|
Note 16 - Accounting for Claims, Unapproved Change Orders and Incentives on Long-Term Construction Contracts
|
3 Months Ended | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Nov. 30, 2011
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Long-term Contracts or Programs Disclosure [Text Block] |
Note 16 —Accounting
for Claims, Unapproved Change Orders and Incentives on
Long-Term Construction Contracts
Claims
include amounts in excess of the original contract price (as
it may be adjusted for approved change orders) that we seek
to collect from our clients for delays, errors in
specifications and designs, contract terminations, change
orders in dispute or unapproved as to both scope and price,
or other causes of unanticipated additional costs and are
included in estimated revenues when recovery of the amounts
is probable and the costs can be reasonably estimated.
Backcharges and claims against vendors, subcontractors and
others are included in our cost estimates as a reduction in
total estimated costs when recovery of the amounts is
probable and the costs can be reasonably estimated. Profit
recognition on our claims is deferred until the change order
has been approved or the disputed amounts have been settled.
The recording of these claims against third parties increases
gross profit or reduces gross loss on the related projects in
the periods the claims are reported. Claims receivable are
included in costs and estimated earnings in excess of
billings on uncompleted contracts on the accompanying
consolidated balance sheets.
We
enter into cost-reimbursable arrangements in which the final
outcome or overall estimate at completion may be materially
different than the original contract estimated value. While
the terms of such contracts indicate costs are to be
reimbursed by our clients, we typically process change notice
requests to document agreement as to scope and price. Due to
the nature of these items, we have not classified and
disclosed the amounts as unapproved change orders. While we
have no history of significant losses on this type of work,
potential exposure exists relative to costs incurred in
excess of agreed upon contract value.
Unapproved
Change Orders and Claims
The
table below (in millions) summarizes information related to
our significant unapproved change orders and claims from
project owners that we have recorded on a total project basis
at November 30, 2011, and November 30, 2010, and excludes all
unrecorded amounts and non-significant unapproved change
orders and claims.
In
the table above, the difference between the amounts included
in project estimates-at-completion and the amounts recorded
in revenues (or reductions to contract costs) on a total
project basis represents the forecasted costs for work which
has not yet been incurred (i.e. the remaining
percentage-of-completion revenue to be recognized on the
related project). The amounts presented in this table
include, but are not limited to, those matters currently in
litigation or arbitration for which we have recorded revenue.
Additional discussion regarding our legal proceedings
relating to unapproved change orders and claims in litigation
or arbitration is provided in our Legal Proceedings in Note
12 — Contingencies and Commitments.
Unapproved
change orders and claims included in project
estimates-at-completion (EAC) remained relatively flat
during the three months ended November 30, 2011. The
majority of the amounts included in the
estimates-at-completion in the table above relates to
engineering, equipment supply, material fabrication, and
construction cost estimates which may exceed $400 million
associated with regulatory mandated design changes
resulting from the certification of the AP1000 nuclear
power plant technology in the United States and our
clients’ application to obtain combined operating
licenses (COLs) for four nuclear power reactors. We perform
much of the modular fabrication, assembly and construction
related activities on these projects with WEC being
responsible for the nuclear island engineering and
equipment supply. We believe that we have contractual
entitlement to recover the additional costs related to
these design changes from our clients and to the extent not
paid by clients, WEC has acknowledged an obligation to
reimburse us for our material and fabrication costs. Final
terms are currently being negotiated with WEC, and the
regulatory approvals have not yet been finalized.
Therefore, the design and cost estimates are subject to
change. Change order requests or claims have not been
completed or submitted to the respective clients or to WEC.
We have an understanding with WEC regarding these
additional costs which will be followed up with formal
amendments to the existing consortium agreement between us.
It is expected that the cost estimates will continue to be
refined as more information becomes available. These
projects have a long construction duration and it is
possible that these matters may not be resolved in the near
term. Should these matters proceed to formal dispute
resolution, our contracts call for clients to co-fund our
costs until the matters are resolved.
During
the three months ended November 30, 2011, our clients
approved change orders totaling $8.7 million.
If
we collect amounts different than the amounts that we have
recorded as unapproved change orders/claims receivable, that
difference will be reflected in the EAC used in determining
contract profit or loss. Timing of claim collections is
uncertain and depends on such items as regulatory approvals,
negotiated settlements, trial date scheduling and other
dispute resolution processes pursuant to the contracts. As a
result, we may not collect our unapproved change
orders/claims receivable within the next twelve
months.
In
addition to the unapproved change orders and claims discussed
above, we have recorded as a reduction to costs at November
30, 2011, approximately $0.7 million in expected recoveries
for backcharges, liquidated damages and other cost exposures
resulting from supplier or subcontractor caused impediments
to our work. Such impediments may be caused by the failure of
suppliers or subcontractors to provide services, materials,
or equipment compliant with provisions of our agreements,
resulting in delays to our work or additional costs to
remedy. See Note 12 — Contingencies and Commitments for
information with respect to certain vendor
backcharges.
In
the ordinary course of business, the Company enters into
various agreements pending assurances and guarantees to
clients. While in most cases these performance
risks are offset by similar guarantees by our suppliers,
there are instances where the full extent of the exposure is
not eliminated.
Should
we not prevail in these matters, the outcome could have an
adverse effect on our statements of operations and statement
of cash flows.
Project
Incentives
Some
of our contracts contain performance incentive and award
fee arrangements (collectively referred to as project
incentives) that provide for increasing or
decreasing revenue based upon the achievement of some
measure of contract performance in relation to agreed upon
targets. Project incentives can occur in all segments, but
the majority of contracts containing project incentives are
in our Plant Services and E&I segments. Therefore, the
gross profit in those segments may be significantly
influenced by these project incentives.
We
include in our EAC revenue an estimate of the probable
amounts of these project incentives we expect to earn if we
achieve the agreed-upon criteria. We recognize revenue
associated with these project incentives using the
percentage-of-completion method of accounting. As the
contract progresses and more information becomes available,
the estimate of the anticipated incentive fee that will be
earned is revised as necessary.
At
November 30, 2011, and August 31, 2011, our project EACs
included approximately $115.9 million and $109.0 million,
respectively, related to estimates of amounts we expect to
earn on incentive fee arrangement. On a
percentage-of-completion basis, we have recorded $79.1
million and $64.8 million as of November 30, 2011, and August
31, 2011, respectively, of these estimated amounts in
revenues for the related contracts. We bill incentive fees
based on the terms and conditions of the individual contracts
which may allow billing over the performance period of the
contract or only after the target criterion has been
achieved. Incentive fees which have been recognized but not
billed are included in costs and estimated earnings in excess
of billings on uncompleted contracts in the accompanying
consolidated balance sheets. If we do not achieve the
criteria at the amounts we have estimated, project revenues
and profit may be materially reduced.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||