Commitments and contingencies (Tables)
9 Months Ended
Dec. 31, 2019
Commitments and contingencies  
Schedule of variable lease components

 

 

 

 

 

 

 

 

 

Three Months Ended 

 

Nine Months Ended 

 

 

December 31, 

 

December 31, 

 

    

2019

    

2019

Lease cost

 

 

 

 

 

 

Finance lease costs:

 

 

 

 

 

 

Amortization of right-of-use asset

 

$

607

 

$

666

Interest on lease liabilities

 

 

591

 

 

652

Operating lease costs

 

 

262

 

 

633

Total lease cost

 

$

1,460

 

$

1,951

 

Summary of the maturity of company's lease liabilities

 

 

 

 

 

 

 

 

 

 

 

 

December 31, 2019

 

    

Operating lease

    

Financing lease

    

Total

2020 (remaining three months)

 

$

243

 

$

593

 

$

836

2021

 

 

1,034

 

 

2,411

 

 

3,445

2022

 

 

586

 

 

2,483

 

 

3,069

2023

 

 

596

 

 

2,558

 

 

3,154

2024

 

 

605

 

 

2,634

 

 

3,239

Thereafter

 

 

3,384

 

 

46,398

 

 

49,782

Total lease payments

 

 

6,448

 

 

57,077

 

 

63,525

Less: interest

 

 

1,551

 

 

29,668

 

 

31,219

Total lease liabilities

 

$

4,897

 

$

27,409

 

$

32,306

 

Schedule of future annual minimum lease payment commitments

 

 

 

 

 

 

2020

 

$

2,062

2021

 

 

2,901

2022

 

 

2,493

2023

 

 

2,568

2024

 

 

2,645

2025

 

 

2,725

Thereafter

 

 

12,770

 

 

$

28,164

 

Schedule of additional information related to leases

 

 

 

 

 

 

    

December 31, 2019

 

Leases

 

 

 

 

Right-to-use operating lease asset

 

$

4,731

 

Right-to-use finance lease asset

 

 

47,528

 

Total lease assets

 

$

52,259

 

 

 

 

 

 

Operating lease liabilities, current

 

$

1,011

 

Finance lease liabilities, current

 

 

2,393

 

Operating lease liabilities, non-current

 

 

3,886

 

Finance lease liabilities, non-current

 

 

25,016

 

Total lease liabilities

 

$

32,306

 

 

 

 

 

 

Other information

 

 

  

 

Cash paid for amounts included in the measurement of lease liabilities:

 

 

 

 

Operating cash flows from operating leases

 

$

516

 

Operating cash flows from finance leases

 

$

623

 

Financing cash flows from finance leases

 

$

22

 

Right-to-use asset obtained in exchange for new operating lease liabilities

 

$

5,152

 

Right-to-use asset obtained in exchange for new financing lease liabilities

 

$

48,224

 

Variable lease costs

 

$

 —

 

Short term lease costs

 

$

 —

 

Weighted-average remaining lease term - operating leases

 

 

8.6

years

Weighted-average remaining lease term - financing leases

 

 

19.6

years

Weighted-average discount rate - operating leases

 

 

 7

%

Weighted-average discount rate - financing leases

 

 

 8

%