Inferred Resources. Only Measured or Indicated
resources are considered for conversion into mineral reserves.
Figure 7-2 shows all boreholes used in the 2023 Resource model and Resource estimate. The holes have
been used to generate a geological model, through which a geological section is presented in Figure. Holes
in Burngrove Formation in south-western Mineral Development Leases are not shown as the coal in the
Burngrove Formation is not included in the Resources or Reserves.
Curragh has extensive drilling. The results over the years have shown that the seams are generally shallow
dip (less than 5°), however in fault and deformation zones, steep dips occur locally. Seam deformation has
resulted principally from thrust faulting from the north-east resulting in seam displacements up to 20 metres
vertically. North-south and east-west normal faults are less common and some of these have a strike-slip
component.
Fault deformation has resulted in seam thinning, thickening and barren areas which is more prevalent in south.
The Jellinbah fault occurs on the eastern side of the Curragh North mining lease. The fault is a thrust fault
upthrown on the eastern side by several hundred metres . This is a physical boundary to coal mining.
Coal quality sample data indicates that metallurgical coal products (low-vol coking and PCI) can be produced
from all seams. A secondary thermal product is also produced after beneficiation. A much smaller proportion
of seams in some areas are only suitable for thermal coal. The metallurgical coal rank (impacts coke strength)
slowly decreases with increasing depth to the east.
Coal quality models are well supported by historical production with low vol coking, PCI and thermal coal
produced at Curragh for several decades. Coal quality is not expected to materially change in the life of mine
plan.
Page 31 of 118
7.2 Hydrology
Curragh Mine is in the Mackenzie River sub-basin of the Fitzroy River Basin. Mackenzie River forms at the
confluence of the Nogoa and Comet rivers approximately 66 km upstream of Curragh Mine and joins with
Dawson River to form Fitzroy River approximately 250 km downstream.
Rainfall is relatively low, with an average of 635 mm of annual precipitation, and consequently interruptions
seldom occur in the mining operations due to severe weather. Most rain occurs in summer.
Water bearing units at Curragh Mine comprise:
●
Duaringa/Emerald Formation of Tertiary age
●
●
fractured sediments
of the Burngrove Formation including coal seams and sandstone units.
The aquitard units of low to very low permeability at Curragh Mine comprise:
●
●
●
Measures
●
have very low primary porosity (typically void spacing in the sandstones is cemented by clay providing
poor interconnection of void space).
Large north-west trending faults provide potential barriers to groundwater flow.
Wetlands and swamps in the area are not believed to be materially reliant on groundwater and are unlikely to
be affected by drawdown. Current approved Environmental Management Plans ensures any environmental
impacts are minimised.
The potential for acid mine drainage issues is low.
Curragh has a large network of hydro bores (Figure 7-4).
Curragh has a groundwater monitoring procedure as part of its Environmental Management System to
characterize groundwater systems and monitor any potential impacts on groundwater over time and to meet
its obligations under Environmental Authorities. Monitoring locations are installed in Alluvium, Rangal Coal
Measure and the underlying Burngrove Formation and additionally Observation bores adjacent to
infrastructure such as dams and levees.
Compliance and Reference bores are sampled bi-annually including the recording of depth to water, physical
chemical parameters as well as the collection and submission of a sample to NATA accredited laboratory for
analysis. Sampling is undertaken by a suitably trained and competent person in accordance with Australian
Standard AS/NZS 5667.11:1998 – Water Quality Sampling.
Future underground mining requires a rigorous understanding of groundwater systems. In 2023, a network of
monitoring bores and Vibrating Wire Piezometers (VWP) was installed in preparation for underground mining.
All bores have dataloggers with satellite telemetry. The new boreholes are tested monthly for insitu parameters,
and a standard suite of laboratory tests conducted by NATA accredited laboratory.
Detailed hydrological modelling has been carried out in order to obtain approvals from the environmental
authorities for existing operations and new modelling is being undertaken for future underground mining
operations.
Page 32 of 118
Figure 7-4 Hydro Monitoring Sites
Page 33 of 118
7.3 Geotechnical Data
Geotechnical data is collected to facilitate geotechnical assessments, analysis and design, with the aim of
ensuring that the geotechnical risks encountered at Curragh are appropriately understood and managed.
Geotechnical ground models are the basis on which geotechnical assessments, analysis and design is
completed and need to be informed by a level of data appropriate to the design phase. The geotechnical
ground model is comprised of the: Geological Model, Structural Model, Material Properties Model and
Hydrogeological Model.
The development of geotechnical ground models to support mine planning is informed by operational data (i.e.
geological mapping, survey pick-ups, rock mass defect logging etc.) and exploration data (i.e. drill hole data,
down hole geophysical data, seismic surveys, piezometers etc.).
The Curragh Safety Health Management System (Curragh SHMS) provides instructions on how geotechnical
risks at Curragh are identified, reported, and managed. The Curragh Planning System (CPS) is used in
conjunction with the Curragh SHMS and provisions under the relevant SHMS documents, to define the data
requirements, and associated data management systems, necessary to inform geotechnical assessments,
analysis and design.
7.3.0 2022 to 2023 Geotechnical Logging and Material Testing
Curragh has undertaken geotechnical logging, sampling and material testing of select boreholes to help
support the on-going development of the geotechnical ground models.
7.3.1 2022 Geotechnical Borehole Locations
A total of twenty-four (24) sites in Curragh Main and fourteen (14) sites in Curragh North were selected for
geotechnical logging, sampling and material testing in 2022 (refer to Table 7.5, Table 7.6, Figure 7-4 and
Figure 7-5).
These sites are comprised of geotechnically logged and sampled HQ sized diamond core boreholes.
7.3.2 2023 Geotechnical Borehole Locations
A total of eighteen (18) sites in Curragh Main and twenty-four (24) sites in Curragh North (including four (4)
boreholes within MDL162) were selected for geotechnical logging, sampling and material testing in 2023 (refer
to Table 7.7 ,Table 7.8, Figure 7-4 and Figure 7-5).
These sites comprised of HQ sized diamond core geotechnically logged and sampled boreholes.
Four (4) of these boreholes were selected for further diagnostic fracture injection tests (DFIT) and drill stem
tests (DST) across the Mammoth and Mackenzie coal seams and within the Mackenzie Interburden as part of
the Curragh Gas Project.
7.3.3 Geotechnical Borehole Logging, Sampling and Material Testing
Geotechnical logging was undertaken using the Australian coal industry standard – ACARP Project CoalLog
v3.1 and in line with Australia Standards for Geotechnical Site Investigations (AS 1726 2017).
Geotechnical samples were collected and recorded by trained and competent geologists, in line with Curragh
processes and work instructions for the appropriate selection, storage, handling and transport of samples. The
selection of samples for testing and determination of associated testing parameters was undertaken by
appropriately qualified geotechnical engineers.
Page 34 of 118
7.3.4 On-Site Geotechnical Testing
7.3.4.1 Point Load Testing
Point Load Testing (PLT) on selected HQ core were conducted on-site by suitably trained and competent
geologists. PLT was completed using a calibrated PLT Model 6510 from HMA Geotechnical and in line with
AS 4133.4.1-2007.
7.3.4.2 Immersion Testing
Immersion testing on selected HQ core was conducted on-site by suitably trained and competent geologists
in line with CPS.
7.3.4.3 Geotechnical Laboratory Testing
Geotechnical laboratory testing was undertaken by National Association of Testing Authorities (NATA
accredited laboratories in line with Australian Standards (AS) and/or International Standards (ASTM) (Table
7.4).
A summary of the geotechnical laboratory testing completed is provided in Table 7.4.
Table 7.4 Geotechnical Laboratory Testing: Australian Standards (AS) International
Standards (ASTM) and No. of Completed Tests 2022-23
Test
Standard
No. of Completed Test
Uniaxial Compressive Strength
Rock Moisture Content
AS 4133.4.2.2
AS 4133.1.1.1
298
Uniaxial Compressive Strength & Deformation
Test
Rock Moisture Content
AS 4133.4.3.2
AS 4133.1.1.1
204
Direct Shear Test
ASTM D5607
59
Strength of Rock Material in Triaxial
Compression
ASTM D7012
7
Slake Durability Index Test
AS 4133.3.4
177
Indirect Tensile Strength
ASTM D3967
185
Page 35 of 118
Hole ID
Completio
n Year
Lease
Easting
Northing
RL
Survey
Accuracy
Total
Depth (m)
Drilling
Completion
Date
Samples Sent to External
Laboratory for
Geotechnical Testing
Core
Photographs
Downhole
Geophysics
Acoustic Scanner
(ATV)
In Field Point Load Data
Collected
In Field Immersion
Tests
DFIT &
DST
Testing
18458C
2022
ML1878
690390.51
7396253.52
165.01
Surveyed
102.00
31/07/2022
Yes
Yes
Yes
Yes
No
No
No
18459C
2022
ML1878
689591.47
7396454.12
168.04
Surveyed
42.00
4/08/2022
Yes
Yes
Yes
No
No
No
No
18464C
2022
ML1878
689932.82
7396107.03
169.08
Surveyed
89.89
22/08/2022
Yes
Yes
Yes
Yes
No
No
No
18435C
2022
ML80110
692614.98
7416655.02
138.16
Surveyed
114.07
9/04/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18436C
2022
ML80110
692469.32
7416310.65
133.82
Surveyed
99.05
11/04/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18437C
2022
ML80110
692719.34
7416450.32
130.98
Surveyed
120.00
12/04/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18438C
2022
ML80110
692565.23
7416469.16
135.41
Surveyed
101.90
15/04/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18439C
2022
ML80110
692622.33
7416186.45
129.56
Surveyed
114.20
16/04/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18440C
2022
ML80110
692761.08
7416738.6
138.65
Surveyed
132.19
18/04/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18441C
2022
ML80110
692747.29
7418700.75
113.59
Surveyed
162.42
1/05/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18442C
2022
ML80110
692779.65
7418921.44
129.75
Surveyed
120.00
4/05/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18443C
2022
ML80110
692774.31
7418582.18
112.65
Surveyed
162.28
17/05/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18444C
2022
ML80110
692793.91
7418478.63
113.96
Surveyed
162.30
27/05/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18445C
2022
ML80110
692730.09
7418791.05
112.58
Surveyed
162.08
29/05/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18446C
2022
ML80110
692610.78
7418442.73
51.63
Surveyed
78.17
6/06/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18447C
2022
ML80110
692631.67
7418307.46
54.18
Surveyed
78.05
8/06/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18448C
2022
ML80110
692898.38
7418635.84
134.42
Surveyed
132.19
11/06/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18449C
2022
ML80110
692875.79
7418775.21
133.62
Surveyed
132.58
12/06/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18450C
2022
ML80110
692790.76
7418284.21
98.72
Surveyed
138.08
21/06/2022
Yes
Yes
Yes
Yes
Yes
Yes
No
18479C
2022
ML80110
694200.22
7416070.65
139.53
Surveyed
324.54
26/09/2022
Yes
Yes
Yes
Yes
Yes
No
No
18481C
2022
ML80110
693370.39
7420976.07
124.62
Surveyed
300.89
8/10/2022
Yes
Yes
Yes
Yes
Yes
No
No
18482C
2022
ML80110
692470.73
7424159.36
124.94
Surveyed
214.00
11/11/2022
Yes
Yes
Yes
Yes
No
No
No
18483C
2022
ML80110
692051.77
7415848.3
128.28
Surveyed
126.12
15/11/2022
Yes
Yes
Yes
Yes
Yes
No
No
18484C
2022
ML80110
691788.64
7415674.19
126.39
Surveyed
120.03
29/11/2022
Yes
Yes
Yes
Yes
Yes
No
No
Table 7.5 2022 Curragh North Geotechnical Drilling
Page 36 of 118
Hole ID
Completio
n Year
Lease
Easting
Northing
RL
Survey
Accuracy
Total
Depth (m)
Drilling
Completion
Date
Samples Sent to External
Laboratory for
Geotechnical Testing
Core
Photographs
Downhole
Geophysics
Acoustic Scanner
(ATV)
In Field Point Load Data
Collected
In Field Immersion
Tests
DFIT &
DST
Testing
18421C
2022
ML8008
6
693196
7400988.68
156.49
Surveyed
95.09
15/03/2022
Yes
Yes
Yes
Yes
No
No
No
18422C
2022
ML8008
6
693166.01
7400596.12
156.34
Surveyed
101.3
17/03/2022
Yes
Yes
Yes
Yes
No
No
No
18423C
2022
ML8008
6
694001.47
7400767.62
161.69
Surveyed
96
19/03/2022
Yes
Yes
Yes
Yes
No
No
No
18431C
2022
ML8008
6
693829.43
7401050.63
156
Surveyed
95
26/03/2022
Yes
Yes
Yes
Yes
No
No
No
18433C
2022
ML8008
6
693694.72
7400778.78
157.83
Surveyed
95
28/03/2022
Yes
Yes
Yes
Yes
No
No
No
18434C
2022
ML8008
6
693713.19
7400530.49
161.08
Surveyed
83
31/03/2022
Yes
Yes
Yes
Yes
No
No
No
18451C
2022
ML8008
6
693498.69
7400103.62
160.74
Surveyed
101
15/07/2022
Yes
Yes
Yes
Yes
No
No
No
18452C
2022
ML8008
6
693718.94
7400326.65
161.76
Surveyed
95
17/07/2022
Yes
Yes
Yes
Yes
No
No
No
18453C
2022
ML8008
6
693458.79
7400402.16
159.13
Surveyed
95
19/07/2022
Yes
Yes
Yes
Yes
No
No
No
18454C
2022
ML8008
6
693825.21
7400208.22
165.43
Surveyed
95
23/07/2022
Yes
Yes
Yes
Yes
No
No
No
18455C
2022
ML8008
6
694044.15
7400087.91
166.04
Surveyed
95
26/07/2022
Yes
Yes
Yes
Yes
No
No
No
18456C
2022
ML8008
6
694283.77
7400116.8
167.57
Surveyed
108.07
28/07/2022
Yes
Yes
Yes
Yes
No
No
No
18460C
2022
ML8008
6
694640.9
7401615.1
158.82
Surveyed
134.42
13/08/2022
Yes
Yes
Yes
Yes
No
No
No
18461C
2022
ML8008
6
694546.33
7399913.2
169.83
Surveyed
120.42
14/08/2022
Yes
Yes
Yes
Yes
No
No
No
Table 7.6 2022 Curragh Main Geotechnical Drilling
Page 37 of 118
Hole
ID
Completion
Year
Lease
Easting
Northing
RL
Survey
Accuracy
Total
Depth (m)
Drilling
Completion
Date
Samples Sent to External
Laboratory for
Geotechnical Testing
Core
Photographs
Downhole
Geophysics
Acoustic Scanner
(ATV)
In Field Point Load Data
Collected
In Field Immersion
Tests
DFIT &
DST
Testing
18491
C
2023
ML8011
0
692356.34
7414854.51
128.08
Surveyed
182
25/02/2023
Yes
Yes
Yes
No
Yes
No
No
18492
C
2023
ML8011
0
692752.55
7415224.32
127.55
Surveyed
174.07
4/03/2023
Yes
Yes
Yes
Yes
Yes
Yes
Yes
18493
C
2023
ML8011
0
693709.67
7416081.23
140.82
Surveyed
300.07
8/03/2023
Yes
Yes
Yes
Yes
Yes
Yes
Yes
18494
C
2023
ML8011
0
693205.41
7414989.29
125.42
Surveyed
228.04
19/03/2023
Yes
Yes
Yes
Yes
Yes
Yes
Yes
18532
C
2023
ML8011
0
693906.13
7418104.2
175.09
Surveyed
366.09
11/05/2023
Yes
Yes
Yes
Yes
Yes
Yes
Yes
18533
C
2023
ML8011
0
693473.03
7418626.8
155.24
Surveyed
300.06
20/05/2023
Yes
Yes
Yes
Yes
Yes
Yes
Yes
18536
C
2023
ML8011
0
692944.55
7418117.61
133.62
Surveyed
222.45
20/05/2023
Yes
Yes
Yes
Yes
Yes
Yes
No
18537
C
2023
ML8011
0
692800.84
7419347
130.29
Surveyed
228
4/06/2023
Yes
Yes
Yes
Yes
Yes
Yes
Yes
18538
C
2023
ML8011
0
693338.4
7415532.98
129.64
Surveyed
252.46
10/06/2023
Yes
Yes
Yes
Yes
Yes
Yes
Yes
18542
C
2023
ML8011
0
692858.85
7420123.11
127.31
Surveyed
252
18/06/2023
Yes
Yes
Yes
Yes
Yes
Yes
Yes
18546
C
2023
ML8011
0
693446.66
7418113.15
161.87
Surveyed
289.9
11/07/2023
Yes
Yes
Yes
Yes
Yes
Yes
Yes
18573
C
2023
ML8011
0
691999.8
7415584.79
123.2
Surveyed
57.2
22/09/2023
Yes
Yes
Yes
Yes
No
No
No
18587
C
2023
ML8011
0
691843.27
7420307.70
8
126.97
Surveyed
180.28
1/11/2023
Yes
Yes
Yes
Yes
No
No
No
20808
C
2023
ML8011
0
692913.66
7415971.49
132.56
Surveyed
201.53
28/03/2023
No
Yes
Yes
No
No
No
Yes
22058
C
2023
ML8011
0
692836.76
7414697.05
126.59
Surveyed
204.48
27/03/2023
Yes
Yes
Yes
Yes
Yes
No
Yes
22059
C
2023
ML8011
0
693173.49
7416270.35
134.96
Surveyed
258.28
18/04/2023
Yes
Yes
Yes
Yes
Yes
Yes
Yes
22062
C
2023
ML8011
0
692361.79
7415473.77
127.72
Surveyed
174.18
25/04/2023
Yes
Yes
Yes
Yes
Yes
Yes
Yes
22063
C
2023
ML8011
0
693304.56
7419168.77
143.87
Surveyed
282.09
8/03/2023
Yes
Yes
Yes
Yes
Yes
Yes
Yes
22089
2023
ML8011
0
693214.83
7419556.88
139.66
Surveyed
284.00
20/06/2023
No
No
Yes
No
No
No
Yes
22101
C
2023
ML8011
0
692447.22
7423352.68
166.11
Surveyed
329.9
26/08/2023
Yes
Yes
Yes
Yes
Yes
Yes
No
22102
C
2023
MDL162
694532.01
7417576.79
143.84
Surveyed
348.36
16/09/2023
Yes
Yes
Yes
Yes
Yes
Yes
No
22103
C
2023
MDL162
694864.6
7416659.39
144.42
Surveyed
402.08
25/09/2023
Yes
Yes
Yes
Yes
Yes
Yes
No
22104
C
2023
MDL162
694681.51
7415806.01
144.08
Surveyed
375.25
5/10/2023
Yes
Yes
Yes
No
Yes
Yes
No
22105
C
2023
MDL162
694729.23
2
7414860.30
9
130.00
Surveyed
345.42
17/10/2023
Yes
Yes
Yes
Yes
Yes
Yes
No
22100
C
2023
ML7000
08
691864.2
7413476.33
128.11
Surveyed
54.23
24/08/2023
Yes
Yes
Yes
Yes
Yes
Yes
No
Table 7.7 2023 Curragh North Geotechnical Drilling
Page 38 of 118
Hole
ID
Completion
Year
Lease
Easting
Northing
RL
Survey
Accuracy
Total
Depth (m)
Drilling
Completion
Date
Samples Sent to External
Laboratory for
Geotechnical Testing
Core
Photographs
Downhole
Geophysics
Acoustic Scanner
(ATV)
In Field Point Load Data
Collected
In Field Immersion
Tests
DFIT &
DST
Testing
18485
C
2023
ML8008
6
695027.24
7403034.28
152.99
Surveyed
144.24
26/01/2023
Yes
Yes
Yes
No
Yes
No
No
18486
C
2023
ML8008
6
693975.49
7401275.99
159.46
Surveyed
96
30/01/2023
Yes
Yes
Yes
Yes
No
No
No
18487
C
2023
ML8008
6
693807.37
7399914.9
163.01
Surveyed
108.04
11/02/2023
Yes
Yes
Yes
Yes
No
No
No
18488
C
2023
ML8008
6
693956.08
7399572.65
163.94
Surveyed
79
15/02/2023
Yes
Yes
Yes
Yes
Yes
No
No
18489
C
2023
ML8008
6
695229.39
7401176.59
156.74
Surveyed
126
17/02/2023
Yes
Yes
Yes
No
Yes
No
No
18490
C
2023
ML8008
6
694299.11
7399473.99
166.3
Surveyed
83.3
20/02/2023
Yes
Yes
Yes
Yes
Yes
No
No
18504
C
2023
ML8008
6
694569.07
7400317.27
168.55
Surveyed
102
4/04/2023
Yes
Yes
Yes
Yes
No
No
No
18510
C
2023
ML8008
6
694770.5
7399550.52
172.43
Surveyed
138
14/04/2023
Yes
Yes
Yes
Yes
No
No
No
18524
C
2023
ML8008
6
693834.83
7399742.35
162.31
Surveyed
101.98
27/04/2023
Yes
Yes
Yes
Yes
No
No
No
18541
C
2023
ML8008
6
694178.53
7401765.46
165.73
Surveyed
108
16/06/2023
Yes
Yes
Yes
No
No
No
No
18543
C
2023
ML8008
6
694252.83
7399857.19
167.91
Surveyed
96
22/06/2023
Yes
Yes
Yes
Yes
No
No
No
18544
C
2023
ML8008
6
694161.57
7399475.41
166.84
Surveyed
126.18
26/06/2023
Yes
Yes
Yes
Yes
No
No
No
18551
C
2023
ML8008
6
694672.81
7399322.73
176.23
Surveyed
150.01
23/07/2023
Yes
Yes
Yes
Yes
No
No
No
18552
C
2023
ML8008
6
694397.71
7399093.68
177.81
Surveyed
162
30/07/2023
Yes
Yes
Yes
Yes
No
No
No
18554
C
2023
ML8008
6
694377.74
7399298.84
176.66
Surveyed
143.8
3/08/2023
Yes
Yes
Yes
Yes
No
No
No
18555
C
2023
ML8008
6
694907.44
7399849.69
172.6
Surveyed
150
10/08/2023
Yes
Yes
Yes
Yes
No
No
No
18560
C
2023
ML8008
6
694348.4
7400297.28
167.85
Surveyed
114
19/08/2023
Yes
Yes
Yes
Yes
No
No
No
18561
C
2023
ML8008
6
694583.49
7400531.59
167.64
Surveyed
132.07
22/08/2023
Yes
Yes
Yes
Yes
No
No
No
18562
C
2023
ML8008
6
694724.28
7402251.06
152.6
Surveyed
156
25/08/2023
Yes
Yes
Yes
Yes
No
No
No
Table 7.8 2023 Curragh Main Geotechnical Drilling
Page 39 of 118
Figure 7-4 Curragh Main Sample Sites
Page 40 of 118
Figure 7-5 Curragh North Sample Sites
Page 41 of 118
8 Sample Preparation, Analysis and Security
8.1 Prior to Sending to the Lab and Lab Procedures
Handling of coal and rock samples at Curragh follows standard procedures used in the coal mining industry
with regard to preparation, analysis and security. Likewise, laboratory tests are performed according to
standards utilized internationally. In this instance, Curragh’s standards are based upon the Australian
Standards which are stated as applicable for this analysis.
Curragh has used an independent laboratory ALS Coal (formerly ACIRL) since 1983, now located at 478
Freeman Rd, Richlands QLD 4077 for all exploration coal quality determinations. ALS is regularly
benchmarked against ISO 17025. by reputable organisations such as NATA.
The coal laboratory performs a specific workflow of testing that is compatible for testing of coking, thermal and
PCI coals. The testing comprises sample pre-treatment, raw coal quality analysis, washability and product
composite testing which is suitable for full beneficiation and market product characterization. This testing is
conducted under Australian and international standards samples including but not limited to those listed in
Table 8.1.
Table 8.1: Analytical Test Standards Numbers – Coal Quality
Analytical Test
Standard No
Ash
AS1038.3
Ash Fusibility
AS1038.15
Carbon
AS1038.15
Crucible Swelling Number
AS1038.12.1
Dilatometer
AS1038.12.3
Fixed Carbon
AS1038.3
Float/Sink Analysis
AS4156.1
Gieseler
AS1038.12.4.1
Hydrogen
AS1038.6.4
Moisture (residual)
AS1038.3
Moisture Holding Capacity
AS1038.17
Nitrogen
AS1038.6.4
Oxygen
AS1038.16
Phosphorus
BS1016.14
Relative Density
AS1038.21.1.1
Size Analysis
AS3881
Gross Calorific Value
AS1038.5
Total Moisture
AS1038.1
Total Sulfur
AS1038.6.3.3
Volatile Matter
AS1038.3
Ash Analysis
AS1038.14.3
Proximate Analysis
AS 1038
Geotechnical testing is conducted under Australian and international standards samples including but not
limited to those listed in Table 8.2. Geotechnical testing in last five years has been completed by Trilab Pty Ltd
at 362 Bilset Rd Geebung Qld 4034 or Strata Testing Services Pty Ltd at Unit 2, 77 Jardine Street Fairy
Meadow, N.S.W 2519 Australia
Page 42 of 118
Table 8.2: Analytical Test Standards Numbers – Geotechnical
Analytical Test
Standard No
Geotechnical Site Investigations
AS 1726 2017
Uniaxial Compressive Strength
AS 4133.4.2.2
Uniaxial Compressive Strength &
Deformation Test
AS 4133.4.3.2
Direct Shear Test
ASTM D5607
Strength Of Rock Material In Triaxial
Compression
ASTM D7012
Slake Durability Index Test
AS 4133.3.4
Rock Moisture Content
AS 4133.1.1.1
Atterberg Limits Test
AS 1289 2.1.1, 3.2.1, 3.3.1,
3.4.1
It is the opinion of the Qualified Person that samples are collected, dispatched, prepared, analysed and verified
adequately for subsequent Resource and Reserve evaluation and estimation.
9 Data Verification
9.1 Limitations of Verification
In a small percentage of drillholes, downhole geophysical records have been lost or not stored securely over
the mine life. In these instances, hole logs are reviewed for detailed logging as would be the practice if
geophysical logs were available and corrected by a geologist. As addition checks, seam thicknesses are
compared to surrounding data for consistency and excluded if in doubt.
Some of the historical drilling in deeper parts of MDL162 was not able to be fully validated due to lack of
original survey records and geologists written logs. Greater uncertainty is placed on this drilling data. However,
seismic data indicates the presence of strong reflectors that are aligned with boreholes records. Where data
is considered less reliable, the coal resources are classified as lower confidence resources i.e. Inferred.
9.2 Procedures of Qualified Person
The Qualified Person has a long history of working with Coronado geological data and production of geological
models and Resource estimates. The data verification process follows a detailed process for confirming the
accuracy of data upon which subsequent Resource and reserve estimation is based. This process includes:
●
●
●
●
●
●
●
●
9.3 Opinion of Qualified Person
In the opinion of the Qualified Person Mr Barry Lay, there has been sufficient data obtained through various
exploration and sampling programs and mining operations to support the geological interpretations of seam
structure and thickness for coal horizons situated on the Curragh property. The data seem to be of sufficient
quantity and reliability to reasonably support the Coal Resource and Coal Reserve estimates in this TRS.
Page 43 of 118
10 Mineral Processing and Metallurgical Testing
10.1 Testing Procedures and Sample Representatives
Laboratory testing procedures begin with a routine to ensure that each sample is representative of typical run-
of-mine feed and Coal Prep Plant (CPP) feed involving a process including drop shattering, dry sizing, wet
tumbling and wet screening of coal samples.
These pre-treated samples are analysed using a washability testing procedure which estimates the yield and
ash at various density cut points. This information is subsequently used in plant simulator (developed by A and
B Mylec Pty Ltd (A&B Mylec)) to estimate yield and product quality after applying plant and equipment
efficiency factors.
Test samples are collected as sufficient density to adequately represent the Resource at the level of reported
Resource and reserve classification. The testing provides sufficient information to determine the coal type (ie.
Coking, PCI or Thermal). There has historically been a good correlation between laboratory test results and
train or shipping results.
10.2 Laboratory Details
Curragh has used an independent laboratory now trading as ALS Coal (“ALS”) since 1983, now located at 478
Freeman Rd, Richlands QLD 4077 for all exploration coal quality determinations. ALS is accredited by NATA
NATA assesses that ALS has appropriately trained people, systems and controls. A NATA assessed coal
quality laboratory is certified against ISO/IEC 17025:2017.
Testing is conducted against appropriate Australian and international standards. The most common standard
numbers are as per Table 8.1.
10.3 Assumptions and Prediction
Resource recovery estimates are based on inputs of extensive coal quality borehole testing which provide run-
of-mine feed sizing, yield and expected product quality.
Expected processing product yields are estimated using coal borecore information and coal loss and dilution
assumptions validated through mine reconciliations. A process simulator developed by A&B Mylec applies
loss, dilution, and plant efficiency factors to derive final yield and quality information at each borehole datapoint.
This data is then modelled in Vulcan software for import to mine scheduling tools. There are no deleterious
elements that have not already been factored in reserves estimates and modelling that would have significant
impact on economic extraction.
10.4 Opinion of Qualified Person
Sufficient metallurgical testing data has been obtained through various exploration and sampling programs
and mining operations to reasonably support the Coal Resource and Coal Reserve estimates in this TRS.
Page 44 of 118
11 Mineral Resource Estimates
11.1 Assumptions, Parameters and Methodology
Coal Resources were estimated as of December 31, 2023.
Resology Pty Ltd independently created two geological models – one at the end of March 2023 and a second
model (sub-set) in August 2023 which included more recent drilling in underground mining areas. Each model
was constructed in MAPTEK Vulcan modelling software. Both models have been used for the estimation of
Coal Resources and Reserve estimates as discussed in the TRS.
The modelling process follows extensive validation of drillhole data. The model included drillholes available in
the company geological database at end of March 2023 for the larger model and August 2023 for the smaller
model.
The March 2023 geological model comprises a 50m grid cell model encompassing all of Curragh’s tenements
and seams within the Rangal Coal Measures only. Seams in the Burngrove Formation have not been modelled
or estimated. The August model comprised a 10m grid cell encompassing the underground potential areas
down dip of the open-cut at Curragh North.
The geological model s include multiple model types including seam roof and floor, base of quaternary, base
of weathering, raw quality, coking and thermal quality and simulated yield and product quality. At Resource
classification stage, thickness and ash cut-offs were applied. Resource classification methodology and
assumptions are discussed under section 11.4.
Coal Resource were calculated from a series of seam area polygons (split by resource confidence) against
insitu geological models. The density grid was derived from a seam ash vs relative density regression equation
with an adjustment for estimated insitu moisture (5.3%). MAPTEK RSVUTE software was used to calculate
the resource tonnes for each seam and each resource confidence category.
Mining surveyed face positions as of September 30, 2023, were used as a starting point of the estimate, with
three months of mining depletion (Sep 23– Dec 23) applied to give coal final Resource estimate at
December 31, 2023.
Page 45 of 118
11.2 Qualified Person’s Resource Estimate
Based on the assumptions and methodology described, a Coal Resource estimate, summarized in Table 11.1,
was prepared as of December 31, 2023, for property controlled by Coronado.
Table 11.1: Coal Resources Summary as of December 31, 2023
Area
Measu
red
(Mt)
Indicated
(Mt)
Meas +
Ind
Inferre
d (Mt)
Total
(Mt)
Ash %
VM %
Sulphur
%
Opencut
Inclusive of
Reserves
217
25
242
-
242
18.7
19.2
0.57
Exclusive of
Reserves
167
81
247
54
302
22.9
19.1
0.59
Total Opencut
383
106
489
54
543
21.0
19.1
0.58
Underground
Inclusive of
Reserves
140
44
183
-
183
14.9
18.2
0.39
Exclusive of
Reserves
41
62
103
106
209
18.6
18.1
0.39
Total Underground
181
106
286
106
392
16.9
18.2
0.39
Total Resources
564
211
775
160
936
19.2
18.7
0.50
Notes
(i) Total Coal Resources (936Mt) are reported inclusive of Reserves
(ii) Coal Resource tonnes are reported on a 5.3% in-situ Moisture basis
(iii) Coal qualities are reported on an air-dried basis
(iv) Underground resources are those that are approximately >15:1 vertical strip ratio or those overlapping underground mining
Resources are reported into two subsets:
●
Reserves
Inclusive Coal Resources are calculated from cut-offs described in section 11.3 and resource
confidence polygonl to determine Measured and Indicated resources. These same coal resources are
the basis for Reserves
Reserves have been assessed for economic viability in the Reserves estimation process using
Modifying Factors and cut-off parameters as discussed in section 12 of this TRS
●
Plan Reserves
Exclusive Coal Resources are calculated from cut-offs described in section 11.3 and resource
confidence polygon to determine Measured and Indicated and Inferred Resources
The Inclusive and Exclusive Coal Resources are also split into open-cut and underground categories.
The total coal Resources within the project concession boundaries are approximately 936 million tonnes, as
determined at an effective year end. Compared to established criteria, this quantity of Resources classifies
Curragh as a large coal mining proposition.
11.3 Cut-off thickness and insitu ash
Open cut Resources have been estimated where thickness is greater than 0.3 metres and raw insitu ash below
50% (air-dried basis).
Page 46 of 118
Underground Resources have been estimated where the insitu coal thickness is greater than 1.8m. No ash
cut-off has been applied as all reported seams have low insitu ash (<~20% air-dried).
Underground Resources are those that can potentially be accessed from final open-cut highwall using a variety
of techniques including but not limited to board and pillar mining techniques and highwall mining.
Underground resources have been defined as those that are part of underground reserves or in areas where
no reserves are declared, where the vertical overburden to tonnes of insitu coal ratio is greater than 15:1
Deeper potential mineralization that is poorly defined through exploration or not easily accessible from final
open-cut highwalls has been excluded from the Resource Estimate.
11.4 Resources Exclusive of Reserves
Curragh tenements contain Resources exclusive of Reserves which have not been included in the current
mine plan (Table 11.1). Reasons that may preclude elevation for Resources to Reserves include, but are not
limited to:
●
Reserves
●
short-term product price assumptions
Considering the long-life of Curragh assets, changing technologies and varying market conditions over time
provide options to revise Reserves periodically.
11.5 Initial Economic Assessment
Opencut
An initial economic assessment has been completed to determine whether there are reasonable prospects for
economic extraction of open-cut resources outside of reserves. There are 247Mt of Coal Resources estimated
as potentially suitable for open cut mining pending future suitable feasibility analysis and study. The
assessment assumes that any future mining of these resources would occur after the depletion of current
LOMP reserves (>20 years). It is assumed that demand for metallurgical product will continue beyond this
timeframe.
The assessment is preliminary in nature and contains inferred mineral resources that are considered too
speculative geologically to have modifying factors applied to them that would enable them to be categorized
as mineral reserves, and there is no certainty that this economic assessment will be realized.
The cut-off grades used in the assessment correspond to those in section 11.3. The cut-off grade is within
range of normal current open-cut Operations. The total resource average Insitu ash grade is much lower than
the cut-off grade. The portion of resource that approach cut-off grade is only a small proportion of the total
resource.
The analysis has included mining costs, processing costs, transport, marketing, sustaining capital and royalty
costs. A long term realized product price of $US133/t was assumed based at an average total product yield of
75% calculated from LOMP average product mix and yield. Resources exclusive or reserves are expected to
yield a similar product mix and yield to the LOMP plan.
The initial economic analysis indicates that a break-even strip ratio of 17.3 is appropriate for Curragh open-cut
operations as per Figure 14. The opencut Coal Resource estimates in this TRS have been calculated using a
lesser strip ratio cut-off ratio of approximately15:1.
Page 47 of 118
Various assumption and limitation of this analysis include:
o
o
approximate 40% coking, 30% PCI and 30% thermal.
o
o
o
domestic thermal contracts due to finish in 2037
o
studies available at time of publication
o
resources outside of reserves will be available at end of pit life albeit at a low recovery
Risk with converting the resources to reserves include:
o
o
o
o
Figure 14 Breakeven analysis vs strip ratio.
Underground
An initial economic assessment has been completed to determine whether there are reasonable prospects for
economic extraction of underground resources outside of underground reserves. There are 209Mt of Coal
Resources estimated as potentially suitable for underground mining. The assessment is preliminary in nature
and contains inferred mineral resources that are considered too speculative geologically to have modifying
factors applied to them that would enable them to be categorized as mineral reserves, and there is no certainty
that this economic assessment will be realized.
To determine whether there are reasonable prospects for economic extraction of these underground
resources, mining cost and capital cost data was extracted from a financial model used in definition of
Underground Reserves defined in section 12.2 and merged with the actual cost data for downstream
Page 48 of 118
processing costs, transport, marketing and royalties on the same basis as the previous opencut analysis as
used in the 2023 LOMP Plan. The analysis demonstrates a positive net margin as per Figure 11 -1.
Underground resources are only those that could be accessed from end of open-cut life highwalls or resources
as extension to declared underground reserves.
Figure 11-1 – Underground cost per tonne vs average realized price per product tonne
Various assumption and limitation of this analysis include:
o
o
o
o
o
o
o
Risks with converting the resources to reserves include:
●
Fault, there is risk that geological complexity may preclude any coal extraction adjacent to the fault
●
risk associated with confirming acceptable continuity, coal quality and product yield
●
●
●
●
to a Mining Lease
11.6 Resource Classification and Estimate Uncertainty
Resource Classifications have been based on a borehole geostatistical study conducted in 2020:
Page 49 of 118
Curragh Drillhole Spacing Analysis Project; Resology Pty Ltd; October 2020
The project involved exploratory data analysis (“EDA”) of seam thickness and quality information to define
seam domains. Each seam domain was then assessed using drillhole spacing analysis (“DHSA”) to calculate
the global estimation precision (“error”) for each major seam. A 10-year mining rate was then used to calculate
error at different drillhole spacings for use in Resource classification process.
The critical Resource variables analyzed were seam thickness and insitu ash. These were chosen for the
Resource estimate classification as these parameters are the main drivers of economics. Ash exhibits a very
good correlation to density and hence density was not analyzed separately. Ash also exhibits a good
correlation to total product yield, a proxy for product tonnes. Other quality parameters are well with market
acceptability and not reviewed separately.
As all seam exhibit different variability for thickness and ash in different domains, a variety of drillhole spacings
have been applied. In summary, the following drillhole spacing ranges (Table 11.2) have been applied for
thickness and ash to define reported Resource categories. The value chosen will depend on which seam, and
which domain is being estimated. The drillhole spacings for a given category tend to be higher at Curragh
North due to lower seam variability compared to coal seams further south.
Table 11.2: Ranges of drillhole spacing used to define coal Resource categories (metres)
Measured
Indicated
Inferred
Thickness
500-1000m
800-2400m
2000-4000m
Ash
800-1000m
1400-1800m
3500m
For reported categories the following precision levels apply (Table 11.3). Resources reported as Measured
would be expected to be within +/- 10% on if mined over a 10-year mining timeframe.
Table 11.3: Resource Estimate Global Precision
Category
Global Estimation Precision
Measured
+/- 10%
Indicated
+/- 10%-20%
Inferred
+/- 20%-50%
11.7 Qualified Person ’s Opinion
It is the Qualified Person’s opinion that the Resource estimate is an accurate and fair representation of
Curragh’s coal Resource and that all issues relating to relevant technical and economic factors likely to
influence the prospect of economic extraction can be resolved by further work and/or improvement in cost
base over time with innovation and improving mining technology over a long mine life. Sufficient exploration
data is supported by a longstanding history of successful coal production at Curragh, further increasing the
confidence of the Resource estimates.
11.8 Qualified Person ’s Credentials
Mr. Barry Lay, BSc Geology (Hons); MAusIMM; possesses the necessary credentials as a member of the
AusIMM to serve as a Qualified Person for this TRS.
Page 50 of 118
12 Mineral Reserve Estimates
12.1 Open Cut
12.1.0 Assumptions, Parameters and Methodology
A
Coal Reserve is the economically mineable part of a Measured and/or Indicated Coal Resource. It includes
diluting materials and allowances for losses, which may occur when the material is mined or extracted and is
defined by studies as appropriate that include application of Modifying Factors. These include, but are not
restricted to, mining, processing, metallurgical, infrastructure, economic, marketing, legal, environmental,
social and governmental factors. Such studies demonstrate that, at the time of reporting, extraction could
reasonably be justified. Coal Reserves are sub-divided, in order of decreasing geological confidence, into
Proven and Probable classifications.
Proven Coal Reserves are the economically mineable part of a Measured Coal Resource, adjusted for diluting
materials and allowances for losses when the material is mined. It is based on appropriate assessment and
studies in consideration of and adjusted for reasonably assumed modifying factors. These assessments
demonstrate that extraction could be reasonably justified at the time of reporting.
Probable Coal Reserves are the economically mineable part of an Indicated Coal Resource, and in some
circumstances a Measured Coal Resource, adjusted for diluting materials and allowances for losses when the
material is mined. It is based on appropriate assessment and studies in consideration of and adjusted for
reasonably assumed modifying factors. These assessments demonstrate that extraction could be reasonably
justified at the time of reporting.
The Life of Mine plan pit limits for the Curragh Open Cut were defined using a combination of methods. An
initial first pass unconstrained pit optimisation was undertaken on the geological Resource model using Deswik
pseudoflow. This uses a block model of the resource with the Lerchs-Grossman algorithm to determine the
optimised pit shell limits for the available Resource. Modifying factors were then applied including approved
Mining Lease and Environmental constraints as hard limits to the open cut mine extents, including flood
protection levee banks and environmental offset and protected conservation areas. Installed critical
infrastructure such as the Curragh Noth Overland Conveyor were also taken into consideration for limits on
the open cut mine extents.
A mine design was developed using a pitwall batter angle and benching configuration consistent with the
existing open cut operation mine design and used to cut a full mining reserve set of waste and coal solids for
margin ranking and scheduling. Mining reserves were cut to beyond the initial Deswik pit optimiser pitshell
extents where other constraints were not limiting the mining reserve. This was a more detailed margin ranking
process could be undertaken in a scheduling package to define the economic cut-off point of the open cut.
The mining reserve solids were imported into the mine scheduling software package SPRY and converted
from Insitu to ROM reserves using a number of mining modifying factor assumptions as summarised in Table
12.1.
Page 51 of 118
Table 12.1 – Insitu to ROM Coal Modifying Factors
Insitu to ROM Coal Modifying Factors
Unit
Value
Roof Loss
cm
15.0
Roof Dilution
cm
7.5
Floor Loss
cm
0.0
Floor Dilution
cm
15.0
Minimum Coal Mining Thickness
m
0.5
Minimum Waste Mining Thickness
m
0.5
Insitu Raw Ash (adb) cutoff
%
45
%
2.0
Dilution density
t/bcm
2.4
Dilution Raw Ash (adb)
%
90
A detailed margin ranking process was undertaken on the ROM reserve set in SPRY using Long Term
benchmark revenue pricing assumptions and product realisation percentages from benchmark. These
assumptions were Coronado’s internal view of the long-term market as at October 2023. An average realised
price of USD 131/t has been adopted in this margin ranking analysis The average realised price is a result of
the benchmark price forecast assumption for the Premium Low Volatile Hard Coking Coal combined with
appropriate quality discounts and other price adjustments relevant to Curragh’s product mix. This was the
economic cut-off price used to determine the economic limits of open cut mining in the Curragh Reserve.
Costs applied to the margin rank included unit rate actual Curragh mine site costs on a 3-year historical rolling
average of actuals. The product coal yield estimation was derived from an A&B Mylec washability simulation
model gridset that was reserved with the mining solids on each coal ply level for each mining reserve solid.
The margin ranking process for the Curragh LOM plan was undertaken in SPRY and the output determined
the economic cut-off point of the open cut mine plan where other hard constraints like Mining Leases or
Environmental constraints weren’t limiting the mining extents.
It should be noted that the open cut mine design in some pits has taken some slightly margin negative blocks
in order to maintain the operational strike length for efficient dragline waste mining operations. These loss
making blocks are offset with positive margin mining blocks within the strip, and a strip by strip margin analysis
shows the strips overall in the mine plan are margin positive. The pits where this is occurring is T pit, L pit and
Z pit in particular.
Page 52 of 118
12.1.1 Open Cut Reserves Estimate
The Open Cut (ROM) Coal Reserve estimate for Curragh reported in Table 12.2 has been converted from the
Coal Resource estimate.
The Open Cut Marketable Coal Reserve estimate represents beneficiated or otherwise enhanced coal product
where modifications due to mining, dilution and processing have been considered and is an estimate of the
marketable product achievable from the ROM Coal Reserve. This is shown in Table 12.3.
The numbers are based on the results and findings of the Qualified Persons and their application of the relevant
modifying factors to the Coal Resource geological model. The basis for the conversion of Coal Resources to
Coal Reserves presented considers only the Measured and Indicated Coal Resources are converted to Proven
and Probable Coal Reserves respectively.
Table 12.2: Open Cut ROM Coal Reserve Summary as of December 31, 2023 (Mt)
Curragh
Proven
Probable
Total
Coal Quality of Reserve inclusive of loss and dilution
(adb)
Mt
Mt
Mt
Ash (%)
TS (%)
VM (%)
ROM tonnes
227
22
249
31.3
0.5
16.0
Table 12.3: Open Cut Marketable Coal Reserve Summary as of December 31, 2023 (Mt)
Demonstrated Coal Reserves
(Wet Tonnes, Washed or Direct Shipped, Mt)
Quality (adb)
Curragh
By Reliability Category
Proven
Probable
Total
Ash%
Sulphur%
VM%
Product
tonnes
173
16
189
12.2
0.5
19.5
Notes:
a) Coronado’s ownership is 100% of the Curragh Mine
b) All tonnes are millions of metric tonnes (Mt).
c) ROM Coal Reserves have been stated on a 7.5% Moisture basis.
d) Marketable Reserves are stated on a 9.5% moisture basis, including a combination of surface moisture and inherent moisture.
e) Coal qualities are reported on an air-dried basis.
f) Totals may not sum due to rounding.
12.1.2 Qualified Person’s Opinion
Mr. Daniel Millers BE (Mining) MAusIMM(CP) possesses the required experience in open cut coal mining and
reserve estimation and credentials as a member of the AusIMM to act as a Qualified Person for Coal Reserves
estimation in this TRS.
Determination of Marketable Reserves has relied on Product Coal Quality grids and washability yield
simulation data at defined CHPP cut points provided by Coronado which are then reserved and imported to
the scheduling model to calculate marketable reserve tonnes and coal quality. The product qualities and
washability yield simulation grids are based on modelling completed by AB Mylec. The models and outputs
appear consistent with historical production results. The washability simulation and coal quality grids are
showing a deterioration in yield and quality in the Z and X pit opencut development mining areas. This has
been factored into the mine plan, however there has been no production data to reconcile against in these
new greenfield development pit areas.
It is the opinion of Mr. Daniel Millers that this TRS accurately reflects the Open Cut Coal Reserve estimate for
Curragh as defined by the JORC Code and SEC Regulation S-K 1300. Sufficient exploration data is supported
by a long history of 40 years successful open cut coal production at Curragh, further increasing the confidence
of the Coal Reserve estimate. The application of modifying factors is supported by a combination of laboratory-
based data and practical historical mining knowledge from the Curragh operation.
Page 53 of 118
12.2 Underground
12.2.0 Assumptions, Parameters and Methodology
The author adopted reasonable assumptions when applying the appropriate modifying factors to Curragh’s
Resources to derive reserve estimates. Such modifying factors include mining, metallurgical, economic,
marketing, legal, environmental, social and governmental factors.
Proven Coal Reserves are the economically mineable part of a measured coal Resource, adjusted for diluting
materials and allowances for losses when the material is mined. It is based on appropriate assessment and
studies in consideration of and adjusted for reasonably assumed modifying factors. These assessments
demonstrate that extraction could be reasonably justified at the time of reporting.
Probable Coal Reserves are the economically mineable part of an indicated coal Resource, and in some
circumstances a measured coal Resource, adjusted for diluting materials and allowances for losses when the
material is mined. It is based on appropriate assessment and studies in consideration of and adjusted for
reasonably assumed modifying factors. These assessments demonstrate that extraction could be reasonably
justified at the time of reporting.
Upon completion of delineation and calculation of coal Resources, a Pre-Feasibility Study of Curragh North
area for both target seams (Mammoth Seam and Mackenzie Seam) and subsequently a more detailed
Operational Readiness Study (Feasibility Study level of accuracy) of the Southern Area in the Mammoth Seam
was undertaken. The Mine plan was generated based on the forecast mine plan and permit plan using current
property control limits, modifications to geologic mapping, or other factors determined during the evaluation.
The planned Mammoth Seam working section is for a minimum primary extraction of 2.5m and a maximum of
3.5m in combination with secondary floor coal extraction of up to 2m resulting in a maximum total extraction
height of 5.5m. Additional secondary extraction from Bell Outs to a maximum height of 5.5m is also planned.
Where the seam height exceeds 5.5m coal will be left in the floor. The planned out of seam dilution is 50mm
in the roof and 50mm in the floor when mining to the floor of the seam
The planned Mackenzie Seam working section is for a minimum primary extraction height of 3m and a
maximum of 3.5m in combination with secondary floor coal extraction of up to 2m resulting in a maximum total
extraction height of 5.5m. Additional secondary extraction from Bell Outs to a maximum height of 5.5m is also
planned. The working section in Mackenzie Seam will leave a minimum of 0.5m of coal in the floor and 0.8m
of coal in the roof due to geotechnical requirements. Consequently, there is zero out of seam stone dilution in
the normal Mackenzie Seam working section.
Plant recovery is a function of in-seam recovery and plant efficiency factor.
ROM and product data outputs from the LOM plan sequencing were processed into reports and summarized
on an annual basis for processing into the economic model. Product tonnes are reported at 10 percent moisture
and represent the Marketable product from the Property.
Pricing data as provided by Coronado marketing team is based on internationally recognised forecasting and
the view of Coronado Pricing Committee as of October 2023. The average FOB coal price per tonne for the
Underground Mine LOM was approximately US$ 143 / tonne. The breakeven cost per FOB product tonne over
the LOM (FOB Product tonnes / (total cash cost + total capital cost)) was approximately US$ 89 / tonne. The
minimum annual average income per FOM product tonne for the underground mine was estimated to be
US$134 / tonne. Based on the stated coal price and cost assumptions the minable reserves are economically
extractable and a Cut Off Grade has not been applied. Practical limits of mining height and depth of cover
(DOC) have been applied.
The coal Resource mapping and estimation process, described in the report, was used as a basis for the coal
reserve estimate. Proven and probable coal Reserves were derived from the defined coal Resource
considering relevant processing, economic (including technical estimates of capital, revenue, and cost),
marketing, legal, environmental, socio-economic, and regulatory factors and are presented on a moist,
Page 54 of 118
recoverable basis. Modifying factors have been applied based on the current understanding of geological,
geotechnical and gas impacts on the planned mining method and extraction.
Points of observation include exploration drill holes, degas holes, and mine measurements which have been
fully vetted and processed into a geologic model. The geologic model is based on seam depositional
modelling, the interrelationship of overlying and underlying strata on seam mineability, seam thickness trends,
the impact of seam structure (i.e., faulting), intra-seam characteristics, etc. Once the geological model was
completed, a statistical analysis, described in Section 11.1.1 was conducted and up to a 1 kilometre radius
from a valid point of observation was selected to define Measured Resources.
Likewise, the distance between 1 and 2 of a kilometre radius was selected to define Indicated Resources.
Indicated Resources may convert to Probable Reserves. No Inferred coal was included in the Reserve
estimation
The Measured, Indicated and Inferred Reso urce classifications overlayed on the current mine layout at the
time of this study in the Mammoth Seam and Mackenzie Seam are shown in Figure 12-1 and Figure 12-2
respectively. No reserves have been reported in the adjoining MDL162 tenement.
Page 55 of 118
Figure 12-1. S-K 1300 Resource Classifications Relative to Mammoth Seam Mine Plan
Page 56 of 118
Figure 12-2. S-K 1300 Resource Classifications Relative to Mackenzie Seam Mine Plan
Page 57 of 118
12.2.1 Underground Reserves Estimate
Reserve tonnage estimates provided herein report coal Reserves derived from the in-situ Resource tonnes
presented in Table 12.4, and not in addition to coal Resources. Proven and Probable coal Reserves were
derived from the defined coal Resource considering relevant mining, processing, infrastructure, economic
(including estimates of capital, revenue, and cost), marketing, legal, environmental, socio-economic and
regulatory factors. The Mineral Reserve estimates for Curragh have been determined and are presented in
Table 12.4 and Table 12.5. The numbers are based on the results and findings of the Qualified Persons and
their application of the relevant modifying factors to the aforementioned Resource model. The Reserves
presented consider only the Measured and Indicated Resources that have subsequently been converted to
Proven and Probable Reserves. The numbers exclude tonnes from MDL162.
The LOM ROM tonnes reported in the Curragh North Underground PFS (completed in the first quarter of 2023)
was approximately 40.4 Mt. Following updating of the geological model based on additional exploration data
the Updated LOM Plan reported 57Mt of which 50.4 Mt ROM was within Measured and Indicated Resource
classification and excluding inferred resources and MDL 162. At the time of completion of this reserve estimate
the results of a 3D Seismic Study were in progress and incomplete. Conservative modifying factors have been
applied for possible impacts of geological structures yet to be defined and impacts on mining recovery. Based
on potentially positive outcomes of further geological exploration (including Seismic Studies) that are currently
in progress and planned in the future it is probable that the modifying factors could be reviewed . Currently a
conservative value of 41 Mt ROM of the 50 Mt ROM of the current planned LOM production within Measured
and Indicated resource categories and excluding MDL162, have been reported as Proven and Probable
Reserves respectively. This is approximately 84% of the potential LOM ROM tonnes.
Table 12.4: Underground ROM Coal Reserve Summary as of December 31, 2023 (Mt)
Curragh North
Underground
Proven
Probable
Total
Coal Quality of Reserve inclusive of loss and dilution
(adb)
Mt
Mt
Mt
Ash (%)
TS (%)
VM (%)
ROM tonnes
30
11
41
17.0
0.3
16.4
Table 12.5: Underground Marketable Coal Reserve Summary as of December 31, 2023 (Mt)
Demonstrated Coal Reserves
(Wet Tonnes, Washed or Direct Shipped, Mt)
Quality (adb)
Curragh
North
Undergroun
d
By Reliability Category
Proven
Probable
Total
Ash%
Sulphur%
VM%
Total
25
9
34
10.0
0.3
16.9
Notes:
a) Coronado’s ownership is 100% of the Curragh Mine
b) All tonnes are millions of metric tonnes (Mt).
c) ROM Coal Reserves have been stated on a 8% Moisture basis.
d) Marketable Reserves are stated on a 10% moisture basis, including a combination of surface moisture and inherent moisture.
e) Coal qualities are reported on an air-dried basis.
f) Totals may not sum due to rounding.
g) Curragh produce a range of Coking, PCI and Thermal Coal products from the underground target seams. The combined
yield for Primary and Secondary Product Coal modelled over the LOM was approximately 87%
12.2.2 Qualified Person’s Opinion
Mr. Christopher Wilkinson Bsc (Mining) MAusIMM(CP) possesses the required experience in underground
coal mining and reserve estimation and credentials as a member of the AusIMM to act as a Qualified Person
for Coal Reserves estimation in this TRS.
It is the opinion of Mr. Christopher Wilkinson that this TRS accurately reflects the Underground Coal Reserves
estimate as defined by the JORC Code and SEC Regulation S-K 1300. Sufficient exploration data is supported
by a longstanding history of successful coal production at Curragh, further increasing the confidence of the
reserve estimates. The application of modifying factors are supported by a combination of laboratory-based
Page 58 of 118
data, practical historical mining knowledge from Curragh and relevant experience from other mines in the
region extracting the target seams using the same underground mining methods. Appropriate modifying factors
have been applied in determination of ROM and Marketable Reserves based on the currently available
exploration data and analysis.
Determination of Marketable Reserves has relied on Product Coal Quality grids and yields at defined CHPP
cut points provided by Coronado which are then used in the Deswik LOM scheduling model to generate
marketable reserve tonnes and coal quality The product qualities and yield grids are based on modelling by
AB Mylec. The models and outputs have not been validated by Mr Wilkinson or Mining Consultancy Services
Pty Ltd / Talisman Technical Pty Ltd.
Page 59 of 118
13 Mining Methods
13.1 Open Cut Mining
Coal mine development at Curragh is accomplished by surface strip mining methods and has been so
historically since the mine commenced in 1983. The mine’s annual production capacity of around 200 Mbcm
of total movement means it can be ranked as a large open cut coal operation when compared to producers in
Australia and internationally. The open cut operation mines around 13.5Mt Run of Mine (ROM) coal per annum,
producing around 11Mtpa of product coal for both international metallurgical markets, thermal coal for domestic
and international markets.
Curragh operates 4 large electric draglines, 1 large electric rope shovel and a fleet of smaller diesel hydraulic
excavators. This is typical of large open cut coal mines in the Bowen Basin in Central Queensland. The
Curragh Life of Mine (LOM) plan continues the use of dragline strip mining, with truck and shovel/excavators
moving the prestrip waste ahead of the dragline fleet. Hydraulic excavators mine the ROM coal and transport
it to the ROM stockpile for feed to the processing plant for beneficiation.
13.1.0 Geotech and Hydrology
The management of geotechnical hazards at the Curragh Mine is managed in the site Safety and Health
Management System (SHMS) with a Principal Hazard Management Plan (PHMP). The Curragh Geotechnical
Hazard Control System Structure consists of 4 primary elements:
●
●
●
●
The validity of the mine design and geotechnical hazard management is achieved by ensuring data of sufficient
quantity and quality for the geotechnical model is available to support the design process. Safe design and
mine planning processes are applied throughout the life of mine. The design is prepared, reviewed, and revised
by competent persons throughout the life of mine.
The coal seams at Curragh generally dip to the east at less than 5°, however in fault and deformation zones,
steep dips occur locally. On the western side of Curragh East the seams dip to the west due to the complex
dome and basin structures resulting from deformation.
Seam deformation has resulted principally from thrust faulting from the north-east resulting in seam
displacements up to 20 metres vertically. North-south and east-west normal faults are less common and some
of these have a strike-slip component. Fault deformation has resulted in seam thinning, thickening and barren
areas within the mine plan.
The Jellinbah fault occurs on the eastern side of the Curragh North mining lease. The fault is a thrust fault
upthrown on the eastern side by approximately 300 metres.
The Curragh Planning System (CPS) consists of a collective of mine planning systems developed and
maintained to ensure mine design and scheduling are consistently applied.
The CPS describes, through each Process, the steps to be taken and relevant Work Instructions to be utilised.
Refer to Appendix B: Curragh Planning System (CPS) Documents for a full list of documents used to inform
various stages of mine planning, design, monitoring, and auditing.
Page 60 of 118
Geotechnical ground models are the basis on which slope stability analysis and slope design is completed and
need to be informed by a level of data appropriate to the design phase. The Geotechnical ground model is
comprised of the following components:
●
●
●
●
Geotechnical slope stability analysis aims to predictively assess slope performance based on developed
geotechnical ground models and understood slope failure mechanisms associated with the observed and
interpreted geological, geotechnical, and hydrogeological conditions.
There are various geotechnical slope stability analysis methods available:
●
●
●
●
Geotechnical hazard zoning provides an indication of the likelihood of failure for various failure scales and
forms, and for a defined pit wall design option, to assist mine planning in determining if the risks presented by
the design are acceptable.
Geotechnical hazard zoning considers the following:
●
●
●
●
●
●
●
●
●
Geotechnical Hazard Mapping can be undertaken at a conceptual level or at a detailed design level. The
Geotechnical Hazard Mapping Plans present the projection design, assessed level of geological uncertainty
and potential pit wall failure mechanism types that have been identified together with an assessed likelihood
of failure.
Seismic hazard assessments are completed, where required, for geotechnical infrastructure during the design
and assessment phase with reference to Geoscience Australia monitoring (maps, likelihood etc.).
Typical Highwall and lowall mine design profiles for the Curragh North active mining area are shown in Figure
13-1 and Figure 13-2 respectively. The Draglines will typically take the lower Pisces seam interburden which
as typically cast blasted into the adjacent mined out pit void.
Page 61 of 118
Figure 13-1 - Curragh North typical Highwall design profile
Figure 13-2 - Curragh North typical Lowall design profile
Typical Highwall and lowall mine design profiles for the Curragh Main active mining area are shown in Figure
13-3 and Figure 13-4 respectively. The Draglines will typically take the lower two passes of Castor and Pollux
seam interburdens at Curragh Main.
Page 62 of 118
Figure 13-3 - Curragh Main typical Highwall design profile
Figure 13-4 - Curragh Main typical Lowall design profile
Groundwater impacts are greatest at Curragh North, in particular in the Northern pits of S pit North, T pit and
U pits where perched aquifers exist in the upper alluvial sands. This is managed by designing wider benches
on the base of freedig horizon to allow for a trafficable roadway on the bench as well as a drainage and ponding
area on the highwall side of the bench for groundwater to pond and accumulate before being pumped out and
handled with the site surface water management network. Other areas of the mine are not dramatically
impacted by groundwater presence. The coal seams are the principal aquifers in the Rangal Coal Measures.
Page 63 of 118
Groundwater management at the operation is achieved through a network of in-pit and highwall pump systems
that move both ground water and captured surface water from rainfall into sacrificial pit storages and/or into
surface water storages. Captured mine affected water onsite is recycled and used for dust suppression via
water cart fill points, or transferred via the site network back to the CHPP for use as processing water in the
processing plant. Some monitored releases of water to the receiving environment occur when regulated
conditions are met to remove water from the Curragh site inventory.
Mine management at Curragh monitors groundwater inflows and maintains comprehensive site water balance
models.
13.1.1 Open Cut LOM Plan
The Curragh open cut Life of Mine (LOM) plan essentially is a continuation of the existing mining method at
the site over the remaining economic Coal Reserves. The mine is currently operating in the Curragh Main and
Curragh North operational areas, with two new development areas (X and Z pits) to be built and mined
throughout the LOM plan. The primary waste production fleet is four large electric draglines that currently
operate two at Curragh Main and two at Curragh North. These draglines are supported by fleets of diesel
hydraulic excavators at Curragh Main, and at Curragh North an electric shovel as well as diesel hydraulic
excavators. Coal mining is undertaken with diesel hydraulic excavators at both Curragh Main and Curragh
North.
The mining operations utilise cast blasting methods where applicable in the dragline waste passes to move
some waste into final position from blasting practices. Bulk dozer push is utilised to a minor extent at Curragh
for both dragline bench prep and coal uncovery using Cast/Doze/Excavate (CDX) methods in some areas to
boost coal uncovery.
The Curragh North open cut LOM plan aligns with the underground LOM plan. The final open cut highwall
position has been used to define the underground LOM plan. The Open Cut LOM plan is limited in the Southern
half of the mine by the installed Overland Conveyor (OLC). This ROM coal transport system transports ROM
coal from the Open Cut and planned Underground project from Curragh North to the processing plant facility
at Curragh Main. For the purposes of the Open Cut LOM plan, the assumption was to leave this infrastructure
in place and mine up to it with a 100m pit crest offset for Geotechnical stability risk control. The underground
project will mine Coal Reserves under and to the East of this infrastructure. This OLC pit constraint exists for
S Pit North, S Pit and S Pit South.
The T Pit and U Pit Open Cut reserves are planned to be mined down dip to an economic break-even position,
where the underground project will continue with the extraction of ROM coal beyond this open cut break-even
point. The period progress plot of the Curragh North open cut project can be seen in Figure 13-5.
Page 64 of 118
Figure 13-5 – Curragh North Period Progress Plot
The Curragh Main mine plan is the continuation of the existing mining pits within the historic mining area of
the Curragh Main project area. The currently active mining areas that the draglines are active in will be
exhausted with the next 5 years. A new development boxcut is required to open L pit which will be a investment
to bring online within the 3-5 years in the plan to ensure dragline strike continuity. Critical to the open cut LOM
plan is the re-entry to D pit in the North of Curragh Main. D Pit will require dewatering to EN pit void when it
becomes available as a final void in 2025. The establishment of the L pit boxcut and re-entry to D Pit are the
critical factors in delaying the development of Z and X pits to late in the 2020’s. This will ensure continuity of
dragline operations at Curragh Main and maintaining the lowest unit rate cost of production from the Curragh
Main pits.
G pit is currently full of stored mine affected water and requires pumping to another mine void/storage prior to
re-entry to the remaining reserves in G pit. J pit is a truck and excavator and dozer push pit at the southern
end of Curragh Main and is continued to be worked with these mining methods through the LOM plan. The
period progress plot of the Curragh Main open cut project can be seen in Figure 13-6.
Page 65 of 118
Figure 13-6 - Curragh Main Period Progress Plot
X pit is a new development pit area that exists midway between the Curragh Main and Curragh North existing
mining areas at the Curragh Mine. The X Pit economic reserve exists over several different mining pit areas,
with differing optimal target pit floor horizons depending on seam thickness, depth and interburden
thicknesses. Surface development infrastructure is required to unlock the X Pit reserve for mining including a
significant creek diversion of Minnie Creek, flood protection levees, ROM infrastructure and MIA facilities,
surface water and mine affected water handling infrastructure, haulroads, dragline walk road, conveyor cross
over bridge and 66kv high voltage electrical infrastructure to support dragline operations. The existing
Overland Conveyor (OLC) installation exists through the centre of the X Pit reserve. The coal under this
infrastructure produces an attractive cash margin and has been included as a coal reserve on the basis that it
will be mined after the completion of Curragh North open cut and underground operations have completed and
the existing OLC is decommissioned – essentially as the final portion of the mines’ life.
The Eastern extent of the X Pit deposit is bounded by an environmental biodiversity offset conservation limit.
Other areas of the X Pit deposit are cutoff with economic margi n limits where the modelled coal seams break
even on an all-in cost basis margin rank.
X pit contains an ‘early entry’ option by way of the Southern two mining pit areas are shallow truck and
excavator and bulk dozer push areas that can be accessed with minimal surface infrastructure investment to
unlock and could be used by the business as alternative mining areas to boost ROM coal production prior to
what is scheduled in the LOM plan. The period progress plot of the X Pit open cut project can be seen in Figure
13-7.
Page 66 of 118
Figure 13-7 - X Pit Period Progress Plot
Z Pit is a second new development area that exists to the South-West of the existing Curragh Main operational
area. This is a shallow, long strike length deposit ideal for dragline operations. The coal seams however have
thinned in Z pit compared to Curragh Main, and in the South of Z pit the coal seams down dip split into plys
with interburdens less than 10m in thickness and are unsuitable for dragline operations . The impact this has
is Z pit produces the lowest cash margin of the four main mining areas at Curragh and has been prioritised
within the LOM plan to optimise project cashflow.
Surface development infrastructure is required to be invested in by the business to unlock the Z Pit reserve for
mining including a creek diversion of Bonnie Doon Creek, flood protection levee, ROM infrastructure and MIA
facilities, surface water and mine affected water handling infrastructure, haulroads, dragline walk road, public
road upgrades and 66kv high voltage electrical infrastructure to support dragline operations.
Most of the Z Pit mining blocks start on the modelled base of weathering cropline of the Pollux seam in the
Western side of the deposit. The North-Western edge of the Z pit deposit is limited by the Bonnie Doon Creek
diversion on the existing Mining Lease. The Eastern downdip extent of the Z Pit deposit is bounded by
economic margin cut-off limits where the modelled coal seams break even on an all-in cost basis. The period
progress plot of the Z Pit open cut project can be seen in Figure 13-8.
Page 67 of 118
Figure 13-8 - Z Pit Period Progress Plot
The primary production fleet at Curragh revolves around both maintaining sufficient prestripping capacity in
advance of the dragline waste stripping fleet and supporting open cut coal targets. The dragline fleet consists
of two 8200 draglines, an 8750 and an 8750 Supermax dragline making for a total fleet of four machines. The
prestripping fleet consists of a BE495 electric rope shovel, and three classes of diesel hydraulic backhoe
excavators – 800t, 600t and 350t class excavators. There is currently budgeted 13 x prestripping and coal
mining fleets being operated at Curragh in addition to the four electric draglines. This prestripping fleet is
planned to increase to 15 fleets in the LOM plan to match the strip ratio requirements of the deposit, and then
reduce later in the LOM plan when capital development is undertaken in the new pit development areas of X
and Z pits. The primary excavator fleet is planned to increase the number of 800t class machines from two to
four in the LOM plan, with an additional 800t excavator replacing the retired BE495 electric shovel at the end
of its productive life in 2032. The LOM plan primary production fleet scheduled is shown in Figure 13-9 inclusive
of the dragline fleet. The LOM plan for the Curragh Open Cut is 21 years and is completed production in 2045.
Page 68 of 118
Figure 13-9 - Curragh Open Cut LOM Production Fleets
The LOM plan Run of Mine coal production profile from the Open Cut is shown in Figure 13-10. The mine plan
is to uncover and mine around 13.6 Mtpa ROM coal from the Open Cut. This production profile can be
maintained through until 2040 when the Curragh North open cut reserves then become exhausted and the
mine production profile reduces as Open Cut mining reserves are completed and the remaining mining areas
of Curragh Main, X and Z pits are completed.
Figure 13-10 - Curragh Open Cut LOM ROM t Mined
Figure 13-
11
shows the Open Cut LOM waste production profile by equipment type and the planned ROM
strip ratio over the LOM. The ROM strip ratio reduces later in the mine life when X and Z pits are developed.
The yield for these new pits however reduces and product strip ratio increases.
Page 69 of 118
Figure 13-11 - Curragh Open Cut LOM Waste Handled by Equipment Type
The LOM ROM coal production profile by source pit is shown in Figure 13-12.
Figure 13-12 - Curragh Open Cut ROM t Mined by Pit
The planned product coal production profile from the Curragh Open Cut mine plan is shown in Figure 13-13
plotted against the Run of Mine coal production profile. The declining product yield can be seen with the
reducing product coal over the LOM plan.
Page 70 of 118
Figure 13-13 - Curragh Open Cut ROM t Mined and Product Coal
The forecasted Open Cut product coal by product type can be seen in Figure 13-14, with the declining total
yield over time on the secondary chart axis.
Figure 13-14 - Curragh Open Cut Product Coal by Type
13.2 Underground Mining
The feasibility of underground mining of the Curragh North mine east of the planned location of the current
planned Open Cut mine LOM has been undertaken between 2020 and 2023 comprising a Pre Feasibility Study
Page 71 of 118
BELLOUTS
PRODUCTION FACES
CONVEYOR
DCB
INTAKE AIRWAYS
RETURN AIRWAYS
MINING DIRECTION
completed in Q1 2023 and a subsequent more detailed Operational Readiness Study (Feasibility Level of
Study) on the South Area in the Mammoth Seam.
The selected mining method is Bord and Pillar Mining using the Place Change operating methodology. Due to
the variation in seam thickness Bord and Pillar mining would be undertaken using Primary extraction of panels
with roadway widths of 6.5m reducing to 6m where the overburden thickness (Depth of Cover: DOC) or mining
conditions require. Primary extraction height would vary between 2.5m minimum to 3.5m maximum. Secondary
extraction of Floor Coal over the same panel layout created by Primary Mining would be undertaken with a
minimum floor coal extraction of 1m and a maximum extraction thickness of 2m and a maximum total combined
(Primary plus Secondary Extraction) extraction height of 5.5m. The secondary extraction width would be 1m
less than the Primary Extraction roadway width (eg. 5.5m Secondary Extraction width in a 6.5m primary
extraction roadway). Secondary Extraction would also comprise mining of “Bell Outs” around the perimeter of
the production panels mined from stubs (blind entry roadways) mined into the inter panel pillar. The Bell Outs
would be mined to a maximum height of 5.5m (where seam thickness allows) or the combined extraction
thickness of Primary and Secondary Extraction mining. The proposed mining method is well proven at several
mines in the Region who extract the same target coal seams from underground mines. This method has been
proven to not create any sig nificant surface subsidence and impact on overlying aquifers. The method has
been shown to be safe, productive and economicaly viable using readily available equipment technology and
people skills.
A typical extraction panel would comprise of 5-7 roadways with pillars designed to comply with industry
standard pillar design methodologies (UNSW Pillar Design Method) with Bell Out extraction around the
perimiter of the panel, as shown in Figure 13-15. Secondary Coal Floor extraction may also occur in panels
through out the mine in addition to the Bell Out Extraction, an example of the secondary floor workings can be
found in Figure 13-16.
Figure 13-15. Typical Bord and Pillar Production Panel with Primary and Secondary
Extraction.
Note: No. of roadway and heading within Bord and Pillar Panels vary across the Mine.
Page 72 of 118
Figure 13-16. Example of Secondary Floor Coal Workings
The Curragh North Underground mine would commence with 1 Bord and Pillar Continuous Miner Production
Unit to mine the pit bottom area and scale up to 4 Production Units at full production. Each Production Unit
would utilise a single place change continuous miner with 3 shuttle cars discharging to a Feeder Breaker. A
single Mobile Bolter would install roof and rib support. LHD vehicles would be used to undertake floor clean
up and materials supply and ancillary work.
All the Production Units would be able to undertake Primary and Secondary Extraction and mining Mains
Development Panels as required by the LOM Schedule and Plan.
13.2.0 Productivity
The mine has been planned to operate on a similar shift roster and production methodology to other
underground bord and pillar mines in Central QLD with an even time 7 day on, 7 day off roster for production
and maintenance crews and management and technical staff on a separate roster. The planned average
underground mine labour complement of approximately 320 people is consistent with similar mines.
The average budgeted operating time (Production hours) per week is approximately 84 hrs per week which
includes panel extension / retraction time for primary and secondary mining. This equates to an overall system
utilisation of 50% and has been benchmarked against other similar Bord and Pillar mining operations in
Queensland who target and achieve similar utilisation.
Production Rates have been determined based on first principles analysis of the following parameters using
proven and calibrated simulation models which are benchmarked to relevant operating bord and pillar mines:
●
●
●
●
●
●
production is not indicated to be constrained by normal support requirements.
The scheduled average annual Production Rates vary over the Mammoth Seam LOM between 177 ROM tph
to 245 ROM tph with an average of approximately 213 tph. The scheduled average annual Production Rates
Page 73 of 118
vary over the Mackenzie Seam LOM between 100 ROM tph to 220 ROM tph with an average of approximately
171 tph. Average annual ROM production per Continuous Miner Unit varies between 0.6Mt ROM per CM per
year to 1.0Mt ROM per CM per year and a LOM average of approximately 0.75Mt ROM per CM per year. This
has been benchmarked against comparable bord and pillar mines in Queensland mining similar coal seams
and using similar equipment. The average annual production rates per continuous miner unit over the LOM is
shown in Figure 13-17.
Figure 13-17. Average Annual Production Rate by CM Unit over LOM
13.2.1 Underground Geotech and Hydrology
Geotechnical analysis has been undertaken based on the available information at the time of the PFS by Mr
Chris Hanson of Prime Global Pty Ltd for MCS and subsequently up to the time of this study by Mr. Andrew
Seccombe of Blackrock Mining Solutions Pty Ltd. Ongoing exploration, sampling and laboratory testing is also
ongoing. Both Geotechnical Consultants are appropriately qualified and experienced.
Mine design analysis of the following aspects of the proposed underground mine design have been
considered:
●
●
●
●
and width to height ratio.
●
●
●
●
●
understood at the time of this report.
The currently planned Bord and Pillar Primary and Secondary mining method has been applied at similar
mines in the same coal measures in Queensland with proven geotechnical and hydrogeological outcomes.
Using this mining method and design principles has been shown to have negligible surface subsidence and
impact on overlying aquifers and bodies of surface water. The selected mining method has successfully
undermined a regional river without significant ground water impacts due to mining.
Curragh mine has an extensive water monitoring system and history which is no w being supplemented by
additional borehole test data over the planned underground mining area. Data from these sampling points is
being used by Hansen Environmental Consulting to support the EA amendment for underground mining.
Page 74 of 118
13.2.2 Underground LOM Plan
The planned Curragh North Underground Mine will initially extract the Mammoth Seam and subsequently the
underlying Mackenzie seam. Production would commence in the South Area from the southern end of S-Pit
as this area has the lowest DOC and is preferable from a productivity, recovery and gas drainage perspective.
Figure 13 -18 shows the DOC to the Mammoth Seam which ranges from approximately 50m to 28 0m. The
interburden to the underlying Mackenzie Seam varies between approximately 50m and 70m. Figure 13-19
shows the DOC to the Mackenzie Seam roof and varies between approximately 50m to 350m. The DOC
includes the Open Cut waste Dumps of between 50m to 60m height which overly the underground mining
areas. The natural DOC of the Mammoth Seam is comparable with other bord and pillar mines in QLD.
Page 75 of 118
Figure 13-18. Mammoth Seam Depth of Cover (DOC) (m)
Page 76 of 118
Figure 13-19. Mackenzie Seam Depth of Cover (DOC) (m)
Page 77 of 118
The thickness of the Mammoth Seam varies from approximately 2.5m to 7m over the proposed LOM layout
as illustrated in Figure 13-20 with a minimum 2.5m extraction height cut off.
Figure 13-20. Mammoth Seam thickness (m)
Page 78 of 118
The thickness of the Mackenzie Seam varies from approximately 4m to 9m over the proposed LOM layout as
illustrated in Figure 13-21 with a minimum 3m extraction height (4.3m seam thickness).
Figure 13-21. Mackenzie Seam thickness (m)
Page 79 of 118
The gas content of the Mammoth Seam is shown inFigure 13-22 and varies from approximately 0 to 11 m3/t
and Mackenzie Seams are shown in Figure 13-23, which varies from approximately 5m3/t to 13.5m3/t. Gas
content and permeability have been determined by bore hole core sample testing and modeled by recognized
industry experts Novus Energy and Geogas. A Gas analysis and management study on the initial South Area
of Mammoth Seam has been undertaken by Mr. Miles Brown (Drive Mining).
Figure 13-22. Mammoth Seam Gas Content (m3/t)
Page 80 of 118
Figure 13-23. Mackenzie Seam Gas Content (m3/t)
Page 81 of 118
Permeability of the coal seams has been tested and mapped in order to model the requirements for gas
management over the resource. Where the gas content is similar to or greater than the Gas Outburst
Threshold, gas drainage will be required to reduce the gas content to suitable levels for safe and productive
mining operations. Surface to In Seam (SIS) test gas wells will be implemented and the results used to design
appropriate gas drainage strategies for the underground mine. Drive Mining have completed an initial UIS and
SIS gas drainage Plan for the Mammoth Seam South Area. The results from gas drainage in this area can
then be used as inputs to extend gas drainage layouts and designs over the LOM.
Mine access is via 4 portal entries from the southern end of S-Pit and the surface infrastructure and access
would be as illustrated in Figure 13-24. ROM coal from the South Area underground mine will be transported
by truck from the portal to the Curragh North ROM stock pill area where it is loaded onto the existing. overland
conveyor and delivered to the CHPP. The underground MIA facilities would be located adjacent to the current
S-Pit Open Cut MIA and Workshop and men and material access to the underground mine would be via mobile
vehicles. The mine access methodology and surface infrastructure arrangement is consistent with other
underground bord and pillar mines operating from existing Open Cut mines in QLD.
Figure 13-24. Surface infrastructure for the Mammoth Seam South Area Mine Access from
S-Pit
The mine has been planned with three mining areas: South, Central and North. Production transitions from
South to Central and then North Areas as reserves deplete and geographical expansion is required to maintain
the required LOM production.
The electrical power requirements for the Underground Mine have been determined. Studies have shown there
is adequate power on site for establishing the underground mine and commencing the first two continuous
miner Units, however upgrades to the site infrastructure for full underground production with four continuous
miner units is required.
A load study is being undertaken for Curragh site to determine the required upgrades for the Open Cut and
Underground LOM. Once completed, the required power line and infrastructure upgrades must be completed
before full underground production to sustain safe and effective underground operations.
Page 82 of 118
Figure 13-25. Curragh North Underground Mine – Mammoth Seam LOM Layout
Page 83 of 118
Figure 13-26. Curragh North Underground Mine – Mackenzie Seam LOM Layout
Page 84 of 118
The mine will commence in the South Area of Mammoth Seam in planned to commence in December 2024
and then introduce additional continuous miner units, with full production using 4 units by 2026. Production is
planned to commence in the Mackenzie Seam in 2034 and the expected LOM of approximately 20 years.
Figure 13-27 & Figure 13-28 shows the Period Plot of production in the Mammoth Seam by year and Figure
13-29 shows the Period Plot for production in Mackenzie Seam by year. The ROM Production by Year for
each seam over the LOM is shown graph form in Figure 13-30. The annual ROM Production by continuous
miner unit over the LOM is shown in Figure 13-31.
Figure 13-27. LOM Production Period Plot for
Mammoth
Page 85 of 118
Figure 13-28. LOM Production Period Plot for Mammoth Seam Central & North
Page 86 of 118
Figure 13-29. LOM Production Period Plot for Mackenzie Seam
Page 87 of 118
Figure 13-30. LOM ROM Production per year by seam mined graph.
Figure 13-31. LOM ROM Production per year by CM Production Unit graph
Curragh Mine currently produces a range of Met Coal (Coking Coals), PCI and Thermal Coal from the
Mammoth and Mackenzie seams depending on market conditions and requirements to optimize recovery and
income. The product yield from the underground for both target seams has been determined based on existing
washing models and data at Specific Gravity Cut Points of 1.34 SG for a Primary Product consistent with Met
Coal and a Secondary Product at a Cut Point of 1.7 SG. Alternative Cut Points and blending strategies with
Open Cut coal from Curragh have been considered and would generate different products and yields.
The LOM Marketable coal based on a Primary Product at a 1.34SG cut point and a Secondary Product at a
1.7SG cut point and the combined Yield % is shown by year over the LOM in Figure 13-32.
Page 88 of 118
Figure 13-32. LOM Marketable tonnes by Primary and Secondary Product per year graph
Page 89 of 118
14 Process and recovery methods
14.1 Description
Curragh has two coal preparation plants CPP1 and CPP2. CPP1 is the oldest of the two processing plants
and has a documented nameplate capacity of 1100 t/h (as received). The CPP processes the 32mm x 0.7 mm
fractions through a 2-stage dense medium cyclone (“DMC”) circuit operating in a low density / high density
configuration to produce a low ash primary and a high ash secondary product respectively. The primary
cyclone underflow has the functionality to bypass the secondary DMC circuit and report directly as a secondary
product.
The minus 0.7 mm fraction is directed to a Jameson cell flotation circuit for processing. The concentrate from
the flotation circuit is pre-thickened via classifying cyclones before reporting to horizontal belt vacuum filters
and screen bowls for further dewatering prior to being conveyed to the primary product conveyor. The
classifying cyclone overflow is directed to a coal thickener, where the thickened product material is then
combined with the horizontal belt vacuum filter feed.
These processing methods are typical of what is used at other coal mines throughout the Bowen Basin in
Central Queensland, the technology is tried and proven.
CPP 2 has a documented nameplate capacity of 1200 t/h (as received) with a capability of up to 1350 t/h when
processing selected feed types.
CPP2 largely mirrors CPP 1 with the following exceptions.
●
minus 12 mm size fraction. This functionality directs the higher ash, coarse fraction directly to the
secondary dense medium circuit reducing the circuit loading of the primary circuit.
●
stream from the spirals circuit is directed to a splitter box which allows the recovered product to be
diverted to either the primary product or secondary product streams via the screen-bowls or fine coal
centrifuges respectively.
Page 90 of 118
Figure 14-1: Aerial view of the CHPP facilities and associated infrastructure
Page 91 of 118
14.1.0 Raw Coal Handling
The 22 km overland conveyor from Curragh North is an integral component of the coal transportation and
logistics system at the Curragh operation. The two ROM systems are important features of the mine operations
to ensure blending of the ROM coals for the CPPs. A series of conveyors, a ROM crushed stockpile and small
ROM bins allows flexibility in the operations of the two CPPs.
14.1.1 Product Handling
Product coal is stockpiled on to either the primary or secondary product stockpiles. Two stockpiles of
approximately 190,000 tonnes each are available for metallurgical and thermal coal products. Multiple
stockpiles of differing quality can be built on the overall stockpile footprint and reclaimed discretely by means
of the 4400 t/h bucket wheel reclaim system. The two installed product stackers have the capability to slew
180 degrees and stack to an emergency stockpile area. The emergency stockpile area is not able to be
recovered directly but is transferred by truck and loader operation to the main stockpiling area to be reclaimed
by the bucket wheel reclaim system.
14.1.2 Train Loadout
The processed coal is loaded onto trains via a single dedicated bucket wheel reclaimer which loads two 580 t
capacity bins, designed to load both thermal and metallurgical coal. In an emergency, there is a dozer push
loading system in place should there an electrical outage at the mine site, which reduces the risk of train
loading system.
14.1.3 Reject and Tailings
Coarse reject is conveyed from each CPP to a common reject bin for collection by mine trucks and deposited
in the allocated reject dump, as capping material for the tailings dam or as part of the rehabilitation process.
Flotation tailings material is passed through thickening cyclones with the underflow directed to a fine coal
dewatering screen for dewatering. The screen overflow is combined with the coarse reject material and
conveyed to the reject bin. The remaining flotation tailings material from either CPP is directed to dedicated
tailings thickeners with the underflow pumped to the tails storage facility (TSF). The LOM TSF is currently a
project in progress assessing the use of the void at Pit B. Water recovered from the in-pit TSF is included as
part of the site water balance model and is reused within the site to offset the volume of purchased raw water.
14.1.4 Operating performance
The two processing plants have a nominal nameplate throughput capacity of 2300 t/h on a combined basis,
with a surge capacity on selected coal feeds to 2350t/h. Applying the nominal throughput capacity with a
planned 7400 operating hours per annum the capacity of the CHPP’s at Curragh would be as seen in Table
14.1. This is consistent with the LOM plan annual production rates planned from the combined Open Cut and
Underground mining complex at Curragh.
Table 14.1: CHPP Capacity
CHPP
Nameplate
Feed (t/hr)
Operating
Hours (per
year)
Feed Capacity
(Mtpa)
Forecast
Yield (%)
Total Product
Capacity(Mtpa)
1
1,100
7,400
8.1
79
6.4
2
1,200
7,400
8.9
79
7.0
TOTAL
2,300
7,400
16.5
79
13.4
Historical operating performance indicates that the combined facilities have achieved a maximum processed
throughput of 15.2 Mtpa ROM feed in recent years and would require further increases in utilised hours to be
achieved to exceed this value. The ability to bypass selected raw feed material directly as a thermal product
is considered an accepted site practice and where quality shortfalls are realised can be blended with washed
thermal product to achieve the required product specification and the required annual product volumes.
Page 92 of 118
15 Infrastructure
Curragh owns and operates the necessary coal load-out system for dispatches via rail line to the port at
Gladstone or the Stanwell Power Plant. Moreover, the mine has maintenance facilities for the fleet of mining
equipment as well as office buildings for the mine staff and personnel.
15.1.0 Water
Curragh obtains its water requirement from two main sources:
Pursuant to a supply agreement with SunWater Ltd (“SunWater”) from the Bedford Weir and Fairburn Dam.
Curragh is permitted to draw up to 708 M gallons per year through a take or pay offtake agreement with
SunWater. Mine water recycling can significantly reduce the need for importing purchased water into the
stored mine water inventory.
Pollution control dams and old pit voids capture rainfall and mine affected water from pit dewatering activities.
15.1.1 Power
Curragh has a dedicated 66kv power supply to support the mining operations with a capacity of up to 57MW
sourced from the main grid power. The substation is located on the southwest corner of the lease and both
66kv and 22kv distribution networks to supply the draglines, shovel and CHPP’s. Part of the site electrical
system was upgraded in 2015 at the time of upgrading the ROM crushing station.
The electrical power requirements for the Underground Mine have been determined. Studies have shown there
is adequate power on site for establishing the underground mine and commencing the first two continuous
miner Units, however upgrades to the site infrastructure for full underground production with four continuous
miner units is required.
A load study is being undertaken for Curragh site to determine the required upgrades for the Open Cut and
Underground LOM. Once completed, the required 66kv power line and infrastructure upgrades must be
completed before full underground production to sustain safe and effective underground operations
15.1.2 Roads
Curragh has a network of haul roads and ramps connecting the various working areas of the operation.
Established national highways such as Route A4 (Capricorn Highway) connect nearby regional towns of
Blackwater and Emerald to the regional city of Rockhampton to the East. Site access from the Capricorn
Highway is via sealed road to the Curragh Mine Industrial Area main carpark.
15.1.3 Rail
Curragh is linked to the main Blackwater rail link to the Port of Gladstone’s RG Tanna Coal Terminal (RG
Tanna) and Wiggins Island Coal Export Terminal (WICET) coal terminals by dedicated rail balloon loop with a
Marketable Coal capacity of 14 million tonnes per year. Train capacity averages 8,500 tonnes at a loading
capacity of 4,400 t/h with an average 28 trains loaded every week (with a maximum capacity of 36 trains).
Curragh is located 290 km from the Port of Gladstone. Under an existing agreement, CCPL has the right to
rail up to 11.0 Mtpa, plus surge of rail capacity on the Blackwater system. This network is operated by Aurizon
and links Central Queensland mines from the Bowen Basin to two export terminals at the Port of Gladstone –
RG Tanna and WICET, under two long term rail haulage agreements with Aurizon.
Domestically, Curragh’s steam coal is railed 160 km to the Stanwell Power Station near Rockhampton. Under
the Stanwell Coal Supply Agreement, Stanwell is responsible for the transport of the steam coal from Curragh
to the power station and pays for the railing costs.
Page 93 of 118
15.1.4 Port
Curragh’s export coal is shipped either from RG Tanna or WICET terminals at Gladstone. The coal is blended
at the port to meet market requirements.
There are agreements in place for approximately 8.6 million tonnes per year in exports from RG Tanna and a
take or pay agreement with WICET for 1.5 million tonnes per year. There is sufficient capacity to increase
these capacities as required.
Figure 15-1: Curragh Preparation Plant Infrastructure
Page 94 of 118
16 Market studies
16.1 Market Description
Coronado maintains a specialist corporate marketing team that focusses on direct sales of Curragh products
to steel mills in all major international markets. Curragh coals are widely technically tested and approved for
use in coke making blends, with product positioning optimised over many years (40 years) in the
market. Curragh coals are widely known for their low ash, low to mid volatile matter, low Sulphur and low
Phosphorous content. Curragh Metallurgical Coal products are also known for their consistent delivered quality
which supports a consistent offtake across a diversified market base.
Table 16.1: Coal Quality for Washed Products
Seam
Primary
Yield (%)
Secondary
Yield (%)
CSN
Primary
Comments
Cancer
~30 @ 9% Ash
30
7 - 8
~0.5m thick. Typically, a Coking Coal blend
Aries
~50 @ 9% Ash
20 - 30
6 - 7
Aries Lower has better Coking Coal properties
and higher CSN than Aries Upper, also has
fluidity 50-100 ddpm. Aries Upper typically
produces a high-ash blend PCI.
Castor Lower
45 - 50 @ 8% Ash
30 - 35
7 - 8
A high quality coking coal seam with strong
swelling and plastics and an important coking
coal blend component. Good middlings blend
product for steam coal.
Pollux
~45 @ 7% Ash
30 - 35
6.5 - 7.5
A low ash Coking coal blend coal, Pollux has
low plastic properties. The middlings product is
a key high Ash PCI blend component.
Pisces Working
Section
UWS: ~80 @ 9%
Ash, mainly PCI
-
<3
Split into upper working section (UWS) and
lower working section (LWS). The UWS
products a low ash PCI product for PCI blend.
The LWS middlings typically produces a high-
ash (12%) PCI.
LWS: ~45 @ 7.5%
Ash
30 - 35
6.5 - 7.5
Page 95 of 118
16.2 Price Forecasts
In selecting forward prices for Curragh’s products, Coronado has had regard to price index forward curve as
well as prices forecasts prepared by several brokers and coal industry analysts. For the purpose of this
analysis, Coronado has adopted price benchmark forecasts from a reputable coal market research company
as base case. The projected index price benchmark was then adjusted to reflected realised prices for Curragh’s
products taking into account historical price relativities, recent price negotiations and the product mix strategy
expected to be pursued over the mine life.
Domestic thermal sales tonnes are sold to Stanwell based on the Stanwell Coal Supply Agreement described
in 16.3
Average realised product coal price projections over the LOM for Curragh are set out in Table 16.2.
Table 16.2: Coal Pricing (Real US$/t sold)
16.3 Contract Requirements
Material contracts considered in the economic evaluation of Curragh include:
Stanwell
Coronado are party to contractual arrangements with Stanwell, including a Coal Supply Agreement, or the
CSA, and the Curragh Mine New Coal Supply Deed, dated August 14, 2018, or the Supply Deed.
Under the CSA, Coronado deliver thermal coal from Curragh to Stanwell at an agreed price and quantity.
Stanwell may vary the quantity of thermal coal purchased each year so the total quantity to be delivered to
Stanwell each year cannot be precisely forecast. The coal that Coronado supplies to Stanwell constitutes the
majority of the thermal coal production from Curragh. The cost of supplying coal to Stanwell has been greater
than the contracted price paid by Stanwell during the year ended December 31, 2023 and for prior years.
Under the CSA, Coronado also share part of the revenue earned from export Met coal sales (from particular
Tenements (as defined below)) with Stanwell through various rebates. The most material rebate is the export
price rebate, which is linked to the realized export coal price for a defined Met coal product, as follows:
●
export coal price of Reference coal exceeds the Tier 1 Rebate Coal Floor Price, Coronado pays a
rebate of 25% of the difference between the realized export coal price and the Tier 1 Rebate Coal
Floor Price.
●
coal price of Reference coal exceeds the Tier 2 Rebate Coal Floor Price, Coronado pays a rebate of
10% of the difference between the realized export coal price and the Tier 2 Rebate Coal Floor Price.
Page 96 of 118
The CSA also provides for:
●
a
tonnage rebate to Stanwell per Mt on the first 7.0 MMtpa of export coal sales and on export coal
sales above 7.0 MMtpa; and
●
The total Stanwell rebate for the year ended December 31, 2023, was $136.5 million and has been included
in the Consolidated Statements of Operations and Comprehensive Income included elsewhere in the
Coronado Annual Report on Form 10-K.
The Supply Deed grants Coronado the right to mine the coal reserves in the Stanwell Reserved Area, or the
SRA. In exchange, Coronado agrees to certain amendments to the CSA and to enter into a New Coal Supply
Agreement, or the NCSA upon the expiration of the CSA (which is expected to occur in 2027). On July 12,
2019, Coronado entered into the NCSA with Stanwell. The following are the key terms under the NCSA:
●
-
-
-
●
‘Tonnes Equivalent’ of thermal coal per annum (based on a nominal gross calorific value of 25.6GJ)
at a fixed contract price that varies in accordance with agreed formulae, inclusive of all statutory
charges and royalties in respect of coal sold and delivered under the NCSA;
●
The supply term, the contract tonnage and the contract price under the NCSA are subject to adjustment in
accordance with a financial model agreed between Stanwell and Coronado. In summary, Coronado have
agreed that the total value of the discount received by Stanwell on coal supplied to it under the NCSA should
(by the expiry date of the NCSA) be equal to the net present value of $155.2 million (A$210.0 million) as at the
date of the Supply Deed, using a contractual pre-tax discount rate of 13% per annum. The net present value
of the deferred consideration was $277.4million as of December 31, 2023. On January 18, 2021, the Option
Coal Supply Agreement, or the OCSA, contemplated by clause 5 of the NCSA was entered into, in respect of
the supply of certain additional coal to Stanwell during the term of the NCSA.
Logistics
Curragh typically sells export coal FOB, with the customer paying for transportation from the outbound shipping
port. The majority of Curragh’s export Met coal is railed approximately 300 kilometers to the Port of Gladstone
for export via two main port terminals, RG Tanna Coal Terminal, or RGTCT, and Wiggins Island Coal Export
Terminal, or WICET. Curragh also has capacity available to stockpile coal at the Port of Gladstone. For sales
of thermal coal to Stanwell, Stanwell is responsible for the transport of coal to the Stanwell Power Station.
Rail Services
Curragh is linked to the Blackwater rail line of the Central Queensland Coal Network, or CQCN, an integrated
coal haulage rail system owned and operated by Aurizon Network Pty Ltd., or Aurizon Network. Curragh has
secured annual rail haulage capacity of up to 12.0 MMtpa (plus surge capacity) under long-term rail haulage
agreements with Aurizon Operations Limited, or Aurizon Operations, and Pacific National Holdings Pty Limited,
or Pacific National.
The RGTCT Coal Transport Services Agreement with Aurizon Operations is for 8.5 MMtpa of haulage capacity
to RGTCT. Curragh pays a minimum monthly charge (components of which are payable on a take-or-pay
basis), which is calculated with reference to the below-rail access charges, haulage/freight charges, a
Page 97 of 118
minimum annual tonnage charge and other charges. The RGTCT Coal Transport Services Agreement
terminates on June 30, 2030.
The Coal Transport Services Agreement with Pacific National is for 1.0 MMtpa of haulage capacity to RGTCT.
Curragh pays a minimum monthly charge (components of which are payable on a take-or-pay basis), which is
calculated with reference to the below-rail access charges, haulage/freight charges, a minimum annual
tonnage charge and other charges. The Coal Transport Services Agreement with Pacific National terminates
on July 31, 2029.
The Wiggins Island Rail Project, or WIRP, Transport Services Agreement with Aurizon Operations is for 2.0
MMtpa of capacity to WICET. This contract is effectively 100% take-or-pay (for a portion of the rail haulage
and all capacity access charges). This agreement expires on June 30, 2030.
Port Services
Curragh exports coal through two terminals at the Port of Gladstone, RGTCT and WICET. At RGTCT, Curragh
and Gladstone Port Corporation Limited, or GPC, are parties to a coal handling agreement that expires on
June 30, 2030. The agreement may be renewed at our request and, subject to certain conditions, GPC is
required to agree to the extension if there is capacity at RGTCT to allow the extension. Coronado currently
have the right to export between 7.7 MMtpa and 8.7 MMtpa at Coronado’s nomination on a take-or-pay basis.
Coronado have a minority interest in WICET Holdings Pty Ltd, whose wholly-owned subsidiary, Wiggins Island
Coal Export Terminal Pty Ltd, or WICET Pty Ltd, owns WICET. Other coal producers who export coal through
WICET also hold shares in WICET Holdings Pty Ltd. In addition, Coronado and the other coal producers (or
shippers) have take-or-pay agreements with WICET Pty Ltd and pay a terminal handling charge to export coal
through WICET, which is calculated by reference to WICET’s annual operating costs, as well as finance costs
associated with WICET Pty Ltd’s external debt facilities. Coronado’s take-or-pay agreement with WICET
Pty Ltd, or the WICET Take -or-Pay Agreement, provides Curragh with export capacity of 1.5 MMtpa. The
WICET Take -or-Pay Agreement is an “evergreen” agreement, with rolling ten-year terms. If we inform WICET
Pty Ltd that we do not wish to continue to roll the term of the WICET Take -or-Pay Agreement, the term would
be set at nine years and the terminal handling charge payable by us would be increased so that our proportion
of WICET Pty Ltd’s debt is amortized to nil by the end of that nine-year term.
Under the WICET Take -or-Pay Agreement, Coronado are obligated to pay for that capacity via terminal
handling charges, whether utilized or not. The terminal handling charge payable by Coronado can be adjusted
by WICET Pty Ltd if our share of WICET Pty Ltd’s operational and finance costs increases, including because
of increased operational costs or because another shipper defaults and has its capacity reduced to nil. The
terminal handling charge is subject to a financing cap set out in the terminal handling charge methodology and
has already been reached and is in force. If another shipper defaults under its take-or-pay agreement, each
remaining shipper is effectively proportionately liable to pay that defaulting shipper’s share of WICET Pty Ltd’s
costs going forward, in the form of increased terminal handling charges.
If Coronado default under the WICET Take -or-Pay Agreement, Coronado would be obligated to pay a
termination payment to WICET Pty Ltd. The termination payment effectively represents our proportion of
WICET Pty Ltd’s total debt outstanding, based on the proportion of our contracted tonnage to the total
contracted tonnage of shippers at WICET at the time the payment is triggered. Shippers can also become
liable to pay the termination payment where there is a permanent cessation of operations at WICET. Since
WICET began shipping export tonnages in April 2015, four WICET Holdings Pty Ltd shareholders have entered
into administration and Take -or-Pay Agreements subsequently terminated, resulting in the aggregate
contracted tonnage of shippers decreasing from 27 MMtpa to 15.5 MMtpa.
Under the WICET Take -or-Pay Agreement, Coronado is required to provide security (which is provided in the
form of a bank guarantee). The amount of the security must cover Coronado’s estimated liabilities as a shipper
under the WICET Take -or-Pay Agreement for the following twelve-month period. If Coronado is in default
under the WICET Take-or-Pay Agreement and are subject to a termination payment, WICET Pty Ltd can draw
on the security and apply it to amounts owing by Coronado .
Page 98 of 118
Thiess Mining Services Contract
Thiess Pty Ltd has provided mining services to Curragh at Curragh North since 2004 and currently operate
five excavator fleets. The current contract expires at the end of December 2025. The mining services contract
includes overburden removal and haulage, mining, equipment maintenance and pit dewatering.
Golding Mining Services Contract
Golding Contractors Pty Ltd has provided mining services to Curragh at Curragh Main since 2014 and currently
operate six excavator fleets. The current contract expires at the end of December 2026. The mining services
contract includes overburden removal and haulage, mining and equipment maintenance.
Page 99 of 118
17 Environmental studies, permitting, and plans, negotiations,
or agreements with local individuals or groups
17.1 Results of Studies
Prior to securing the existing relevant Queensland and Commonwealth approvals for Curragh, the necessary
environmental and cultural heritage studies have been completed. Additional environmental studies are
progressing to support relevant approval requirements for future underground mining.
Besides mining, the area affected by the Curragh project is used essentially for low intensity cattle grazing
plus some amount of dryland cropping. Most of the land within the area is currently disturbed as a result of
historical grazing and mining activities. The property has been the subject of extensive activities prior to
Curragh.
Curragh has complied with environmental and heritage requirements under relevant Queensland and
Commonwealth legislation and adheres to standard practices for environmental management set for all coal
mines in central Queensland, including mitigation of impacts on cultural heritage. There have been some
adverse incidents, however, the main ones being spills of diesel fuel (87,000 litres in 2016 and 25,000 litres in
2017), as well occasions of minor uncontrolled or non-compliant water releases. Corrective measures have
remediated these incidents where required. Remediation of the main diesel spills is ongoing.
17.2 Requirements and Plans for Waste Disposal
General and Hazardous (Regulated) solid waste at Curragh is the object of a mandatory management plan
under the environmental license. General waste is disposed at an approved landfill site at Curragh, while all
regulated waste is transported and treated offsite in an environmentally appropriate manner and in compliance
with the Queensland regulations. The mine infrastructure includes two Sewage Treatment Plants (STP)
subject to conditions in the environmental license and with the necessary site procedures in place. These
STPs process effluents from all office and camp/accommodation facilities.
Industrial waste (tailings) from the CHPP is disposed of in regulated structures. There are three TSF’s at
Curragh, two in-pit and one conventional above ground TSF. The above ground TSF is the original, complete
and non-operational facility. In-pit TSF is the process of backfilling abandoned pits, this is currently the
preferred method by the regulator. Pit A TSF has limited remaining capacity and is non-operational while Pit
B TSF is an active facility with storage capacity of significant volume remaining and thus provides long-term
security for tailings storage. These locations are shown in Figure 17-1. All regulated structures are subject to
ongoing inspection by Curragh and annual inspections by an independent Registered Professional Engineer
of Queensland (RPEQ).
Page 100 of 118
Figure 17-1: Mine Waste Disposal Areas
17.3 Permit Requirements and Status
All applicable environmental licenses and permits under both the Queensland and Commonwealth legislation
have been secured and are in place for approved open-cut operations. Work is in progress to meet the
approved open-cut pre-mining requirements for ML’s 700006, 700007, 700008, and 700009.
An amendment to the state-based Queensland Environmental Authority is required for underground mining.
Preparation for an Environmental Authority amendment application lodgement is progressing. No
Commonwealth based approvals are expected. There are no perceived issues expected to prevent securing
any future permits.
Page 101 of 118
17.4 Local Plans, Negotiations or Agreements
Curragh has five environmental management areas that are requirements of conditions of approval under the
two separate referrals under the Commonwealth EPBC Act 1999 Under Commonwealth requirements,
Curragh has also provided a biodiversity offset at Mt. Flora, near Nebo in Central Queensland. Further
biodiversity offsets are required under obligations related to the Commonwealth and State approvals for
ML700007 and ML700008 and are in progress.
Curragh negotiated a CHMP in 2012. This plan was subsequently repealed and replaced by the 2017 CHMP
with the statutory Aboriginal parties for the area to allow access for mining activities. A Services Agreement
signed in December 2017 details the fee schedule for services such as cultural heritage survey and mitigation
prior to mining and exploration activities by Curragh. These agreements comply with the legislation and are
within industry standards. All cultural heritage sites are protected and subject to mitigation, however there are
currently no identified sites of significant cultural heritage value.
With reference to native title, the Queensland Government coordinates the application process for Resource
authorities and advises on land that may be subject to native title. To date none of the Curragh Mining Leases,
other than ML80123, require native title processes for its grant. However, most areas in central Queensland
are subject to an undetermined Native Title Claim and the determination of native title may affect existing or
future mining activities at Curragh.
17.5 Mine closure plans and associated costs
Queensland legislation requires that all mining activities approved through a site-specific environmental
authority develop a Progressive Rehabilitation and Closure Plan (PRCP). The main purposes of the PRCP are
to plan for how and where mining activities will be carried out in a way that maximises progressive rehabilitation
and to detail the condition to which the land must be rehabilitated prior to relinquishment.
The Curragh Project PRCP has been developed in accordance with the legislative requirements and was
submitted by Coronado Curragh on 21 October 2022 to the administering authority, the Department of
Environment and Science (DES) for assessment. DES reviewed and subsequently issued a Request for
Information Notice (RFI). Coronado Curragh submitted a response addressing the RFI on the 20 November
2023. DES has extended the period for deciding the application to 2 February 2024. The PRCP will include
post-mining land uses, rehabilitation methodologies, community consultation requirements, supporting
technical studies and a schedule outlining when rehabilitation will occur. The Curragh Project is approved to
have residual voids in the post-mining landform.
Estimated costs for mine closure, including removal of infrastructure, contaminated land investigations and
remediation, reshaping and rehabilitation works, monitoring and maintenance and a 10% contingency, have
been undertaken using a government estimated rehabilitation cost calculator. This cost was updated in 2022
and as required by legislation; an appropriate financial provision contribution has been lodged with the
Queensland State Government. Curragh has recognised a provision for Asset Retirement Obligation (ARO) of
$70.2million based on disturbances to date as disclosed in Coronado’s Form 10K for the fiscal year ending 31
December 2023.
17.6 Commitment to local hiring
Curragh has a long association with the Blackwater community. Since the mine opened in 1983, many
employees and their families have lived in Blackwater, and through this connection Curragh has been a major
supporter of the Blackwater community.
Curragh’s community engagement includes providing support across community organisations, health care,
education, sport, culture, indigenous communities and local tourism. Curragh is proud to support the
development of a strong, healthy and vibrant Blackwater community.
Respecting and preserving Indigenous cultural heritage is important to Curragh. Curragh holds regular co-
ordination meetings with representatives of the local Indigenous communities and educates its employees and
contractors on the importance and significance of Aboriginal heritage and culture.
Page 102 of 118
Coronado has long standing relationships with the communities surrounding Curragh. Many of the Coronado
employees live near Curragh and benefit from Coronado’s social partnerships and investments. As at 31
October 2023, Curragh employed over 485 permanent employees. The majority of permanent employees are
based in nearby Blackwater regional township with other staff located in the Brisbane office. Additionally, circa
3500 contractor employees regularly supplement the permanent workforce.
17.7 Qualified Person ’s Opinion
It is the Qualified Person’s opinion (Daniel Millers) that the approach taken to manage environmental
compliance, community impacts and permitting is sufficient to not raise any concerns with the open cut LOM
plan and Coal Reserve estimate in this TRS. There are some secondary approvals required as outlined in 17.3
above, that will need to be in place before overburden waste stripping commences in the X and Z pit
development areas. This is currently planned in this LOM plan for 2030 and 2031 respectively.
It is the Qualified Person’s opinion (Chris Wilkinson) that appropriate approvals for underground mining will be
obtained based on the feedback provided by Coronado.
The planned workings of the Southern area of the underground project in the Mammoth Seam extend under
the environmental offset area within ML 80123. A major amendment will be made to current Environmental
Authority (EPML00643713) for the inclusion of underground mining activities. This major amendment is
supported by an Environmental Assessment Report (EAR) which will be submitted to the Department of
Environment and Science (DES) in early 2024. It is anticipated that the approval of the major EA amendment
to support project commencement will be achieved in December 2024.
Page 103 of 118
18 Capital and Operating Costs
18.1 Capital Cost Estimate
The production sequence selected for a property must consider the proximity of each reserve area to coal
preparation plants, and railroad loading points, along with suitability of production equipment to coal seam
conditions. Existing in-place infrastructure was evaluated, and any future needs were planned to a level
suitable for economic reserves production including assessment of sustaining and development capex to allow
entry into new open pit mining areas.
A summary of the estimated capital costs for the Property is provided in Figure 18-1 below.
Figure 18-1: CAPEX US$ million (nominal)
Exploration, development and expansion capital expenditure for the period between 2024 and 2026 are
associated primarily with the underground project (c. US$ 105 million) and planned boxcut development (c
US$ 31million). From 2028 to 2032, exploration, development and expansion capex are associated with the
developments of X and Z pits in the open cut mine plan (c. US$ 319 million).
The development and expansion capital cost estimates for both the open cut and underground mines at
Curragh are currently completed to a Pre-Feasibility Study level at +/-25% level of accuracy. The proposed
startup location for the underground mine in the Mammoth seam has a more detailed capital development cost
estimate undertaken at a Feasibility level of study with an accuracy level of +/-15%.
18.2 Operating Cost Estimate
Curragh’s costs estimates are based on expected operational productivity and associated fixed and variable
costs which have been projected having regard to a number of factors including existing and estimated contract
rates for both upstream and downstream costs, forecast exchange rate, impact of inflation on costs, among
other macroeconomic conditions impacting the business. Unit rates by activities are assessed in detail for site
budget preparations and long term averages adjusted for inflation are applied to future periods for the life of
mine. Operating costs include calculation of Queensland state royalties applied to sales revenue and
calculated within mandated tiers as well as contractual rebates paid to Stanwell as per the CSA.
The operating costs for the open cut mine are at a high level of accuracy supported by supply contracts for
material goods and services including offsite logistics and existing mining costs from the open cut operation.
The forecasted LOM open cut costs have been benchmarked against actuals and budget costs for the open
cut operation to ensure validity in this LOM financial model. The level of accuracy for the open cut operating
costs would be described as detailed budget level costs for 2024 and 2025 years at +/- 10%. For 2026 and
beyond the LOM open cut operating costs are at a Feasibility Study level detail at +/- 15% level of accuracy.
Page 104 of 118
The underground LOM operating costs are project level cost estimates as there is no existing operating mine
at Curragh to benchmark or reconcile against. The Curragh underground operating costs are at a Pre-
Feasibility Study level of accuracy of +/-25%.
A summary of nominal operating costs is provided in Figure 18-2.
Figure 18-2 : Curragh Operating Cost Profile (nominal)
19 Economic Analysis
19.1 Assumptions, Parameters and Methods
The Mine plan, productivity expectations and cost estimates generally reflect historical performance by
Coronado and efforts have been made to adjust plans and costs to reflect future conditions and comply with
contractual obligations.
The financial model, prepared for this TRS, was developed to test the economic viability of the Coal Reserve
estimate. The results of this financial model are not intended to represent a bankable feasibility study, required
for financing of any current or future mining operations, but are intended to prove the economic viability of the
estimated Coal Reserves.
On an unlevered basis, the NPV of the project cash flows after taxes was estimated for the purpose of
classifying Coal Reserves. The project cash flows, excluding debt service, are calculated by subtracting direct
and indirect operating expenses and capital expenditures from revenue. Revenue is derived from long term
forward price estimates observed at December 2023. Both upstream and downstream costs are calculated
based on site knowledge of costs profiles and contractor obligations. Net cash flows incorporate applicable
state and federal taxes plus progressive reclamation obligations to the end of mine closure. All cash flows are
denominated in nominal USD incorporating inflation of 2.5% in FY24 and 2.0% thereafter.
All figures are reported in USD millions unless otherwise stated and volume related data is reported on a metric
tonne basis. The net present value of the projected cash flows have been calculated adopting a 10% post-tax
discount rate.
The projection model also includes notional income tax calculations at the Curragh level adopting a federal tax
rate of 30%. To the extent the mine generates net operating losses for tax purposes, the losses are carried
over to offset future taxable income. The terms “cash flows” and “project cash flows” used in this report refer
to after tax, unlevered cash flows.
Page 105 of 118
19.2 Results
A base case NPV of US$1.1 billion is based on life of mine average exchange rate of 0.69 which has been
assessed having regard to exchange rate forward curves, economic specialists forecasts and broker
consensus as at 31 December 2023.
Annual cash flows based throughout mine life to final reclamation and make good on assumptions applied is
provided in Figure 19-1.
Figure 19-1: Project Post Tax Net Cash Flow Summary (Millions)
US$ million
(nominal)
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
Rest of
LOM
EBITDA
113
76
133
224
310
364
314
334
318
347
4,509
Payable income tax
(5)
0
(7)
(43)
(63)
(78)
(59)
(63)
(57)
(73)
(1,010)
Change in working capital
5
55
(29)
15
(17)
7
(1)
(6)
2
(5)
(120)
Capex
(105)
(99)
(92)
(64)
(115)
(123)
(153)
(151)
(148)
(80)
(921)
Rehabilitation costs
(9)
(5)
(4)
(4)
(5)
(4)
(5)
(9)
(8)
(9)
(389)
Free cash flow
(2)
27
1
128
110
166
96
106
106
179
2,070
The results of this financial model are not intended to represent a bankable feasibility study, as may be required
for financing of any current or future mining operations contemplated but are intended to prove the economic
viability of the estimated Coal Reserves.
Cash flows are sufficient to support identified economic reserves.
19.3 Sensitivity
Sensitivity of the NPV results to changes in the key drivers is presented in Table 19.1. The sensitivity study
shows the NPV at the 10% discount rate when Base Case sales prices and exchange rates increased and
decreased in increments of 5%.
Table 19.1: Sensitivity of NPV (USD billions)
Price/FX
-5%FX
Base
+5% FX
+5% Price
$1.8
$1.5
$1.2
Base
$1.4
$1.1
$0.8
-5% Price
$0.9
$0.6
$0.3
Page 106 of 118
20 Adjacent properties
20.1 Information Used
No Proprietary information associated with neighbouring properties was used as part of this study.
Page 107 of 118
21 Other relevant data and information
This document applies solely to the Curragh mining operations and no other relevant data or information were
contemplated in its findings.
Page 108 of 118
22 Interpretation and conclusions
22.1 Conclusion
Upon completion of these studies and analyses of the Curragh project, the authors have reached the
conclusion that the Coal Resource and Reserve estimates and related findings presented in this TRS are
reasonably accurate and representative of the property conditions. The data has been interpreted according
to industry standards, geostatistics was used to estimate resource tonnes and qualities away from drill holes
according to the level of confidence as drill hole spacing outlined in this report. Reserve estimates were derived
from the defined Coal Resource considering relevant mining, processing, infrastructure, economic (including
estimates of capital, revenue, and cost), marketing, legal, environmental, socio-economic and regulatory
modifying factors.
22.2 Significant Risk Factors
The purpose of the characterization of the project risk components is to inform the project stakeholders of key
aspects of the Curragh project that can be impacted by events whose consequences can affect the success
of the venture. The significance of an impacted aspect of the operation is directly related to both the probability
of occurrence and the severity of the consequences. Risk can be ranked numerically, derived from the values
assigned to probability and consequence ranging from very low risk to very high risk.
The probability and consequence parameters are subjective estimates made by the Qualified Persons’
authoring this report. Consequence estimates are assigned numerical values from 1 to 5 for which the value
1 represents the highest consequence, and the value 5 represents the lowest. Probability estimates are
assigned alphabetical values from A to E with A representing the highest probability of occurrence and E
representing the lowest probability. The combination of Consequence and Probability rankings are used to
assign the Risk Level classified from Very High to Low risk.
22.2.0 Governing Assumptions
The listing of the aspects is not presumed to be exhaustive. Instead that listing is presented based on the
experiences of the contributors to the TRS.
The probability and consequence ratings are subjectively assigned, and it is assumed that this subjectivity
reasonably reflects the condition of the active and projected mine operations.
The Control Measures shown in the matrices presented in this chapter are not exhaustive. They represent a
condensed collection of activities that the author of the risk assessment section has observed to be effective
in coal mining scenarios.
Mitigation Measures listed for each risk factor of the operation are not exhaustive. The measures listed,
however, have been observed by the author to be effective.
The financial values used in ranking the consequences are generally accepted quantities for the coal mining
industry.
22.2.1 Limitations
The risk assessment in this report is subject to the limitations of the information currently collected, tested, and
interpreted at the time of the writing of the report.
22.2.2 Development of the Risk Matrix
Risks have been identified for the technical, operational, and administrative subjects addressed in the TRS.
The risk matrix and risk assessment process are modelled according to the Coronado group Risk Management
Policy.
Page 109 of 118
22.2.2.1 Consequence and Probability Level Tables
The Likelihood Table 22.1 was sourced from the Coronado Group Risk Management Policy dated 16th
February 2023.
Table 22.1: Likelihood/Probability Level Table
Cat.
Likelihood
Description
A
Almost Certain
May occur more than once in a year
B
Likely
May occur over a one to two-year period
C
Possible
May occur within a five-year period
D
Unlikely
May occur within a 10-year period
E
Rare
May occur within a 30-year time period
Page 110 of 118
The Consequence Level Table 22.2 was sourced from the Coronado Group Risk Management Policy dated 16th February 2023.
Table 22.2; Consequence Level Table
#
FL Category
Safety
Environment
Reputation
Production
Financial
5
Catastrophic
Multiple fatalities.
Unplanned permanent
environmental impact over
extensive area.
Permanent loss of
ecosystem or extinction of
species.
Serious and long-term
damage to corporate
reputation through the loss
of trust and respect across
all stakeholder groups and
the general public.
Lost production by more
than 2 million tonnes.
Breach of bank covenants.
Unable to make payment to
employees in accordance
with agreed terms.
Reduces revenue or
increases cost by more
than US$ 200 million.
4
Major
Single fatality and/ or
Severe irreversible disability
or impairment (>30% of
body) to one or more
persons.
Severe impact (>20 years)
on ecosystem or
Threatened Species.
Serious and long-term
damage to corporate
reputation through the loss
of trust and respect of one
or more key stakeholder
groups and the general
public.
Lost production of 1 to
2 million tonnes.
Unable to pay contractors in
accordance with agreed
terms
Reduces revenue or
increases cost by between
US$ 100 million to US$
200 million
3
Moderate
Severe irreversible disability
or impairment (<30% of
body) to one or more
persons.
Serious or extensive impact
(<20 years) on ecosystem
or Threatened Species.
Short-term corporate
reputation damage through
the loss of trust and respect
limited to one or more key
stakeholder group.
Lost production of 0.5 to
1 million tonnes.
Reduces revenue or
increases cost by between
US$ 50 million to US$
100 million
2
Minor
Lost time injury/ies.
Major impact (<5 years) on
ecosystem or Threatened
Species
Short-term corporate
reputation damage through
the loss of trust and respect
limited to one key
stakeholder group.
Lost production of 0.1 to
0.5 million tonnes.
Reduces revenue or
increases cost by between
US$ 5 million to US$
50 million
1
Insignificant
Medical treatment case(s).
Minor impact (< 3 months)
to non-threatened species
or their habitat
Small impact on corporate
reputation through some
loss of trust and respect –
minor and isolated
expression of concern.
Lost production of less than
0.1 million tonnes.
Reduces revenue or
increases cost by less than
US$ 5 million.
Page
111
of 118
22.2.2.2 Composite Risk Matrix and Color-Code Convention
The risk matrix in Table 22.3 is sourced from the Curragh site Safety and Health Management System
(SHMS) Workplace Risk Assessment and Controls (WRAC) template form. This 5x5 matrix uses the
consequence and likelihood values to identify and colour code risk categories from a Low (green) to
Very High (red) Risk Rating.
Table 22.3: Risk Matrix
CONSEQUENCE
Loss Type
1 -
Insignificant
2 - Minor
3 - Moderate
4 - Major
5 -
Catastrophic
Likelihood
Risk Rating
A
- Almost
Certain
Medium
High
High
Very High
Very High
B - Likely
Medium
Medium
High
High
Very High
C - Possible
Low
Medium
High
High
High
D - Unlikely
Low
Low
Medium
High
High
E - Rare
Low
Low
Medium
Medium
High
Page 112 of 118
22.2.2.3 Risk Assessment
Table 22.4: Risk Assessment
IDENTIFICATION
C
L
Risk
Ratin
g
RISK
TREATMENT
Discipline
Risk Factors
Consequence
s
Risk treatment
strategy
Mining
Equipment
productivity
assumptions
unrealistic or
cannot be
achieved
Production
schedule
unachievable
and increased
cost/t driving
down project
valuation.
Reserve loss
from this.
3
C
H
Reconciling
planned
productivities in
LOM plan against
historical actuals
from the
operation.
Significant
flood event
overtopping 1
in 100yr levees
on site –
inundation of
underground
operations
Loss of
production for
duration
required to
dewater
operation
5
E
M
Site inclement
weather TARP’s
and site SHMS
Unplanned
inrush of water
from
underground
mining under
Blackwater
Creek
Loss of
production for
duration
required to
dewater
operation
5
D
H
Exploration and
fault delineation
drilling and
modelling and
inclusion in UG
mine plan
Lower than
predicted
permeability
causing
ineffective gas
drainage in
underground
operations
Loss of
Reserves as
cannot be
mined safely or
economically
Potential gas
outburst
4
C
H
Exploration and
testing – gas
drainage
requirements
Operational
systems – Permit
to Mine etc
Spontaneous
combustion in
underground
work areas
Loss of
production
while
inertisation
takes place to
stabilise spon
com
4
D
M
Coal samples
tested and contain
low propensity for
spon com.
and management
practices
combined with gas
monitoring and
Inertisation
infrastructure.
Unplanned fall
of ground in
underground
operations
Potential safety
hazard and
suspension of
operations.
Potential loss
of reserves if
areas cannot
be mined
safely.
4
C
H
Geotechincal
design based on
exploration
samples.
Operational SHMS
and principal
hazard TARPS.
Page 113 of 118
Significant
unplanned
geotechnical
failure on
highwall
impacting flood
protection
levees.
Loss of
production
potentially
safety hazard
5
E
H
Geotechincal
design based on
exploration
samples.
Operational SHMS
and principal
hazard TARPS.
Significant
safety incident
Loss of license
to operate
5
E
H
Continue to
adhere to the
SHMS and
operational
discipline
Uncertain soft
floor conditions
encountered in
UG mining
Loss of
Reserves
leaving coal in
floor
3
D
M
Geotechnical core
investigation for
floor conditions
(slake durability
etc) include in UG
mine planning.
Control of mine
water.
Unexpectedly
high frictional
ignition
propensity of
roof, floor or
partings
material in UG
operation
Health and
safety risk in
operations
4
D
H
Gas control in
operations –
ventilation etc
when mining in
areas which may
exhibit this
harzard
Geology/Geotechnica
l
Unexpected
geological
complexity in
underground
Higher
operational
costs of mining.
Loss of reserve
3
B
H
Reserve allows for
up to 15%
geological risk in
Reserve estimate
orientation to
consider faulting.
orientation to
consider joints.
geotech drilling
and modelling.
ahead of mining.
Unexpected
geological
complexity in
open cut
Planned
reserve not
recovered
2
C
M
orientation to
consider faulting.
orientation to
consider joints.
geotech drilling
and modelling.
drilling ahead of
mining.
Incorporation of
highwall structural
mapping into the
short-term
geological model.
Page 114 of 118
Product yields
or coal quality
data
significantly
lower than
estimated
Lower revenue
than planned
affecting
project
valuation
3
C
H
quality core drilling
and washability
simulation ahead
of mining.
Unexpected
igneous
intrusions
Loss of
Reserve
3
D
M
exploration
including seismic
studies, UIS and
SIS drilling ahead
of mining in UG
Unexpected
seam splitting
Loss of
Reserve
Increased ROM
dilution
Reduced
operational
productivity
2
C
M
n drilling and
seismic
investigations
Excessive
stress,
magnitude and
direction
Reduced
roadway widths
in UG,
increased
ground support
requirements
Reduced
productivity and
loss of Reserve
3
D
M
stress testing
investigations
breakout analysis
roof monitoring
Geological
uncertainty in
UG below
existing out of
pit waste
dumps
Loss of
Reserve
Unexpected
geotechnical
conditions
4
D
H
spoil drilling
exploration
Infrastructure
Failure of
CHPP
structures due
to age of
infrastructure
Increased
operating costs
and potential
for production
loss in
unplanned
downtime
4
D
H
to maintain the
structural
maintenance
programme
CHPP yield
below planned
recoveries
Loss of
production
revenue due to
failure to
achieve
forecast
production
recoveries
3
C
H
monitoring of plant
operations to
improve
recoveries
Insufficient HV
power available
for UG
development
project at
Curragh
Production
delays due to
insufficient
supply
available to full
planned UG
production fleet
3
C
H
in progress in
2024 to determine
requirements .
Upgrades
undertaken in time
for underground
production build
up.
Environmental
Environmental
Authority
amendment for
UG operation
not approved in
time to meet
planned
production
profile
Production
delays
4
E
M
working with
regulatory bodies
through the EA
amendment
process
Page 115 of 118
subsidence mining
method planned in
UG mine plan
Environmental
complaints
from sensitive
receptors for
new open cut
development
areas (Z pits)
Loss of reserve
if
Environmental
Authority
conditions
cannot be met
(noise/dust etc)
4
D
H
Expansion Project
EIS
er management of
external
stakeholders
Restriction to
exploration
activities in
biodiversity
offset areas
Increased
geological
uncertainty to
UG mine plan
in these areas
causing
potential loss of
Reserves
3
C
H
er relationships
with regulator
ahead of mining.
Economics
Price forecast
reducing
significantly or
foreign
exchange rate
fluctuation
impacting
revenue
negatively
Reserve
reduction and
potential
business asset
value write
down
5
C
H
mining method
and cost
assumptions in
financial model
capex
assumptions
Underestimate
d capital costs
for operation
Lower return on
investment
3
D
M
Review capital
plan and re-
engineer to suit
business
requirements
Underestimate
d operating
costs for
operation
Lower return on
investment
4
D
H
g planned
operating costs in
LOM plan against
historical actuals
from the
operation.
nd costs
calculated from
first principles and
benchmarked
against industry
Page 116 of 118
23 Recommendations
Coronado is continuing to work both internally and with outside assistance to further define their
resource base and to optimize the open cut LOM plan.
The current primary focus for exploration for the underground mine is concentrated in the southern area
where production is planned to commence. Various techniques including 2D and 3D Seismic surveys,
exploration bore holes and both Surface to In Seam (SIS) and Underground in Seam (UIS) gas drainage
bore holes will provide additional definition of the resource and mining predicted mining conditions. The
results obtained and experience gained will then be used to derive appropriate exploration programs
for the remaining areas of the underground. Exploration techniques and strategies appropriate to the
requirements of the planned mining method and LOM plan will need to be considered where surface
access is limited due to open cut waste dumps and restricted access areas.
A major amendment will be made to current Environmental Authority (EPML00643713) for the inclusion
of underground mining activities. This major amendment is supported by an Environmental Assessment
Report (EAR) which will be submitted to the Department of Environment and Science (DES) in early
2024. It is anticipated that the approval of the major EA amendment to support project commencement
will be achieved in December 2024.
Page 117 of 118
24 References
Publicly available information from various State and Federal agencies was used where relevant.
25 Reliance on information provided by the registrant
Portions of this report has been prepared by Qualified Persons for Coronado. The information,
conclusions, opinions, and estimates contained herein are based on:
●
●
●
For the purpose of this report, the Qualified Person for Resources has relied on information provided
by Coronado and other third-party sources, specifically for Sections 7.2 & 7.3 & 10 & 11.5 .
For the purpose of this report, the Qualified Persons for Reserves have relied on information provided
by Coronado and other third-party sources, specifically for Sections 12 and 13.
The Qualified Persons for Reserves have relied on information provided by Coronado for property
control, marketing, material contracts, environmental studies, permitting, infrastructure, product
washability yield simulation data and macro-economic assumptions as stated in:
●
●
●
●
●
●
●
As the mine has been in operation for forty years, Coronado has considerable experience in those
areas. The Qualified Persons have relied on Coronado for guidance on applicable taxes, royalties,
government interests, revenue assumptions, projected capital costs and operating cost data from the
mine in the Executive Summary and Sections 18 and 19.
The Qualified Persons have taken all appropriate steps, in their professional opinion, to ensure that the
above information from Coronado or its third-party sources is sound.
Except for the purposes legislated under applicable securities laws, any use of this report by any third
party is at that party’s sole risk.
Page 118 of 118
26 Glossary of Abbreviations and Definitions
Abbreviation
Definition
AUD
Australian Dollar
AUD:USD
Australian Dollar to US Dollar currency conversion rate
CHPP
Coal Handling and Processing Plant
CM
Continuous Miner
DOC
Depth of Cover
EBITDA
Earnings Before Interest Tax Depreciation & Amortization
FS
Feasibility Study
Kt
Kilo tonnes; Units in thousands
LHD
Load haul dump
LOM
Life Of Mine
m3/t
Cubic meters per tonne
Mbcm
Million bank cubic meters
MIA
Mine Industrial Area
MDL
Mineral Development Licence
Metallurgical Coal
Coal used in the steel making process
ML
Mining Lease
MMt
Million Metric Tonne
Mt
Million Tonnes
NPV
Net present value
P&L
Profit and loss
PCI
Pulverised Coal Injection
PFS
Pre Feasibility Study
Prdt
Product Tonne
QLD
Queensland
ROM
Run Of Mine, Coal mined
t
Metric tonnes
tph
Tonnes per hour
UNSW
University of New South Wales
USD
US Dollar
WACC
Weighted average cost of capital as a percentage