|
Note 16 - Accounting for Claims, Unapproved Change Orders and Incentives on Long-Term Construction Contracts
|
3 Months Ended | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Nov. 30, 2012
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Long-term Contracts or Programs Disclosure [Text Block] |
Note 16 —Accounting
for Claims, Unapproved Change Orders and Incentives on
Long-Term Construction Contracts
Claims
include amounts in excess of the original contract price (as
it may be adjusted for approved change orders) that we seek
to collect from our clients for delays, errors in
specifications and designs, contract terminations, change
orders in dispute or unapproved as to both scope and price or
other causes of unanticipated additional costs, and are
included in estimated revenues when recovery of the amounts
is probable and the costs can be reasonably estimated.
Similarly, backcharges and claims against vendors,
subcontractors and others are included in our cost estimates
as a reduction in total estimated costs when recovery of the
amounts is probable and the costs can be reasonably
estimated.
Claims
and backcharges are recorded at the amount deemed probable of
recovery up to the amount of estimated costs, and profit is
not recorded until the claim or backcharge is resolved. The
recognition of these items may increase gross profit or
reduce gross loss on the related projects as compared to the
gross profit/gross loss that would have been recognized had
no claim revenue been recorded. Claims receivable are
included in costs and estimated earnings in excess of
billings on uncompleted contracts on the accompanying
consolidated balance sheets.
We
enter into cost-reimbursable arrangements in which the final
outcome or overall estimate at completion may be materially
different than the original contract estimated value. We
believe the terms of such contracts indicate costs are to be
reimbursed by our clients. However, we typically process
change notice requests to document agreement as to scope and
price and thereby mitigate potential exposure relative to
costs incurred in excess of agreed upon contract value. Due
to the nature of these items, we have not classified and
disclosed costs incurred in excess of agreed upon contract
value as unapproved change orders.
Unapproved
Change Orders and Claims
The
table below (in millions) summarizes information related to
our significant unapproved change orders and claims from
project owners that we have recorded on a total project basis
at November 30, 2012, and November 30, 2011, and excludes all
unrecorded amounts and non-significant unapproved change
orders and claims.
In
the table above, the difference between the amounts included
in project estimates-at-completion and the amounts recorded
in revenues (or reductions to contract costs) on a total
project basis represents the forecasted costs for work which
has not yet been incurred (i.e. the remaining
percentage-of-completion revenue to be recognized on the
related project). The amounts presented in this table
include, but are not limited to, those matters currently in
litigation or arbitration for which we have recorded revenue.
Additional discussion regarding our legal proceedings
relating to unapproved change orders and claims in litigation
or arbitration is provided in our Legal Proceedings in Note
12 – Contingencies and Commitments.
The
majority of the amounts included in the project
estimates-at-completion in the table above relate to
engineering, equipment supply, material fabrication and
construction cost estimates and costs from regulatory
required design changes and delays in our clients’
obtaining combined operating licenses (COLs) for two nuclear
power reactors in Georgia. Under the provisions of this
contract, we have entered into a formal dispute resolution
process on certain claims associated with backfill
activities, shield building, large structural modules and COL
issuance delays included within construction costs at the
site. As provided in the contract, as of November 30, 2012,
we have received a partial funding payment from our customer
of $29.0 million related to the backfill costs and $96
million related to the COL issuance delays while the dispute
resolution process continues. These amounts are included in
billings in excess of costs and estimated earnings on
uncompleted contracts. Should we not prevail in these
disputes, we may be required to repay a portion or all of
these amounts. We continue to discuss with our client the
impact of other elements of unapproved change orders
associated with this project. Should those matters in Georgia
proceed to formal dispute resolution, our contract calls for
the clients to co-fund our costs until the matters are
resolved.
In
connection with our consortium agreement for the design and
construction of two domestic nuclear power reactors in South
Carolina, we reached an agreement with the client to settle
certain change orders resulting from regulatory required
design changes and COL issuance delays on the project. As a
result of this agreement, these costs have been excluded from
the total of unapproved change orders presented above.
We
believe the amounts included in the table above related to
all of our AP1000
nuclear and other projects are recoverable from our clients
under existing provisions of our contractual arrangements.
The nuclear power projects have a long construction duration
and the cost estimates cover costs that will not be incurred
for several years. It is expected that the cost estimates
resulting from the design changes and COL delays will
continue to be refined as more information becomes available.
It is possible that these commercial matters may not be
resolved in the near term.
Under
the terms of two consortium agreements with WEC, which is our
EPC partner, to design and construct the four nuclear power
reactors, we perform much of the pipe, steel and modular
fabrication and assembly and certain engineering and
construction related activities on the domestic AP1000
nuclear projects, with WEC being responsible for the nuclear
island engineering and equipment supply. During the
quarter ended February 29, 2012, we signed a memorandum of
understanding with WEC (“the WEC MOU”) wherein
WEC has the obligation, in addition to obligations under the
original consortium agreement, to reimburse us for material
and fabrication costs associated with design changes to the
extent these costs are not recovered from our clients.
Accordingly, amounts which may be recovered under the WEC MOU
have been excluded from the unapproved change orders and
claims presented in the table above, even when we are seeking
recovery from the client. These consortium agreements, as
supplemented by the WEC MOU, provide a contractual mechanism
for cost sharing to the extent project costs exceed
certain thresholds and are not recovered from our clients.
Our costs, including construction related expenses, resulting
from the design changes and delays in issuance of the COLs
would be considered within this cost sharing mechanism. As of
November 30, 2012, we estimate that our recovery under these
consortium agreements and the related WEC MOU is
approximately $293.0 million, which has been excluded from
the presentation of unapproved change orders in the above
table. The amounts recoverable from WEC will decline to the
extent we recover the costs from our clients.
In
the ordinary course of business, the Company enters into
various agreements and guarantees to clients. While in most
cases these performance risks are offset by similar
guarantees by our suppliers, there are instances where the
full extent of the exposure is not eliminated.
In
general, if we collect amounts differing from the amounts
that we have recorded as unapproved change orders/claims
receivable on any of our projects, that difference will be
reflected in the estimate at completion (EAC) used in
determining contract profit or loss. Timing of claim
collections is uncertain and depends on such items as
regulatory approvals, negotiated settlements, trial date
scheduling and other dispute resolution processes pursuant to
the contracts. As a result, we may not collect our unapproved
change orders/claims receivable within the next twelve
months. Should we not prevail in these matters, the outcome
could have an adverse effect on our statements of operations
and statement of cash flows.
Project
Incentives
Some
of our contracts contain performance incentive and award fee
arrangements (collectively referred to as incentive fees)
that provide for increasing or decreasing our revenue based
upon the achievement of some measure of contract performance
in relation to agreed upon targets. Incentive fees can occur
in all segments, but the majority of contracts containing
project incentives are in our Plant Services and E&I
segments. Therefore, the gross profit in those segments may
be significantly influenced by these project
incentives.
We
include in our EAC revenue an estimate of the probable
amounts of the incentive fees we expect to earn if we achieve
the agreed-upon criteria. We bill incentive fees based on the
terms and conditions of the individual contracts which may
allow billing over the performance period of the contract or
only after the target criterion have been achieved. We
generally recognize incentive fee revenue using the
percentage of completion method of accounting. As the
contract progresses and more information becomes available,
the estimate of the anticipated incentive fee that will be
earned is revised as necessary. Incentive fees which have
been recognized but not billed are included in costs and
estimated earnings in excess of billings on uncompleted
contracts in the accompanying consolidated balance sheets.
Incentive fees that have been billed but for which we have
not recognized as revenue are included in the advanced
billings and billings in excess of costs and estimated
earnings on uncompleted contracts in the accompanying
consolidated balance sheets.
At
November 30, 2012, and August 31, 2012, our project EACs
included approximately $67.7 million and $78.2 million,
respectively, related to estimates of amounts we expect to
earn on incentive fee arrangement. We have recorded $40.7
million and $48.0 million as of November 30, 2012, and August
31, 2012, respectively, of these estimated amounts in
revenues for the related contracts. If we do not achieve the
criteria at the amounts we have estimated, project revenues
and profit may be materially reduced.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||