<font style="FONT-FAMILY: ARIAL" size="2"><b><i>Illinois Settlement
Agreement (Exelon, Generation and ComEd).</i></b> In July
2007, following extensive discussions with legislative leaders in
Illinois, ComEd, Generation and other utilities and generators in
Illinois reached an agreement (Illinois Settlement) with various
parties concluding discussions of measures to address concerns
about higher electric bills in Illinois without rate freeze,
generation tax or other legislation that Exelon believes would be
harmful to consumers of electricity, electric utilities, generators
of electricity and the State of Illinois. Legislation reflecting
the Illinois Settlement (Illinois Settlement Legislation) was
signed into law in August 2007. The Illinois Settlement and
the Illinois Settlement Legislation provide for the following,
among other things:</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; MARGIN-LEFT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><i>Rate Relief
Programs</i></font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: -6px"><font size="1"> </font></p>
<table style="BORDER-COLLAPSE: collapse" cellspacing="0" cellpadding="0" width="100%" border="0">
<tr>
<td width="4%"><font size="1"> </font></td>
<td valign="top" align="left" width="2%"><font style="FONT-FAMILY: ARIAL" size="2">•</font></td>
<td valign="top" width="1%"> </td>
<td valign="top" align="left">
<p align="left"><font style="FONT-FAMILY: ARIAL" size="2">Various
Illinois electric utilities, their affiliates and generators of
electricity in Illinois agreed to contribute approximately $1
billion over a period of four years (2007-2010) to programs to
provide rate relief to Illinois electricity customers and funding
for the IPA created by the Illinois Settlement Legislation. ComEd
committed to issue $64 million in rate relief credits to customers
or to fund various programs to assist customers. Generation
committed to contribute an aggregate of $747 million, consisting of
$435 million to pay ComEd for rate relief programs for ComEd
customers, $307.5 million for rate relief programs for customers of
other Illinois utilities and $4.5 million for partially funding
operations of the IPA. The contributions are recognized in the
financial statements of Generation and ComEd as rate relief credits
are applied to customer bills by ComEd and other Illinois utilities
or as operating expenses associated with the programs are
incurred.</font></p>
</td>
</tr>
</table>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: -6px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; MARGIN-LEFT: 7%">
<font style="FONT-FAMILY: ARIAL" size="2">During the years ended
December 31, 2009, 2008 and 2007, Generation and ComEd
recognized net costs from their contributions pursuant to the
Illinois Settlement in their Consolidated Statements of Operations
as follows:</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<table cellspacing="0" cellpadding="0" width="100%" align="center" border="0">
<tr>
<td width="65%"></td>
<td valign="bottom" width="10%"></td>
<td></td>
<td></td>
<td valign="bottom" width="10%"></td>
<td></td>
<td></td>
<td valign="bottom" width="10%"></td>
<td></td>
<td></td>
</tr>
<tr>
<td valign="bottom" nowrap="nowrap">
<p style="WIDTH: 118pt; BORDER-BOTTOM: #000000 1px solid">
<font style="FONT-FAMILY: ARIAL" size="1"><b>Year Ended
December 31, 2009</b></font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td style="BORDER-BOTTOM: #000000 1px solid" valign="bottom" align="center" colspan="2"><font style="FONT-FAMILY: ARIAL" size="1"><b>Generation</b></font></td>
<td valign="bottom"><font size="1">  </font></td>
<td style="BORDER-BOTTOM: #000000 1px solid" valign="bottom" align="center" colspan="2"><font style="FONT-FAMILY: ARIAL" size="1"><b>ComEd</b></font></td>
<td valign="bottom"><font size="1">  </font></td>
<td style="BORDER-BOTTOM: #000000 1px solid" valign="bottom" align="center" colspan="2"><font style="FONT-FAMILY: ARIAL" size="1"><b>Total Credits Issued<br />
to ComEd Customers</b></font></td>
</tr>
<tr bgcolor="#CCEEFF">
<td valign="top">
<p style="MARGIN-LEFT: 1em; TEXT-INDENT: -1em"><font style="FONT-FAMILY: ARIAL" size="2">Credits to ComEd customers</font>
<font style="FONT-FAMILY: ARIAL" size="1"><sup style="VERTICAL-ALIGN: baseline; BOTTOM: 0.8ex; POSITION: relative">(a)</sup></font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">45</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">8</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">53</font></td>
</tr>
<tr>
<td valign="top">
<p style="MARGIN-LEFT: 1em; TEXT-INDENT: -1em"><font style="FONT-FAMILY: ARIAL" size="2">Credits to other Illinois
utilities’ customers</font> <font style="FONT-FAMILY: ARIAL" size="1"><sup style="VERTICAL-ALIGN: baseline; BOTTOM: 0.8ex; POSITION: relative">(a)</sup></font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">53</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">n/a</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">n/a</font></td>
</tr>
<tr bgcolor="#CCEEFF">
<td valign="top">
<p style="MARGIN-LEFT: 1em; TEXT-INDENT: -1em"><font style="FONT-FAMILY: ARIAL" size="2">Other rate relief programs</font>
<font style="FONT-FAMILY: ARIAL" size="1"><sup style="VERTICAL-ALIGN: baseline; BOTTOM: 0.8ex; POSITION: relative">(b)</sup></font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">—  </font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">1</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">n/a</font></td>
</tr>
<tr style="FONT-SIZE: 1px">
<td valign="bottom"></td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
</tr>
<tr>
<td valign="top">
<p style="MARGIN-LEFT: 1em; TEXT-INDENT: -1em"><font style="FONT-FAMILY: ARIAL" size="2">Total incurred costs</font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">98</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">9</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">53</font></td>
</tr>
<tr style="FONT-SIZE: 1px">
<td valign="bottom"></td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
</tr>
</table>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<table cellspacing="0" cellpadding="0" width="100%" align="center" border="0">
<tr>
<td width="65%"></td>
<td valign="bottom" width="9%"></td>
<td></td>
<td></td>
<td valign="bottom" width="9%"></td>
<td></td>
<td></td>
<td valign="bottom" width="9%"></td>
<td></td>
<td></td>
</tr>
<tr>
<td valign="bottom" nowrap="nowrap">
<p style="WIDTH: 118pt; BORDER-BOTTOM: #000000 1px solid">
<font style="FONT-FAMILY: ARIAL" size="1"><b>Year Ended
December 31, 2008</b></font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td style="BORDER-BOTTOM: #000000 1px solid" valign="bottom" align="center" colspan="2"><font style="FONT-FAMILY: ARIAL" size="1"><b>Generation</b></font></td>
<td valign="bottom"><font size="1">  </font></td>
<td style="BORDER-BOTTOM: #000000 1px solid" valign="bottom" align="center" colspan="2"><font style="FONT-FAMILY: ARIAL" size="1"><b>ComEd</b></font></td>
<td valign="bottom"><font size="1">  </font></td>
<td style="BORDER-BOTTOM: #000000 1px solid" valign="bottom" align="center" colspan="2"><font style="FONT-FAMILY: ARIAL" size="1"><b>Total Credits Issued<br />
to ComEd Customers</b></font></td>
</tr>
<tr bgcolor="#CCEEFF">
<td valign="top">
<p style="MARGIN-LEFT: 1em; TEXT-INDENT: -1em"><font style="FONT-FAMILY: ARIAL" size="2">Credits to ComEd customers</font>
<font style="FONT-FAMILY: ARIAL" size="1"><sup style="VERTICAL-ALIGN: baseline; BOTTOM: 0.8ex; POSITION: relative">(a)</sup></font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">131</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">6</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">137</font></td>
</tr>
<tr>
<td valign="top">
<p style="MARGIN-LEFT: 1em; TEXT-INDENT: -1em"><font style="FONT-FAMILY: ARIAL" size="2">Credits to other Illinois
utilities’ customers</font> <font style="FONT-FAMILY: ARIAL" size="1"><sup style="VERTICAL-ALIGN: baseline; BOTTOM: 0.8ex; POSITION: relative">(a)</sup></font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">90</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">n/a</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">n/a</font></td>
</tr>
<tr bgcolor="#CCEEFF">
<td valign="top">
<p style="MARGIN-LEFT: 1em; TEXT-INDENT: -1em"><font style="FONT-FAMILY: ARIAL" size="2">Other rate relief programs</font>
<font style="FONT-FAMILY: ARIAL" size="1"><sup style="VERTICAL-ALIGN: baseline; BOTTOM: 0.8ex; POSITION: relative">(b)</sup></font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">—  </font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">7</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">n/a</font></td>
</tr>
<tr style="FONT-SIZE: 1px">
<td valign="bottom"></td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
</tr>
<tr>
<td valign="top">
<p style="MARGIN-LEFT: 1em; TEXT-INDENT: -1em"><font style="FONT-FAMILY: ARIAL" size="2">Total incurred costs</font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">221</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">13</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">137</font></td>
</tr>
<tr style="FONT-SIZE: 1px">
<td valign="bottom"></td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
</tr>
</table>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<table cellspacing="0" cellpadding="0" width="100%" align="center" border="0">
<tr>
<td width="65%"></td>
<td valign="bottom" width="9%"></td>
<td></td>
<td></td>
<td valign="bottom" width="9%"></td>
<td></td>
<td></td>
<td valign="bottom" width="9%"></td>
<td></td>
<td></td>
</tr>
<tr>
<td valign="bottom" nowrap="nowrap">
<p style="WIDTH: 118pt; BORDER-BOTTOM: #000000 1px solid">
<font style="FONT-FAMILY: ARIAL" size="1"><b>Year Ended
December 31, 2007</b></font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td style="BORDER-BOTTOM: #000000 1px solid" valign="bottom" align="center" colspan="2"><font style="FONT-FAMILY: ARIAL" size="1"><b>Generation</b></font></td>
<td valign="bottom"><font size="1">  </font></td>
<td style="BORDER-BOTTOM: #000000 1px solid" valign="bottom" align="center" colspan="2"><font style="FONT-FAMILY: ARIAL" size="1"><b>ComEd</b></font></td>
<td valign="bottom"><font size="1">  </font></td>
<td style="BORDER-BOTTOM: #000000 1px solid" valign="bottom" align="center" colspan="2"><font style="FONT-FAMILY: ARIAL" size="1"><b>Total Credits Issued<br />
to ComEd Customers</b></font></td>
</tr>
<tr bgcolor="#CCEEFF">
<td valign="top">
<p style="MARGIN-LEFT: 1em; TEXT-INDENT: -1em"><font style="FONT-FAMILY: ARIAL" size="2">Credits to ComEd customers</font>
<font style="FONT-FAMILY: ARIAL" size="1"><sup style="VERTICAL-ALIGN: baseline; BOTTOM: 0.8ex; POSITION: relative">(a)</sup></font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">246</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">33</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">279</font></td>
</tr>
<tr>
<td valign="top">
<p style="MARGIN-LEFT: 1em; TEXT-INDENT: -1em"><font style="FONT-FAMILY: ARIAL" size="2">Credits to other Illinois
utilities’ customers</font> <font style="FONT-FAMILY: ARIAL" size="1"><sup style="VERTICAL-ALIGN: baseline; BOTTOM: 0.8ex; POSITION: relative">(a)</sup></font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">157</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">n/a</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">n/a</font></td>
</tr>
<tr bgcolor="#CCEEFF">
<td valign="top">
<p style="MARGIN-LEFT: 1em; TEXT-INDENT: -1em"><font style="FONT-FAMILY: ARIAL" size="2">Other rate relief programs</font>
<font style="FONT-FAMILY: ARIAL" size="1"><sup style="VERTICAL-ALIGN: baseline; BOTTOM: 0.8ex; POSITION: relative">(b)</sup></font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">—  </font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">8</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">n/a</font></td>
</tr>
<tr>
<td valign="top">
<p style="MARGIN-LEFT: 1em; TEXT-INDENT: -1em"><font style="FONT-FAMILY: ARIAL" size="2">Funding of the IPA</font>
<font style="FONT-FAMILY: ARIAL" size="1"><sup style="VERTICAL-ALIGN: baseline; BOTTOM: 0.8ex; POSITION: relative">(a)</sup></font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">5</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">—  </font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2"> </font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">n/a</font></td>
</tr>
<tr style="FONT-SIZE: 1px">
<td valign="bottom"></td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 1px solid" valign="bottom">
 </td>
</tr>
<tr bgcolor="#CCEEFF">
<td valign="top">
<p style="MARGIN-LEFT: 1em; TEXT-INDENT: -1em"><font style="FONT-FAMILY: ARIAL" size="2">Total incurred costs</font></p>
</td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">408</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">41</font></td>
<td valign="bottom"><font size="1">  </font></td>
<td valign="bottom"><font style="FONT-FAMILY: ARIAL" size="2">$</font></td>
<td valign="bottom" align="right"><font style="FONT-FAMILY: ARIAL" size="2">279</font></td>
</tr>
<tr style="FONT-SIZE: 1px">
<td valign="bottom"></td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td valign="bottom">  </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
<td style="BORDER-TOP: #000000 3px double" valign="bottom">
 </td>
</tr>
</table>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 2px; WIDTH: 10%; LINE-HEIGHT: 8px; BORDER-BOTTOM: #000000 0.5pt solid">
 </p>
<table style="BORDER-COLLAPSE: collapse" cellspacing="0" cellpadding="0" width="100%" border="0">
<tr>
<td valign="top" align="left" width="3%"><font style="FONT-FAMILY: ARIAL" size="1">(a)</font></td>
<td valign="top" align="left"><font style="FONT-FAMILY: ARIAL" size="1">Recorded as a reduction in operating revenues</font></td>
</tr>
</table>
<table style="BORDER-COLLAPSE: collapse" cellspacing="0" cellpadding="0" width="100%" border="0">
<tr>
<td valign="top" align="left" width="3%"><font style="FONT-FAMILY: ARIAL" size="1">(b)</font></td>
<td valign="top" align="left"><font style="FONT-FAMILY: ARIAL" size="1">Recorded as a charge to operating and maintenance
expense</font></td>
</tr>
</table>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">As of December 31,
2009, Generation’s remaining costs to be recognized related
to the rate relief commitment are $20 million, consisting of $13
million related to programs for ComEd customers and $7 million for
programs for customers of other Illinois utilities. ComEd’s
remaining costs to be recognized related to the rate relief
commitment are $1 million as of December 31, 2009.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; MARGIN-LEFT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><i>Energy Efficiency and
Renewable Energy</i></font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: -6px"><font size="1"> </font></p>
<table style="BORDER-COLLAPSE: collapse" cellspacing="0" cellpadding="0" width="100%" border="0">
<tr>
<td width="4%"><font size="1"> </font></td>
<td valign="top" align="left" width="2%"><font style="FONT-FAMILY: ARIAL" size="2">•</font></td>
<td valign="top" width="1%"> </td>
<td valign="top" align="left">
<p align="left"><font style="FONT-FAMILY: ARIAL" size="2">Electric
utilities in Illinois are required to include cost-effective energy
efficiency resources in their plans to meet an incremental annual
program energy savings requirement of 0.2% of energy delivered to
retail customers for the year ended June 1, 2009, which
increases annually to 2% of energy delivered in the year commencing
June 1, 2015 and each year thereafter. Additionally, during
the ten year period that began June 1, 2008, electric
utilities must implement cost-effective demand response measures to
reduce peak demand by 0.1% over the prior year for eligible retail
customers. The energy efficiency and demand response goals are
subject to rate impact caps each year. Utilities are allowed
recovery of costs for energy efficiency and demand response
programs, subject to approval by the ICC. In February 2008,
the ICC issued an order approving substantially all of
ComEd’s Energy Efficiency and Demand Response Plan, including
cost recovery. This plan began in June 2008 and is designed to meet
the Illinois Settlement Legislation’s energy efficiency and
demand response goals for an initial three-year period, including
reductions in delivered energy to all retail customers and in the
peak demand of eligible retail customers. During the years ended
December 31, 2009 and 2008, expenses related to energy
efficiency and demand response programs consisted of $59 million
and $25 million, respectively.</font></p>
</td>
</tr>
</table>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: -6px"><font size="1"> </font></p>
<table style="BORDER-COLLAPSE: collapse" cellspacing="0" cellpadding="0" width="100%" border="0">
<tr>
<td width="4%"><font size="1"> </font></td>
<td valign="top" align="left" width="2%"><font style="FONT-FAMILY: ARIAL" size="2">•</font></td>
<td valign="top" width="1%"> </td>
<td valign="top" align="left">
<p align="left"><font style="FONT-FAMILY: ARIAL" size="2">Since
June 1, 2008, utilities have been required to procure
cost-effective renewable energy resources in amounts that equal or
exceed 2% of the total electricity that each electric utility
supplies to its eligible retail customers. ComEd is also required
to acquire amounts of renewable energy resources that will
cumulatively increase this percentage to at least 10% by
June 1, 2015, with an ultimate target of at least 25% by
June 1, 2025, subject to customer rate cap limitations. All
goals are subject to rate impact criteria set forth in the Illinois
Settlement Legislation. Under a May 2008 ICC-approved RFP, ComEd
procured RECs for the period June 2008 through May 2009. On
May 13, 2009, the ICC approved the results of an RFP to
procure RECs for the period June 2009 through May 2010. ComEd
currently retires all RECs immediately upon purchase. Since June
2008, ComEd recovers procurement costs of RECs through rates. See
Note 18—Commitments and Contingencies for further information
regarding ComEd’s procurement of RECs.</font></p>
</td>
</tr>
</table>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>Illinois
Procurement Proceedings (Exelon, Generation and
ComEd).</i></b> ComEd is permitted to recover its electricity
procurement costs from retail customers without mark-up. Beginning
on January 1, 2007, ComEd procured 100% of energy to meet its
load service requirements through ICC-approved staggered SFCs with
various suppliers, including Generation. For the period from June
2008 to May 2009, the ICC approved an interim procurement plan
under which ComEd procured energy to meet its load service
requirements through an RFP for standard wholesale products,
existing SFC and spot market purchases hedged by a five-year
variable to fixed financial swap contract with
Generation.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">Beginning in June 2009,
under the Illinois Settlement Legislation, the IPA designs, and the
ICC approves, an electricity supply portfolio for ComEd and
administers a competitive process under which ComEd procures its
electricity supply. On January 7, 2009, the ICC approved the
IPA’s plan for procurement of ComEd’s expected energy
requirements from June 2009 through May 2010, which includes
approximately 38% of ComEd’s expected energy requirements
purchased through the spot market and hedged by the financial swap
contract with Generation. The remainder of ComEd’s expected
energy requirements will be met through the existing SFC and
standard products purchased as a result of the 2009 RFP process
completed in May 2009. In addition, approximately 9% of
ComEd’s energy requirements from June 2010 through May 2011
were procured through the 2009 RFP process.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">On September 30,
2009, the IPA filed its procurement plan with the ICC covering June
2010 through May 2015. On December 28, 2009, the ICC approved
this plan which will result in approximately 66% of ComEd’s
expected energy purchases for the June 2010 to May 2011 period
being purchased through the spot market and hedged by the financial
swap contract with Generation. The remainder of ComEd’s
expected energy purchases would be met through the purchases of
standard products in the 2009 and 2010 RFP processes. The
IPA’s plan also includes a provision for procurement of
approximately 3.5% of ComEd’s fixed-price load requirements
from renewable energy resources utilizing long-term contracts
beginning June 2012. The long term renewables purchased would count
towards satisfying ComEd’s obligation under the state’s
RPS. See Note 8—Derivative Financial Instruments for further
discussion on the financial swap contract.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">The ICC has initiated a
proceeding to reconcile the actual costs of power purchased in the
January 2007 through May 2008 period with the costs for power that
flowed through ComEd’s tariffs and were collected from
customers. Because the Illinois Settlement Legislation has already
deemed such costs to be prudently incurred, the reconciliation
proceeding is not expected to have a significant impact on
ComEd.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>2005 Rate Case
(Exelon and ComEd).</i></b> In August 2005, ComEd filed a
rate case with the ICC to comprehensively revise its tariffs and to
adjust rates for delivering electricity effective January 2007
(2005 Rate Case). ComEd proposed a revenue increase of
$317 million. During 2006, the ICC issued various orders
associated with this case, which resulted in a total annual rate
increase of $83 million effective January 2007. ComEd and various
other parties appealed the rate order to the courts. In September
2009, the Appellate Court of Illinois affirmed the ICC’s
order and denied the appeals. Several parties have asked the
Appellate Court to rehear various rate design issues addressed in
the opinion. There is no set time in which the Court must
act.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>Original Cost Audit
(Exelon and ComEd).</i></b> In connection with ComEd’s
2005 Rate Case proceeding, the ICC, with ComEd’s concurrence,
ordered an “original cost” audit of ComEd’s
distribution assets. In December 2007, the consulting firm
completed the audit. The consulting firm’s results of the
audit were reported to the ICC in April 2008, which presented its
findings regarding accounting methodology, documentation and other
matters, along with proposed adjustments. The audit report
recommended gross plant disallowances of approximately $350
million, before reflecting accumulated depreciation. The basis for
the disallowance recommendation on approximately $80 million of the
costs was that the assets were misclassified between ComEd’s
distribution and transmission operations. ComEd reclassified these
costs in September 2007 and they were reflected correctly in
ComEd’s rate case filed in October 2007 (2007 Rate
Case).</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">In April 2008, ComEd
and the ICC Staff reached a stipulation (the stipulation) regarding
various portions of contested issues in the Original Cost Audit as
well as the 2007 Rate Case and agreed to make various joint
recommendations to the ICC in the 2007 Rate Case. In
September 2008, the ICC issued an order in the 2007 Rate Case,
which reflected the joint recommendations made by the ICC Staff and
ComEd and required ComEd to incur a charge of approximately $19
million (pre-tax) related to various items identified in the
Original Cost Audit.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">The ICC opened a
proceeding on the Original Cost Audit in May 2008. Under the terms
of the stipulation, the ICC Staff agreed not to advocate that any
of the proposed adjustments in the audit report be adopted other
than those reflected in the 2007 Rate Case; however, the
stipulation does not preclude other parties to the rate case or to
the Original Cost Audit proceeding from taking positions contrary
to the stipulation. The Illinois Attorney General submitted
testimony and legal briefs suggesting that ComEd improperly changed
the way it capitalized certain cable faults during the rate freeze
period and therefore the rate base should be reduced by $121
million and ComEd should refund at least $42 million to customers.
On January 12, 2010, the ICC issued an order rejecting the
Illinois Attorney General’s recommendations in their
entirety. The order is subject to rehearing and appeal.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>2007 Rate Case
(Exelon and ComEd).</i></b> ComEd filed the 2007 Rate Case
with the ICC for approval to increase its delivery service revenue
requirement by approximately $360 million. The ICC issued an order
in the rate case approving a $274 million increase in ComEd’s
annual revenue requirement, which became effective in September
2008. ComEd and several other parties have filed appeals of the
rate order with the courts. ComEd cannot predict the timing of
resolution or the results of the appeals. In the event the order is
ultimately changed, the changes are expected to be
prospective.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">The 2007 Rate Case filing
also included a system modernization rider, which the ICC approved
for the limited purpose of implementing a pilot program for AMI.
The rider permits investments in AMI to be reflected in rates on a
quarterly basis instead of waiting for the next rate case to begin
recovery. On June 1, 2009, ComEd filed its proposed AMI pilot
program with the ICC, which included revisions to the system
modernization rider. On October 14, 2009, the ICC approved
ComEd’s proposed AMI pilot program, with minor modifications,
and recovery of substantially all program costs under the rider.
The AMI pilot program allows ComEd to study the costs and benefits
related to automated metering and to develop the cost estimate of
full system-wide implementation of AMI. In addition, the program
allows customers the ability to manage energy use, improve energy
efficiency and lower energy bills. The Illinois Attorney General
has appealed the ICC order approving the plan. The matter is not
yet briefed.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">In August 2009, ComEd
filed a request for $175 million of matching Federal stimulus
grants with the DOE under the ARRA of 2009 to help finance AMI and
Smart Grid technologies in Illinois; however, ComEd did not receive
any of the matching grant awards announced by DOE in October
2009.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>Transmission Rate
Case (Exelon and ComEd).</i></b> ComEd’s transmission
rates are established based on a formula that was approved by FERC
in January 2008. FERC’s order establishes the agreed-upon
treatment of costs and revenues in the determination of network
service transmission rates and the process for updating the formula
rate calculation on an annual basis.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">ComEd’s most recent
annual formula rate update filed in May 2009 reflects actual 2008
expenses and investments plus forecasted 2009 capital additions.
The time for parties to challenge the update has expired; no
parties have raised challenges and ComEd will move to close the
docket. The update resulted in a revenue requirement of $436
million resulting in an increase of approximately $6 million from
the 2008 revenue requirement, plus an additional $4 million related
to the 2008 true-up of actual costs. The 2009 revenue
requirement of $440 million, which includes the 2008
true-up, became effective June 1, 2009 and is recovered
over the period extending through May 31, 2010. The
regulatory asset associated with the true-up is being amortized as
the associated revenues are received. ComEd will continue to
reflect its best estimate of its anticipated true-up in the
financial statements.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>Illinois
Legislation for Recovery of Uncollectible Accounts (Exelon and
ComEd).</i></b> Comprehensive legislation has been enacted in
Illinois that provides utilities the ability to adjust their rates
annually through a rider mechanism to reflect the increases or
decreases in annual uncollectible accounts expenses starting with
2008 and prospectively. ComEd under-collected approximately $26
million during 2008 and approximately $44 million during 2009.
On September 8, 2009, ComEd filed a proposed tariff in
accordance with the legislation. On February 2, 2010, the ICC
issued an order adopting ComEd’s proposed tariffs, with minor
modifications.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">With the ICC approval of
the tariff, ComEd is required to make a one-time contribution of
approximately $10 million to the Supplemental Low-Income Energy
Assistance Fund (the Fund). The Fund is used to assist low-income
residential customers. As one way to assist such customers, the
legislation creates a new percentage of income payment program
(PIPP) that includes an arrearage reduction component for
participating customers. The program will be paid for from the Fund
and other state monies.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">As a result of the ICC
order, ComEd will record the $70 million benefit and the $10
million one-time charge in the first quarter of 2010. ComEd will
record a regulatory asset and an offsetting reduction in operating
and maintenance expense for the cumulative under-collections from
2008 and 2009. Recovery of the initial regulatory asset will take
place over an approximate 14-month time frame beginning in April
2010.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>Pennsylvania Gas
Distribution Rate Case (Exelon and PECO).</i></b> In
October 2008, the PAPUC voted to approve the joint settlement
related to PECO’s March 2008 filing providing for an increase
of $77 million to its annual natural gas distribution revenue. As
part of the settlement, PECO agreed to enhance its low-income
programs as well as provide funding for new energy-efficiency
programs to help customers manage their energy usage and gas bills.
Additionally, PECO agreed not to file a new base rate case for
natural gas distribution service before January 1, 2010. The
approved rate adjustment became effective on January 1,
2009.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>Pennsylvania
Transition-Related Legislative and Regulatory Matters (Exelon,
Generation and PECO).</i></b> In Pennsylvania, despite the
recent decline in wholesale electricity market prices, there has
been some continuing interest from elected officials in mitigating
the potential impact of electric generation price increases on
customers when rate caps expire. While PECO’s retail electric
generation rate cap transition period does not end until
December 31, 2010, transition periods have ended for seven
other Pennsylvania electric distribution companies and, in most
instances, post-transition electric generation price increases
occurred. Over the past few years, elected officials in
Pennsylvania have worked on developing legislation to address
concerns over post-transition electric generation price increases.
Measures suggested by legislators include rate-increase deferrals
and phase-ins, rate-cap extensions, a generation tax and
contributions of value by Pennsylvania utility companies toward
rate-relief programs.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">On March 12, 2009,
the PAPUC approved the settlement of PECO’s Market Rate
Transition Phase-In Program. The program allows eligible
residential and small-business electric-service customers to
transition to market-priced generation through pre-payments made
through 2010 that accrue interest at the statutory rate of 6% and
are to be applied as credits to their bills in 2011 and 2012. Total
collections under this program were not significant as of
December 31, 2009.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">On June 9, 2009, the
PAPUC entered an order instituting an investigation into whether
PECO’s nuclear decommissioning cost adjustment clause, which
is a mechanism that allows PECO to recover costs from customers for
the decommissioning of seven former PECO nuclear units now owned by
Generation, should continue after the termination of PECO’s
competitive transition cost collections on December 31, 2010
and assigned the matter for alternative dispute resolution or the
prompt scheduling of such hearings as may be necessary. On
October 14, 2009, a prehearing conference was held and PECO
agreed to report to the ALJ on settlement progress. Settlement
discussions continue and PECO has been providing the ALJ with
periodic reports on settlement progress. See Note 11—Asset
Retirement Obligations for additional information.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>Pennsylvania
Procurement Proceedings (Exelon and PECO).</i></b> On
June 2, 2009, the PAPUC entered an order approving the
settlement of PECO’s DSP Program, under which PECO will
provide default electric service following the expiration of
electric generation rate caps on December 31, 2010. The DSP
Program, which has a 29-month term beginning January 1, 2011
and ending May 31, 2013, complies with electric supply
procurement guidelines set forth in Act 129. Under the settlement,
PECO will also expand its low-income assistance initiatives and
offer a market rate deferral program under which certain customers
can elect to phase-in, with interest, any post-electric generation
rate cap increases in 2011 if they exceed 25%.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">PECO’s default
electric service customers have been divided into four procurement
classes: a residential class, a small commercial class (for
non-residential customers with peak demand up to 100 kW), a medium
commercial class (for non-residential customers with peak demand of
greater than 100 kW up to 500 kW) and a large commercial and
industrial class (for non-residential customers with peak demand in
excess of 500 kW).</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">Seventy-five percent of
the residential class load, 90% of the small commercial class load
and 85% of the medium commercial class load will be served through
competitively procured contracts for load-following, fixed price
full requirements default electric supply. For the remaining
portion of the residential class load, PECO will competitively
procure through block contracts, which represent 20% of the load
and will balance the remaining load through sales and purchases of
energy in the PJM day-ahead wholesale “spot” energy
market (spot market). For the remaining portion of the small
commercial and medium commercial class loads, as well as the large
commercial and industrial class load, PECO will competitively
procure contracts for load-following, full requirements default
electric supply with the price for energy in each contract set to
be the hourly price of the spot market during the term of delivery.
In addition, PECO will offer large commercial and industrial
customers a fixed-price optional service during the first year of
PECO’s DSP Program.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">In 2009, PECO completed
two competitive procurements in accordance with the DSP Program for
electric supply for default electric service customers commencing
January 2011. As of December 31, 2009, PECO has entered into
contracts with terms of 17 to 29 months covering 49% of planned
full requirements contracts for the residential customer class,
contracts with 17-month terms covering 24% of planned full
requirements contracts for the small commercial customer class and
contracts with 17-month terms covering 16% of planned full
requirements contracts for the medium commercial customer class.
PECO also entered into block contracts with 12-month terms for a
total of 80 MW for service to the residential customer class in
2011. PECO will conduct seven additional competitive procurements
in accordance with the DSP Program.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>Smart Meter and
Smart Grid Investments (Exelon and PECO).</i></b> PECO is planning
to spend up to approximately $650 million on its smart meter and
smart grid infrastructure. On November 25, 2009, PECO filed a
joint petition for partial settlement of its $550 million Smart
Meter Procurement and Installation Plan with the PAPUC, which was
filed on August 14, 2009 in accordance with the requirements
of Act 129. PECO is requesting PAPUC approval to install more than
1.6 million smart meters and deploy advanced communication
networks over a 15 year period. The first phase of the plan
includes the procurement and deployment of automated meter
infrastructure and an initial deployment of 100,000 smart meters
over the next three years. On January 28, 2010, the ALJ issued
an initial decision approving the partial settlement and
determining remaining cost allocation issues subject to final PAPUC
approval. PECO plans to file for PAPUC approval of an initial
dynamic pricing and customer acceptance program in June 2010 and
for approval of a universal meter deployment plan for its remaining
customers in 2012.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">On August 6, 2009,
PECO filed with the DOE an application seeking $200 million in ARRA
of 2009 matching grant funds under the Smart Grid Investment Grant
Program. PECO’s “Smart Future Greater
Philadelphia” project will increase the number of smart
meters initially installed to 600,000, accelerate universal smart
meter deployment by five years and increase Smart Grid investments
up to approximately $100 million over the next three years. On
October 27, 2009, the DOE announced its intent to award PECO a
$200 million stimulus grant to fund its smart meter and smart grid
investments. Assuming successful completion of the DOE negotiations
and PECO’s receipt of the full award on reasonable terms,
PECO is committed to implementing expanded initial deployment of
600,000 smart meters within three years and then accelerating
universal smart meter deployment from 15 years to 10
years.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>Energy Efficiency
and Alternative Energy Programs (Exelon and
PECO).</i></b></font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><i>Energy Efficiency
Programs.</i> Pursuant to Act 129’s energy efficiency
and conservation/demand (EE&C) reduction targets, PECO filed
its EE&C plan with the PAPUC on July 1, 2009. The plan set
forth how PECO will reduce electric consumption by at least 1% in
its service territory by May 31, 2011 from expected
consumption for the period June 1, 2009 through May 31,
2010 and by 3% by May 31, 2013. In accordance with Act 129,
PECO also plans to reduce peak demand by a minimum of 4.5% of
PECO’s annual system peak demand in the 100 hours of highest
demand by May 31, 2013, measured against its peak demand
during the period of June 1, 2007 through May 31, 2008.
If PECO fails to achieve the required reductions in consumption
within the stated deadlines, PECO will be subject to civil
penalties of up to $20 million, which would not be recoverable from
ratepayers. Act 129 mandates that the total cost of any EE&C
plan may not exceed 2% of the electric company’s total annual
revenue as of December 31, 2006. On October 28, 2009, the
PAPUC issued an order providing partial approval of PECO’s
EE&C plan. The approved plan totals more than $330 million and
includes the CFL program, weatherization programs, an energy
efficiency appliance rebate and trade-in program, rebates and
energy efficiency programs for non-profit, educational,
governmental and business customers, customer incentives for energy
management programs and incentives to help customers reduce energy
demand during peak periods. On December 24, 2009, PECO filed
revisions to the portions of the plan not approved based on PAPUC
feedback.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><i>Alternative Energy
Portfolio Standards.</i> In November 2004, Pennsylvania
adopted the AEPS Act. The AEPS Act mandated that beginning in 2007,
or following the end of an electric distribution company’s
retail electric generation rate cap transition period, certain
percentages of electric energy sold by an electric distribution
company or electric generation supplier to Pennsylvania retail
electric customers shall be generated from certain alternative
energy resources as measured in AECs. The requirement for electric
energy that must come from Tier I alternative energy resources
(including solar or wind power, low-impact hydropower, geothermal
energy, biologically derived methane gas, fuel cells, biomass
energy generated within Pennsylvania and coal mine methane) ranges
from 1.5% to 8.0% and the requirement for Tier II alternative
energy resources (including waste coal, biomass energy generated
outside of Pennsylvania, demand-side management, large-scale
hydropower, municipal solid waste, generation of electricity
utilizing by-products of the pulping process and wood, distributed
generation systems and integrated combined coal gasification
technology) ranges from 4.2% to 10.0%. These Tier I and Tier II
alternative energy resources include acceptable energy sources as
set forth in Act 129 in addition to those outlined in the AEPS Act.
The AEPS Act mandates the 8.0% requirement for Tier I
resources and the 10.0% requirement for Tier II resources must
be met by the year ending May 31, 2021.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">The Pennsylvania
Legislature is currently considering HB 80, which, if enacted into
law, would increase the minimum required percentage of electric
energy purchased and sold to retail electric customers from
alternative energy resources and extend the period for such
purchases and sales. HB 80 would increase the Tier 1 and solar
purchase and sale requirements, limit eligible solar purchases to
Pennsylvania generating sources and incorporate advanced coal
combustion with limited carbon emissions as an acceptable
alternative energy resource. Generation has proposed
amendments to include extended nuclear uprates as a qualifying
alternative energy source.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">In 2007, the PAPUC
approved PECO’s plan to acquire and bank approximately
450,000 non-solar Tier I AECs (corresponding to the expected annual
output of approximately 240 MW of wind power) annually for a
five-year term in order to prepare for 2011, the first year of
PECO’s required compliance following the completion of its
electric generation rate cap transition period. The banked AECs may
be used in either of the two consecutive AEPS reporting periods
after PECO’s electric generation rate cap transition period.
All costs incurred in connection with AEC procurement prior to 2011
are being deferred as a regulatory asset with a return on the
unamortized balance and will be recovered from customers in 2011.
Those costs, and PECO’s AEPS Act compliance costs incurred
thereafter, will be recovered from customers on a full and current
basis through a reconcilable ratemaking mechanism as contemplated
by the AEPS Act. In conformance with the approved plan, PECO has
entered into five-year agreements with accepted bidders, including
Generation, totaling 452,000 AECs to be purchased
annually.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">On August 27, 2009,
the PAPUC approved a settlement of PECO’s petition for early
procurement and banking of up to 8,000 solar Tier 1 AECs annually
for ten years. PECO’s procurement would employ the same
surcharge cost-recovery mechanism that the PAPUC previously
approved for non-solar Tier 1 AECs. The settlement provides for no
cap on bid price, provides the PAPUC a 10 calendar day review
period, permits facilities capable of generating a minimum of 300
AECs annually to bid and provides that no changes to the agreement
with AEC suppliers will be accepted after PAPUC approval. On
January 25, 2010, the PAPUC approved the fixed-price agreement
solar AEC procurement results. PECO plans to enter into the
fixed-price agreements by February 8, 2010.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>PJM Transmission
Rate Design (Exelon, ComEd and PECO).</i></b> PJM Transmission
Rate Design specifies the rates for transmission service charged to
customers within PJM. Currently, ComEd and PECO incur costs based
on the existing rate design, which charges customers based on the
cost of the existing transmission facilities within their load zone
and the cost of new transmission facilities based on those who
benefit. In April 2007, FERC issued an order concluding that
PJM’s current rate design for existing facilities is just and
reasonable and should not be changed. In the same order, FERC held
that the costs of new facilities 500 kV and above should be
socialized across the entire PJM footprint and that the costs of
new facilities less than 500 kV should be allocated to the
customers of the new facilities who caused the need for those
facilities. In the short term, based on new transmission facilities
approved by PJM, it is likely that allocating across PJM the costs
of new facilities 500 kV and above will increase charges to ComEd
and reduce charges to PECO, as compared to the allocation
methodology in effect before the FERC order. After FERC ultimately
denied all requests for rehearing on all issues, several parties
filed petitions in the U.S. Court of Appeals for the Seventh
Circuit for review of the decision. On August 6, 2009, the
court issued its decision affirming FERC’s order with regard
to the costs of existing facilities but reversing and remanding to
FERC for further consideration its decision with regard to the
costs of new facilities 500 kV and above. On September 21,
2009, two parties filed a petition for rehearing by the full court
concerning the court’s decision to remand to FERC the part of
the decision regarding the allocation of the costs of new
facilities 500 kV and above. On October 20, 2009, the court
denied the rehearing petition. On January 21, 2010, FERC
issued an order establishing paper hearing procedures to supplement
the record. ComEd anticipates that all impacts of any rate design
changes effective after December 31, 2006 should be
recoverable through retail rates and, thus, the rate design changes
are not expected to have a material impact on ComEd’s results
of operations, cash flows or financial position. PECO also has the
right to file with the PAPUC for a change in retail rates to
reflect changes in its wholesale transmission costs. PECO cannot
predict the long-term impact of any rate design changes due to the
uncertainty as to whether new facilities will be built and how the
costs of new facilities less than 500 kV will be allocated;
however, the impact may be material to its results of operations,
cash flows, or financial position.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>PJM-MISO Regional
Rate Design (Exelon, ComEd and PECO).</i></b> The current
PJM-MISO Regional Rate Design is used to specify the pricing of
transmission service between PJM and MISO and impacts ComEd and
PECO due to purchases by suppliers from MISO. In August 2007, ComEd
and PECO and several other transmission owners in PJM and MISO, as
directed by a FERC order, filed with FERC to continue the existing
transmission rate design between PJM and MISO. Additional
transmission owners and certain other entities filed protests
urging FERC to reject the filing. In September 2007, a
complaint was filed asking FERC to find that the PJM-MISO rate
design was unjust and unreasonable and to substitute a rate design
that socializes the costs of all existing and new transmission
facilities of 345 kV and above across PJM and MISO. In December
2008, FERC denied a request for rehearing of these orders and an
appeal was filed in the United States Court of Appeals. On
November 9, 2009, the court dismissed the appeal at the
request of the appellant.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>Authorized Return
on Rate Base (Exelon, ComEd and PECO).</i></b> In the
September 2008 order in the 2007 Rate Case, the ICC authorized a
return on ComEd’s distribution rate base using a weighted
average debt and equity return of 8.36%, an increase over the 8.01%
return previously authorized in the 2005 Rate Case. ComEd’s
formula transmission rate currently provides for a weighted average
debt and equity return on transmission rate base of 9.43%, an
increase over the 9.37% return previously authorized. As part of
the FERC-approved settlement of ComEd’s 2007 transmission
rate case, the rate of return on common equity is 11.5% and the
common equity component of the ratio used to calculate the weighted
average debt and equity return for the formula transmission rate is
currently capped at 57%. This equity cap is reduced to 56% in June
2010 and 55% in June 2011 and subsequent years. This transmission
rate base return is updated annually in accordance with the
formula-based rate calculation discussed above.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">PECO’s transition
period includes caps on electric generation rates that will expire
on December 31, 2010 pursuant to the Competition Act. The
electric distribution and transmission components of PECO’s
rates continue to be regulated. PECO’s most recently approved
weighted average debt and equity return on electric rate base,
which included electric generation, was 11.23% (approved in 1990).
PECO’s purchased gas cost rates are not subject to caps and
do not earn a return. As part of the gas distribution rate case
filed in March 2008, PECO requested that the PAPUC
authorize it to establish base rates for natural gas
distribution service using a weighted average debt and equity
return on gas rate base of 8.90%. The joint settlement
petition in that matter, approved in October 2008 by the PAPUC, did
not specify the rate of return upon which the settlement rates are
based, but rather provided for an increase in annual revenue. Prior
to the 2008 gas distribution rate case, the most recently approved
weighted average debt and equity return on gas rate base was 11.45%
(approved in 1988).</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>Market-Based Rates
(Exelon, Generation, ComEd and PECO).</i></b> Generation,
ComEd and PECO are public utilities for purposes of the Federal
Power Act and are required to obtain FERC’s acceptance of
rate schedules for wholesale electricity sales. Currently,
Generation, ComEd and PECO have authority to execute wholesale
electricity sales at market-based rates. As is customary with
market-based rate schedules, FERC has reserved the right to suspend
market-based rate authority on a retroactive basis if it
subsequently determines that Generation, ComEd or PECO has violated
the terms and conditions of its tariff or the Federal Power Act.
FERC is also authorized to order refunds if it finds that the
market-based rates are not just and reasonable under the Federal
Power Act.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">In June 2007, FERC
issued a Final Rule on Market-Based Rates for Wholesale Sales of
Electric Energy, Capacity and Ancillary Services by Public
Utilities (Order No. 697), which updated and modified the
tests that FERC had implemented in 2004. That order was clarified
in December 2007. Subsequently, Order No. 697 was largely
affirmed and further clarified in Order No. 697-A, Order
No. 697-B and Order No. 697-C. The Registrants do not
expect that the Final Rule will have a material effect on their
results of operations in the short-term. The longer-term impact
will depend on the future application by FERC of Order Nos. 697 and
future actions involving market-based rates.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">During 2008, Generation,
ComEd and PECO filed an analysis for generation in the Northeast
region covering generation in PJM and ISO-New England and
Generation filed an analysis for generation in the Southeast region
covering generation in the Southern Company and Entergy areas; and
in 2009, Generation filed an analysis for generation in the Central
region covering generation in the MISO market. In each case, the
filing used FERC’s updated screening tests, as required by
the Final Rule. These analyses demonstrated that Exelon does not
have market power in those areas and, therefore, is entitled to
continue to sell at market-based rates in them. FERC accepted the
2008 filings on January 15, 2009 and September 2, 2009
and accepted the 2009 filing on October 26, 2009, affirming
Exelon’s affiliates’ continued right to make sales at
market-based rates.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>Reliability Pricing
Model (Exelon and Generation).</i></b> On August 31,
2005, PJM submitted a proposal to FERC for a new capacity
payment construct to replace PJM’s then-existing
capacity obligation rules. The proposal provided for a
forward capacity procurement auction to establish
capacity and payment obligations using a demand curve and
locational deliverability zones for capacity. The FERC
affirmed PJM’s proposal for forward commitments and other
matters, but encouraged PJM and the parties to that
FERC proceeding to resolve other RPM issues by
settlement. A settlement was reached on September 29,
2006 and was approved by FERC on December 22,
2006. The settlement provided for an auction 36
months in advance of each delivery year beginning with the
delivery year ending May 31, 2012 and an
expedited phase-in process for four transitional auctions
covering delivery years ending on
May 31 in 2008 through 2011. All but
one appeal of FERC’s order approving RPM were withdrawn on
February 27, 2009 and the remaining appeal was denied by the
U.S. Court of Appeals for the District of Columbia Circuit (D.C.
Circuit) on March 17, 2009.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">PJM’s four
transitional RPM auctions took place in April 2007, July
2007, October 2007 and January 2008 and established prices for
the period from June 1, 2007 through May 31,
2011. Subsequent auctions will take place 36 months ahead of
the scheduled delivery year. The auction for the delivery year
ending May 31, 2012 and May 31, 2013 occurred in May 2008
and May 2009, respectively. Thus far, the RPM capacity
auctions have secured capacity for the PJM market through 2013.
While auction results produced varying prices, as anticipated, the
RPM has been beneficial for owners of generation facilities,
particularly for such facilities located in constrained zones, as
compared to the prior capacity-payment construct.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">On May 30, 2008, a
group of PJM load-serving entities, state commissions, consumer
advocates and trade associations (referred to collectively as the
RPM Buyers) filed a complaint at FERC against PJM alleging
that three of the four transitional RPM auctions yielded
prices that are unjust and unreasonable under the Federal Power
Act. Most of the parties comprising the RPM Buyers group were
parties to the settlement approved by FERC that established
RPM. In the complaint, the RPM Buyers requested that the total
projected payments to RPM sellers for the three auctions at issue
be materially reduced. On September 19, 2008, FERC
dismissed the complaint finding that no party violated PJM’s
tariff and the prices determined during the initial auctions
implementing the RPM were in accord with the tariff provisions
governing the auctions. On June 18, 2009, FERC denied the RPM
Buyers’ request for rehearing of FERC’s
September 19, 2008 order. On August 14, 2009, RPM Buyers
filed a petition with the U.S. Court of Appeals for the Fourth
Circuit for review of the FERC’s September 19, 2008
order, rejecting their complaint that RPM resulted in unjust and
unreasonable capacity prices. On September 17, 2009, PJM filed
a motion to transfer the case to the D.C. Circuit on the grounds
that the Fourth Circuit was an improper venue. On
November 12, 2009, the court granted the motion. If the D.C.
Circuit were to reverse FERC’s decision, FERC would be
required to conduct additional proceedings regarding the
substantive allegations in the complaint. Exelon and Generation
believe that it is remote that the ultimate outcome of this matter
will have a material adverse impact on their respective results of
operations, cash flows or financial position.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">In a companion order also
issued on September 19, 2008, FERC directed PJM and its
stakeholders to evaluate whether prospective changes should be made
to RPM and, if a consensus is reached, file such a consensus with
FERC in time to be in effect for the May 2009 RPM Auction. PJM
filed a report with FERC on December 12, 2008 summarizing the
discussions and explaining that a consensus was not reached. PJM
also filed its own proposal with FERC on December 12, 2008. On
March 26, 2009, FERC issued an order accepting in part and
rejecting in part PJM’s December 12 filing, as amended
by an Offer of Settlement filed by PJM and some members of PJM in
response to the December 12 filing. A number of parties filed
for rehearing and/or clarification of the March 26, 2009
Order. On August 14, 2009, the Commission granted in part and
denied in part requests for rehearing and clarification. Any order
may then be subject to review in the United States Court of
Appeals.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2"><b><i>License Renewals
(Exelon and Generation).</i></b> In July 2005, Generation
applied for license renewal for Oyster Creek on a timeline
consistent and integrated with the other planned license renewal
filings for the Generation nuclear fleet. The application was
challenged by a coalition of citizen groups (citizen groups) and
the NJDEP, including filings made with the NRC’s ASLB, the
NRC Commissioners and the U.S. Court of Appeals for the Third
Circuit. These filings and appeals were rejected or denied. On
April 8, 2009, the NRC issued the renewed operating license
for Oyster Creek that expires in April 2029. On May 29, 2009,
the citizen groups filed a Petition for Review of the NRC’s
renewal of Oyster Creek’s operating license in the U.S. Court
of Appeals for the Third Circuit. If the appeal is successful, it
is unlikely that it would result in a revocation of the renewed
license; however, it could cause the NRC to impose additional
conditions over the course of the period of extended
operation.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">On January 8, 2008,
AmerGen submitted an application to the NRC to extend the operating
license of TMI Unit 1 for an additional 20 years. On
October 22, 2009, the NRC issued the renewed operating license
for TMI Unit 1 that expires in April 2034.</font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px"><font size="1"> </font></p>
<p style="MARGIN-TOP: 0px; MARGIN-BOTTOM: 0px; TEXT-INDENT: 4%">
<font style="FONT-FAMILY: ARIAL" size="2">On August 18, 2009,
PSEG submitted an application to the NRC to extend the operating
license of Salem Units 1 and 2 by 20 years. Exelon is part owner of
the Salem Units. The NRC is expected to spend a total of 22 to 30
months to review the application before making a decision. The
current operating licenses expire in 2016 and 2020,
respectively.</font></p>
</div>2. Regulatory Issues (Exelon,
Generation, ComEd and PECO)
 
Illinois Settlement
Agreement (Exelon, Generation and ComEd). In July
2007,falsefalseNo definition available.No authoritative reference available.falsefalse11falseUnKnownUnKnownUnKnownfalsetrue