This report beside the one the company filed the year before, on Thursday, February 20, 2025: the paragraphs that are new, the ones that are gone and the ones that were reworded. Every word below is the company’s own, from one report or the other, and each paragraph links to its place. A program compares the two; no AI has a part in it. How this is made

Risk factors · Business

Risk factors

New
12 paragraphs
Gone
20 paragraphs
Reworded
100 paragraphs
Word for word as before
41 of 155

2 more differ only in a number or a date, and are not shown.

New in this report

Following the February 2021 Winter Storm Event, the Texas legislature passed a law to allow TDUs, such as Houston Electric, to lease and temporarily operate TEEEF during widespread power outages where ERCOT has ordered a TDU to Load Shed or the TDU’s distribution facilities are not being fully served by the bulk power system under normal operations. In response to this legislation, Houston Electric began leasing large (27 MW to 32 MW) TEEEF and medium (5.7 MW) TEEEF. In 2023, the Texas legislature amended the law to allow wider use of TEEEF, and in response, Houston Electric has entered into contractual arrangements to facilitate access to small (200 kW to 1,250 kW) TEEEF units; the small TEEEF units represent approximately 4% of the MWs of Houston Electric’s total portfolio of TEEEF assets. In 2025, following the passage of the TEEEF Rule, Houston Electric requested from the PUCT preapproval to lease small TEEEF units for a three-year term. These proceedings remain ongoing and, until PUCT preapproval is received, Houston Electric plans to maintain the current contractual arrangement providing access to the small TEEEF units on a month-to-month basis. See Note 7 to the consolidated financial statements for further information. Additionally, in June 2025, the law was further amended to provide that, effective on or after the date of the amendment’s passage, TDUs may only enter into, renew or extend leases for TEEEF units with a maximum generation capacity of five or fewer MW and that are rapidly deployable. The law prescribes …

Our successful execution and completion of capital projects and programs, including those within our 10-year capital plan, are subject to substantial risks, and our business, financial condition, results of operations and cash flows could be materially affected should such efforts not be executed and completed as planned.

We are managing ongoing, and planning future, significant capital projects relating to, among other things, improvements to our electric and natural gas transmission and distribution infrastructure. The execution of our capital projects, including those within our 10-year capital plan, may not be completed in accordance with current expectations or produce the desired results. Our ability to execute and complete our capital projects, including Houston Electric’s proposed 765 kV and other transmission projects, in a timely and cost-effective manner and within budget is contingent upon many variables and subject to substantial risks. These variables and risks include, but are not limited to, availability of and costs for materials, equipment, commodities and qualified labor; cost and availability of financing; cost of regulatory compliance; economic and market conditions; regulatory approvals, licensing and permitting; land and easement acquisition (including requirements and constraints relating to eminent domain); regulatory, political, public and community relations risks (including in relation to customer affordability concerns); tax law; our ability to capitalize on business opportunities and such opportunities providing desirable rates of return; load growth (including our forecasts thereof) and our ability to capitalize on opportunities relating thereto; safety and environmental requirements; the ability of third parties to provide timely and satisfactory performance under their contracts; delays and cost increases; and supply chains and material constraints. Certain events that may be beyond our control may occur that materially affect the schedule, cost and performance of these projects, including Houston Electric’s proposed 765 kV and other transmission projects. These events may …

In the planning and management of our operations, we must address existing and proposed laws and regulations regarding safety, reliability and other matters, as well as potential changes in regulatory frameworks, including reinterpretation of such regulations, initiatives by federal and state legislatures, regional transmission organizations (e.g., ERCOT and MISO), utility regulators, and taxing authorities, and actions by local jurisdictions regarding such matters. As has occurred in the past, if it were determined that we failed to comply with applicable laws and regulations or with applicable tariff provisions regarding such matters, we could become subject to fines, penalties, refund or disgorgement orders, or disallowed costs, or be required to implement additional compliance or remediation programs, the cost of which could be material. We cannot predict the impact of new laws, rules, regulations, tariffs, principles, or practices by federal or state agencies or regional transmission operators, or challenges or changes to present laws, rules, regulations, tariffs, principles, or practices and the interpretation of any adoption or change. Significant changes in the nature of the regulation of our businesses, including expiration or discontinuation of, or significant changes to, existing regulatory mechanisms, and the current federal administration’s approach to U.S. energy policy and resultant changes in regulatory enforcement priorities, and/or evolving interpretations of existing regulatory requirements, could require changes to our business planning, strategy and management of our businesses and could adversely affect our business, financial condition, results of operations and cash flows.

• acceleration of payments or decreased credit lines

• changes in regulation, governmental policy (including tax and trade policy, such as tariffs) or governmental programs (including tax incentives or tax credits, loans, grants, guarantees and other subsidies); and

Changes in U.S. or foreign trade policies, including the imposition of tariffs and other trade actions, and other factors beyond our control may adversely impact our business, financial condition, results of operations and cash flows.

The U.S. government has taken executive action and proposed additional measures intended to alter the U.S. approach to international trade policy, the terms of certain existing bilateral or multi‐lateral trade agreements and trading arrangements with foreign countries. Such changes to U.S. international trade policy, and retaliatory trade measures that foreign governments have taken and may take in the future in response, including the imposition of tariffs, bans, sanctions, export or import controls, or other measures that restrict international trade, or the threat of such actions, and uncertainties about tariffs and their effects on trading relationships, may affect, and in some cases have affected, the Registrants’ ability to access the capital markets, contribute to inflation in the markets in which the Registrants operate, increase costs and cost volatility, impact availability of goods, materials and services (including those necessary for our business and capital plan), further extend lead times or otherwise negatively impact the global supply chain. While the U.S. government has announced various trade deals, many such agreements are preliminary and may be subject to change. Further, any future disagreement between the U.S. government and other countries over the implementation of trade deals or any failure to obtain required governmental approvals or otherwise reach a final agreement could result in prolonged uncertainty regarding the scope and duration of such trade actions by the U.S. government and other countries. Such announcements, rescissions of tariffs on foreign jurisdictions and other trade actions have increased uncertainty regarding the ultimate effects of the tariffs on …

• shifting governmental policies may impact governmental support for strategic transactions.

Higher electric power demand and load growth could also significantly increase the prices of energy and capacity, which could in turn affect customer rates or be perceived to affect customer rates and raise affordability concerns, as well as raise resource adequacy and reliability concerns, particularly if that increased demand outpaces the addition of firm generation capacity and in transmission constrained zones. For example, there has been increasing media attention and public claims regarding the link between large load customers such as data centers and increased customer bills. Increased customer rates or the perception that customer rates are increasing to address large load customers could attract political and regulatory scrutiny, increase regulatory uncertainty for our capital investment plans and programs and present reputational risks. Additionally, projected load growth across the ERCOT system could, if not sufficiently addressed through system design and reliability measures, negatively impact electric infrastructure reliability and potentially cause system-wide stresses. This resource adequacy challenge presents reliability concerns, as well as potential for increasing energy and capacity prices that could place pressure on customer bills, attract political and regulatory scrutiny, increase regulatory uncertainty for our capital investment plans and programs and present reputational risks. These matters could have an adverse effect on our business, financial condition, results of operations and cash flows.

• the inability to maintain the reliability of our utility services or meet generation capacity obligations;

• regulatory noncompliance, compliance mandates and penalties from our regulators;

No longer in the report

From the report of the year before. A paragraph is listed here when most of its words are nowhere in this year’s risk factors.

Following the February 2021 Winter Storm Event, the Texas legislature passed a law, effective September 1, 2021, that allows TDUs, such as Houston Electric, to lease and temporarily operate back-up generation resources during widespread power outages where ERCOT has ordered a TDU to Load Shed or the TDU’s distribution facilities are not being fully served by the bulk power system under normal operations. In response to this legislation, Houston Electric entered into two leases for large 27 MW to 32 MW TEEEF (temporary generation) and medium five MW TEEEF. In 2023, the Texas legislature amended the law to allow wider use of TEEEF, including in response to a significant power outage affecting a significant number of distribution customers that has lasted or is expected to last for at least six hours, affecting distribution customers in an area for which the governor has issued a disaster or emergency declaration, affecting distribution customers served by a radial transmission or distribution facility that creates a risk to public health or safety and that has lasted or is expected to last for at least 12 hours, or creating a risk to public health or safety because it affects a critical infrastructure facility that serves the public. Pursuant to the amendment, the Texas Division of Emergency Management, ERCOT, or the executive director of the PUCT may also determine that a power outage other than one described above is a significant power outage for purposes of use of TEEEF. In response to this amendment, Houston Electric …

In April 2023, the PUCT approved revenue recovery of $39 million of TEEEF costs incurred in 2021, and in October 2023, an agreement with intervenors was reached with respect to Houston Electric’s second TEEEF filing for revenue recovery of $153 million ($114 million incremental to the prior filing) of TEEEF costs incurred through December 31, 2022, and the agreement was approved by PUCT in February 2024. On September 11, 2024, the TCA filed a complaint with the PUCT requesting that the PUCT modify its rulings with respect to its prior decisions related to the TEEEF filings made in 2022 and 2023. Specifically, TCA requested that the PUCT end cost recovery and return on investment on all the large 32 MW and 5 MW TEEEF units approved in docket 53442. On October 2, 2024, Houston Electric filed a response to the TCA complaint and requested that the complaint be dismissed due to the principles of res judicata and collateral estoppel. On October 8, 2024, TCA supplemented its complaint, and on October 9, 2024, PUCT staff filed a statement of position stating that Houston Electric’s response provided a strong argument for dismissal of the complaint, but also stating that it would be prudent to have a thorough legal argument from TCA. On October 10, 2024, PUCT issued Order No. 2 finding the TCA complaint insufficient and requiring supplemental information or amendment from TCA by October 24, 2024; TCA filed supplemental information on October 24, 2024 and indicated it was prepared to submit …

In July 2024, Hurricane Beryl made landfall in Texas, bringing sustained winds, storm surges and torrential rain, which impacted our operations, customers and personnel in our Texas Gulf Coast markets. Hurricane Beryl caused significant damage to Houston Electric’s electric delivery system, resulting in a substantial number of its customers (peaking at more than 2.1 million customers out of 2.8 million customers) being without power, many for extended periods of time.

The total cost for the restoration of Houston Electric’s electric delivery facilities as a result of Hurricane Beryl is currently estimated to be $1.1 billion, excluding carrying costs, but such estimate is preliminary and restoration costs could vary from that estimate. Houston Electric believes it is entitled to recover prudently incurred storm restoration costs in accordance with applicable regulatory and legal principles. However, neither the amount nor timing of the recovery is certain. Houston Electric’s failure to recover costs incurred as a result of Hurricane Beryl could adversely affect our liquidity, cash flows and financial condition.

Various federal, state and local governmental and regulatory agencies and other entities, such as the Texas Governor’s office, the Texas legislature and the PUCT, have called for or are conducting inquiries and investigations into Hurricane Beryl and the efforts made by Houston Electric to prepare for, and respond to, this event, including, among other things, the electric service outage issues. Moreover, additional governmental and regulatory agencies and other entities may conduct such inquiries and investigations, as well. On August 12, 2024, Texas Attorney General Ken Paxton opened an investigation to evaluate CenterPoint Energy’s conduct during Hurricane Beryl. Certain government officials have also made public statements calling for, and proposed legislation seeking to require, Houston Electric to pay certain costs related to TEEEF. For more information regarding TEEEF-related risks, see “— Houston Electric’s use of TEEEF ...” There are significant uncertainties around these inquiries and investigations and potential results and consequences, including with respect to our recovery of costs incurred as a result of Hurricane Beryl and whether any financial penalties will be assessed or changes to Houston Electric’s system, service territories, operations and/or regulatory treatment will result therefrom. If these or other inquiries, investigations or reviews ultimately result in changes to Houston Electric’s system, service territories, operations and/or regulatory treatment, such changes could have an adverse impact on our business, results of operations, cash flows and financial condition. Further, on January 22, 2025, a putative shareholder of CenterPoint Energy, Donel Davidson, filed a derivative petition in Harris County District Court, …

CenterPoint Energy and Houston Electric are subject to current and potential future litigation and claims arising out of Hurricane Beryl, which litigation and claims could include allegations of, among other things, personal injury, property damage, various economic losses in connection with loss of power, unlawful business practices, and others. As of December 31, 2024, five lawsuits had been filed against CenterPoint Energy and/or Houston Electric in the District Courts of Harris County, including three putative class actions claiming losses due to power outages following Hurricane Beryl. Each class action seeks damages in excess of $100 million for, among other things, business interruption, property damage and loss, cost of repair, loss of use and market value, lost income, nuisance, extreme mental anguish and/or punitive damages. CenterPoint Energy and its subsidiaries have general and excess liability insurance policies that provide coverage for third party bodily injury and property damage claims. Given the nature of some allegations, it is possible that the insurers could dispute coverage for some types of claims or damages that may be alleged by plaintiffs, and CenterPoint Energy has received from two insurers denial of indemnity coverage in the putative class actions based on the failure to supply exclusion. Those insurers have also reserved their rights with respect to coverage in those actions. CenterPoint Energy and Houston Electric intend to continue to pursue all available insurance coverage for all of these matters. While CenterPoint Energy and Houston Electric intend to vigorously defend themselves against the lawsuits, final resolution of …

China is a major producer of solar panels and other solar products. Certain solar cells, modules, laminates and panels from China are subject to various antidumping and countervailing duty rates, depending on the exporter supplying the product, imposed by the U.S. government as a result of determinations the United States was materially injured as a result of such imports being sold at less than fair value and subsidized by the Chinese government. Additionally, in March 2022, the DOC announced it would initiate an investigation into whether imports of solar cells and panels produced in Cambodia, Malaysia, Thailand and Vietnam are circumventing U.S. rules and laws, such as antidumping and countervailing duty rates, which impose a tariff on imports of solar cells and panels manufactured in China. On August 18, 2023, the DOC announced its final determination that five of the eight companies investigated were attempting to bypass U.S. duties by doing minor processing in Southeast Asian countries before shipment to the United States. On May 15, 2024, based on a petition filed by the American Alliance for Solar Manufacturing Trade Committee, the DOC announced the initiation of antidumping and countervailing duty investigations of silicon photovoltaic cells from Cambodia, Malaysia, Thailand, and Vietnam. On October 1, 2024, the DOC’s preliminary countervailing duty determination affirmed the petition and established preliminary duty rates. A final determination is expected in the first quarter of 2025. On November 29, 2024, the DOC announced its preliminary affirmative determination in the antidumping investigation and established preliminary dumping …

In addition, the PUCT and ERCOT continue to review, among other things, the appropriate reliability standard and market design for the Texas electric market. There are uncertainties whether any further changes will result from these discussions or other efforts. If there are changes to how the Texas electric market is structured or regulated, including as a result of Hurricane Beryl and related investigations, such changes could have an adverse impact on Houston Electric’s business, financial condition and results of operations. See Note 7 to the consolidated financial statements for further information.

Climate change and other weather and natural disaster impacts could adversely impact financial results from our businesses and our results of operations.

• compliance mandates that result in penalties from our regulators;

Current and future health pandemics, epidemics and similar public health threats and the measures implemented to contain their spread, such as travel bans and restrictions, quarantines and vaccination mandates, have had and may in the future have widespread impacts on the global economy, our employees, customers, and third-party business partners. The severity, magnitude and duration of future health threats is uncertain and hard to predict. Any future health threat could impact our business in numerous ways, including, but not limited to, those outlined below:

• reduced demand from our commercial and industrial customers and shifts in demand for our services;

• delayed service to customers because of shutdowns or illness and travel restrictions among our employees;

• negative impacts to the financial condition of our customers and REPs and their ability to pay for our services, and our ability to disconnect service for non-payment may be limited, and state regulators may impose bill deferral programs;

• potential limits or significant or entire curtailments of the ability of public utility commissions to approve or authorize applications and other requests we may make with respect to our businesses, including delaying rate making proceedings;

• increased risk to our cybersecurity program as a result of an increase in cyberattacks during the pandemic and increased remote working arrangements (for further information, see “— Risk Factors Affecting Safety and Security Risks”);

• increased rates of inflation and delays in our supply chain and our ability to complete maintenance, repairs, and capital programs, which could result in disruption, increased costs and our inability to execute on or require us to make modifications to our capital plan; and

• accelerated employee turnover as a result of concerns regarding restrictions and guidelines, including mask mandates and quarantine mandates, and increased acceptability of alternative work arrangements.

Our success depends upon our ability to attract, effectively transition, motivate and retain key employees and identify and develop talent to succeed senior management.

We depend on senior executive officers and other key personnel. Our success depends on our ability to attract, effectively transition and retain key personnel. Further tightening of the labor market and increasing wages to attract and retain key personnel may adversely affect our ability to attract and retain key personnel. The inability to recruit and retain or effectively transition key personnel or the unexpected loss of key personnel may adversely affect our operations. In addition, because of the reliance on our management team, our future success depends in part on our ability to identify, motivate and develop talent to succeed senior management. The retention of key personnel and appropriate senior management succession planning will continue to be critically important to the successful implementation of our strategies.

Reworded

Each paragraph as it reads now, with the words that are new this year marked and the words that were taken out struck through. A long stretch that did not change is left out (…).

Electric Transmission, Distribution and Generation Transmission and Distribution (CenterPoint Energy and Houston Electric)

Disruptions at third-party or Indiana Electric’s power generation facilities, generation inadequacy, or directives issued by regulatory authorities or other matters could cause interruptions in Houston Electric’s and Indiana Electric’s ability to provide transmission and distribution services and Houston Electric and Indiana Electric may not be able to promptly respond, repair and restart their facilities, which could adversely affect their reputation, businesses, financial condition, results of operations and cash flows.

Houston Electric owns the transmission and distribution infrastructure in its service territory that delivers electric power to its customers, but it does not own or operate any bulk power generation facilities. except for its operation of TEEEF. Indiana Electric owns and operates power generation facilities in addition to the transmission and distribution infrastructure in its service territory. Both Houston Electric and Indiana Electric must follow the directives issued by their respective independent system operator, ERCOT and MISO, respectively. ERCOT and MISO have in the past and may in the future issue directives requiring members to implement controlled outages as a result of an emergency or reliability issues. and Houston Electric has faced and may in the future face challenges to its planning and preparation for such directives and its implementation of Load Shed, including, for example, allegations that it had discretion as to how to Load Shed load and which customers experienced outages and the duration of those outages. As a result, claims and lawsuits could be filed against Houston Electric and Indiana Electric CenterPoint Energy for personal injury, property damage or other damage or loss as a result of their respective its Load Shed planning, preparation, implementation, and decisions in order to meet the directives of ERCOT and MISO, respectively. For example, in during the February 2021 Winter Storm Event, the ERCOT regulated Texas electric system experienced extreme winter weather conditions and an unprecedented power generation shortage as the amount of electricity generated by the state’s power generation companies was insufficient to meet the amount demanded by customers. … significantly Load Shed, which caused customer outages across the ERCOT electric grid of Texas, including in Houston Electric’s service territory. CenterPoint Energy received various claims and lawsuits with respect to the February 2021 Winter Storm Event, alleging, among other things, wrongful death, personal injury, property damage and other injuries and damages. See Note 7 to the consolidated financial statements and “— Houston Electric’s use of TEEEF ...” for further information. If power generation capacity is severely disrupted or is inadequate for any reason in the future or in the event of significant system disturbances, Houston Electric’s or Indiana Electric’s transmission and distribution services may be diminished, interrupted or interrupted. halted, which could lead to prolonged customer outages, and Houston Electric and Indiana Electric may not be able to promptly repair and restart their facilities, which could adversely affect our businesses, financial condition, results of operations and cash flows. Further, as with the lawsuits filed in the aftermath of the February 2021 Winter Storm Event, claims and lawsuits could be filed against the Registrants, and which could also adversely affect our reputation, business, financial condition, and results of operations. and cash flows could be adversely affected.

Additionally, Indiana Electric’s generating facilities are subject to operational risks, and Houston Electric and Indiana Electric are subject to risk relating to the generating facilities that supply the power transmitted by Houston Electric and Indiana Electric; are subject to operational these risks that have in the past and may in the future result in service interruptions and unscheduled plant outages, unanticipated operation and maintenance expenses, reputational harm and increased purchase power costs. For example, in June 2022, F.B. Culley Unit 3, a coal-fired generation unit, experienced a boiler feed pump turbine failure that caused the unit to be out of … market. Such open market purchases have and may again result in increased costs and have an adverse impact on our operations, business, financial condition, results of operations and cash flows. Further, Indiana Electric is party to a number of PPAs with third parties. Indiana Electric’s power generation operations may be disrupted or otherwise insufficient if third parties do not deliver required power under our PPAs. These operational risks can arise from circumstances such as facility shutdowns or malfunctions due to equipment failure or operator or other human error; aging infrastructure; interruption of fuel supply or increased prices of fuel as a result of, among other things, contract expirations, inflation and/or tariffs; disruptions in the production or delivery of electricity; inability to comply with regulatory or permit requirements; governmental action; labor disputes; or severe weather; natural disasters; or cyberattacks, all of which could adversely affect Indiana Electric’s and Houston Electric’s businesses, including their financial condition, results of operations and cash flows. Further, Indiana Electric currently relies on coal for a portion of its generation capacity. Indiana Electric purchases the majority of its coal supply, and in 2025 purchased all of its coal supply, from a single, unrelated party and, although the coal supply is under long-term contract, the loss … supplier or transportation interruptions could adversely affect its ability to deliver electricity to its customers and adversely impact Indiana Electric’s business, financial condition, results of operations and cash flows. Future labor shortages in the coal industry as well as coal supply shortages (such as those experienced by Indiana Electric in 2021 and part of 2022), Indiana Electric experienced coal supply shortages due to labor shortages that the coal industry experienced. While the coal supply shortage that Indiana Electric experienced did not impact its ability to deliver electricity to its customers, labor shortages as well as supply shortages in the future, whether caused by insufficient supply or supplier bankruptcy or other regulatory and supply issues in the mining industry, may lead to increased cost and have an adverse impact on our operations, business, financial condition, results of operations and cash flows. See “— Disruptions to the global supply...” Further, as Indiana Electric continues its generation transition and more renewable energy sources come online, Indiana Electric’s generating facilities may experience unanticipated disruptions as a result of renewable supply shortages, including, but not limited to, adverse weather unfavorable wind and solar conditions such as cloudy or windless days, Additionally, and such disruptions could adversely affect its ability to deliver electricity to its customers and adversely impact Indiana Electric’s business, financial condition, results of operations and cash flows.

The operations of Houston Electric and Indiana Electric are subject to the usual hazards associated with high-voltage electricity transmission and distribution, including inclement or severe weather, natural disasters, including wildfires, mechanical failure, contact with electrified facilities by people, equipment, and debris, unscheduled downtime, equipment interruptions, loss or outage of key technology platforms or systems, contamination, remediation, explosions, fires, chemical spills, discharges or releases of toxic or hazardous substances and other environmental risks. Such hazards … severe damage to or destruction of property and equipment, including loss of transmission and distribution lines and related equipment and damage to solar panels, and environmental damage, and may result in suspension of operations, disruption of service to customers, prolonged outages and the imposition of civil or criminal penalties. For example, in 2024, Hurricane Beryl caused significant damage to Houston Electric’s electric delivery system resulting and resulted in a substantial number of its customers (peaking at more than 2.1 million customers out of 2.8 million customers being without power, many for extended periods of time. Although CenterPoint Energy currently maintains property and casualty insurance, this insurance is limited in scope and subject to exceptions, conditions and coverage limitations and may not cover the costs associated with potential hazards incident to Houston Electric and Indiana Electric maintain property Electric’s businesses, and casualty there is no guarantee that the insurance but that CenterPoint Energy currently maintains will continue to be available at rates we believe are not fully insured against all potential hazards incident to their businesses. reasonable.

Indiana Electric’s execution of its generation transition plan including its IRP, is subject to various risks, including timely recovery of capital investments and increased costs and risks related to the timing and cost of development and/or construction of new generation facilities.

Indiana requires each electric utility to perform develop and submit an IRP to the IURC every three years, unless extended, that uses economic modeling to consider the costs and risks associated with available resource options to provide reliable, cost effective electric service for the next 20-year period. Indiana Electric has used past IRPs and will continue to use future IRPs … Indiana Electric engages with the communities it serves, its regulators and third-parties in developing its generation transition plan. Recent IRPs, including the 2025 IRP, have demonstrated Indiana Electric can most cost effectively serve its customers by transitioning its generation fleet to identified preferred portfolios that include a wider mix of generating resources including renewables. For example, Indiana Electric’s 2019/2020 IRP identified a preferred portfolio that retires 730 MW of such as coal-fired generation, facilities and replaces these resources with a mix of generating resources composed primarily of renewables, including solar, wind, and solar with storage supported by and dispatchable natural gas combustion turbines. including a pipeline to serve such natural gas generation. Indiana Electric is continuing its plan to transition generation resources away from coal-fired generation to a more sustainable portfolio of resources, including renewables. While the IURC does not approve or reject Indiana Electric’s IRP, the IURC does comment on the IRP. Indiana Electric … to obtain a CPCN prior to constructing or acquiring generating resources. Indiana Electric also obtains IURC approval of PPAs and DSM demand-side management plans to help ensure support cost recovery.

… transition. If Indiana Electric fails to receive IURC approvals necessary to acquire the projects or resources identified in its IRP or if other governmental action is taken with respect to Indiana Electric’s generation resources or generation transition plan, Indiana Electric may not be able to implement its generation transition plan in a timely manner or at all. For example, while Indiana Electric’s 2025 IRP (similar to previous IRPs) preferred portfolios included the retirement of F.B. Culley Unit 2, a coal-fired generation unit, by the end of 2025, the U.S. Department of Energy issued emergency order 202(c) in December 2025 directing Indiana Electric to continue operating the unit through March 23, 2026. Additionally, projected changes in how renewable and battery storage resources are accredited to meet MISO’s planning reserve margin requirement make have made it less economic to pursue these resources. in the future. In connection with its IRPs, Indiana Electric’s determinations with respect to the appropriate mix of generation resources may change from plans that were previously announced. For example, while Indiana Electric’s 2022/2023 IRP recommended the conversion of F.B. Culley Unit 3 from coal to natural gas by 2027, the 2025 IRP re-evaluated this conversion in light of customer affordability concerns, among other things, and deferred the decision regarding F.B. Culley Unit 3’s replacement to a future IRP. If Indiana Electric is unable to implement its generation transition plan, it may have an adverse effect on CenterPoint Energy’s ability to execute on its net zero and GHG emissions reduction energy transition goals, its goal to exit the coal plants that Indiana Electric operates, execute on its growth strategy, achieve its financial goals, and otherwise impact its business, financial condition, results of operations and cash flows.

Even if a generation project is approved, risks associated with the development or construction of any new generation exist, including new legislation or governmental action restricting or delaying new generation, moratorium legislation, changes to trade practices (including tariffs, bans, retaliatory trade measures taken against the United States or related governmental action), changes to business practice manuals of MISO or corresponding impacts such as interconnection delays (which may be exacerbated by significant new load additions), the ability to procure resources needed to build at a reasonable cost, scarcity of resources and labor, the ability to appropriately estimate costs of new generation, the effects of potential construction delays, project scope changes, and cost overruns, cost of and the ability to meet capacity requirements and related customer affordability considerations. For example, due to shifting market dynamics, changing project considerations such as substantial delays in January 2025, President Trump signed executive orders that, among other things, temporarily halted certain federal government agencies from issuing approvals, permits commercial operation dates (due in part to MISO interconnection delays), cost increases and loans for onshore wind projects pending the completion of certain assessments and reviews, and pause the disbursement of funds appropriated through the IRA and the Infrastructure Investments and Jobs Act. As an additional example, the developers of a 130 MW Pike County Solar project informed concerns about customer affordability, Indiana Electric that, due to delays terminated several wind and solar projects in the MISO interconnection queue and inflationary pressures, costs exceeded the agreed upon levels in the BTA. After negotiations, Indiana Electric and the developer were not able to agree upon updated pricing. As a result, on March 15, 2024, Indiana Electric provided notice to the IURC that it was exercising its right to terminate the BTA. Further, tariffs, as well as any new legislation, tariffs, bans, potential retaliatory trade measures taken against the United States or related governmental action, could adversely affect our ability to develop and construct new generation, including our ability to procure the resources needed for such development and construction. For example, on February 6, 2025. the EPC contractor for Indiana Electric’s proposed natural gas combustion turbines provided a notice to Indiana Electric that the EPC contractor was identifying the impacts of the proposed tariffs on the project and intended to seek an equitable adjustment to the contract price for the project. For additional information, see “— Disruptions to the global supply...” Furthermore, we have begun to acquire and/or develop additional solar and wind facilities as part of our capital plan. However, we have not yet entered into definitive agreements with developers for the acquisition and/or development of all of the additional projects, and we face significant competition with other bidders for a limited number of such generation facilities that developers plan to construct and for solar panels. For additional information, see “— Increases in the cost or reduction in supply ...” The number of available projects is further limited by the MISO interconnection queue due to potential interconnection costs that may render projects infeasible. As a result, suitable generation facility project candidates or resources necessary to construct such projects may not be available on terms and conditions we find acceptable, or the expected benefits of a completed facility may not be realized fully or at all, or may not be realized in the anticipated timeframe. If Indiana Electric was is unable to meet its generation needs as a result through development or acquisition of project delays or cancellations, new generation, it would be required to buy the necessary capacity and electricity on the open market. Such open market purchases may result in increased costs and may have an adverse impact on our operations, business, financial condition, results of operations and cash flows. If we are unable to complete or acquire such generation facilities or resources, or if they do not perform as anticipated, our future growth, business, financial condition, results of operations and cash flows may be adversely affected.

Houston Electric’s receivables from the distribution of electricity are collected from REPs that supply the electricity. As of December 31, 2024, 2025, Houston Electric provided electric delivery service to approximately 67 REPs. Adverse conditions, including, but not limited to, the February 2021 … extreme weather (which may result in abnormal power prices), structural problems in the market served by ERCOT, the impact of pandemic public health events or similar occurrences, mismanagement by the REPs, inflation or financial difficulties of one or more REPs, have and … from affiliates of NRG and Vistra Energy Corp. Houston Electric’s aggregate billed receivables balance from REPs as of December 31, 2024 2025 was $263 $279 million. Approximately 37% and 21% 23% of this amount was owed by affiliates of NRG and Vistra Energy Corp., respectively. Any delay or default in payment by REPs could adversely affect Houston Electric’s business, financial condition, results of operations and cash flows. If a REP was unable to meet its obligations, it could consider, … Electric had received from such REP. For example, following the February 2021 Winter Storm Event, multiple REPs filed for bankruptcy. We are currently recording the amounts owed by these REPs as a regulatory asset for bad debt expenses, which is subject to a reasonableness review by the PUCT in our current base rate case. As of December 31, 2025 and 2024, and 2023, as authorized by the PUCT, CenterPoint Energy and Houston Electric recorded had a regulatory asset of $7 million and $8 million, respectively for bad debt expenses resulting from REPs’ defaults on their obligations to pay delivery charges to Houston Electric, net of collateral There is no guarantee that we will be able to recover any or all of the regulatory asset and recovery in our next base rate case. rates. See “— Rate regulation of the Registrants’ electric ...” For further information on certain of Houston Electric’s ongoing regulatory proceedings, see “Management’s Discussion and Analysis of …

Houston Electric’s use of TEEEF is subject to various risks, including failure to obtain and deploy sufficient TEEEF resources, potential performance issues and allegations about Houston Electric’s procurement and deployment of the resources (including the planning, execution and effectiveness of the same), regulatory and environmental requirements, and timely recovery of capital.

If Houston Electric is unable to deploy a sufficient number of TEEEF resources in time to respond to a particular event (including as a result of releasing TEEEF to third parties or similar transactions as described further below, or if leasing certain TEEEF becomes prohibited by law, as further described below); if TEEEF resources fail to perform, or are perceived to fail to perform, as intended; if Houston Electric is otherwise unable, or perceived as unable, to provide back-up generation resources and restore power (such as intended; in the event of ERCOT issuing a directive requiring TDUs to Load Shed); or if the use of TEEEF resources or their failure to perform causes or is alleged to cause any personal … to particular power outages, Houston Electric could be subject to claims, demands, litigation, liability, regulatory scrutiny, and loss of reputation and new legislation could be passed making it no longer viable for Houston Electric to lease TEEEF at the same or similar scale that it currently leases such resources or at all. For example, following Hurricane Beryl, various federal, state and local governmental and regulatory agencies and other entities such as the Texas Governor’s office, the Texas legislature and the PUCT, have called for or are conducting conducted inquiries and investigations into Hurricane Beryl and the efforts made by Houston Electric to prepare for, and respond to, this event, including, among other things, Houston Electric’s procurement of TEEEF, Texas Lieutenant Governor Patrick has publicly urged the PUCT to hold and certain government officials argued that Houston Electric, rather than ratepayers, should be held responsible for paying approximately $800 million which, as detailed below, was (the amount the PUCT had previously approved Houston Electric to recover from ratepayers relating to Houston Electric’s leasing of TEEEF). Additionally, legislation has been proposed in Texas to, among other things, require the PUCT to review TEEEF leased by TDUs, disallow any leases that do not conform to the terms of the proposed legislation (which include, among other things, requirements relating to the speed with which TEEEF may be deployed), disallow recovery of costs associated with such disallowed leases, Ongoing and implement a process to refund ratepayers the charges paid for the leasing of certain TEEEF. On August 12, 2024, Texas Attorney General Ken Paxton opened an investigation to evaluate CenterPoint Energy’s conduct during Hurricane Beryl, including with respect to its TEEEF resources. There are significant uncertainties around these future inquiries, investigations and proposed legislation regarding Houston Electric’s TEEEF could adversely affect our business, financial condition, results of operations and potential results and consequences, cash flows, including with respect to our recovery of costs incurred as a result of Hurricane Beryl and whether any or future severe weather events; the assessment of financial penalties; will be assessed; whether changes to Houston Electric’s system, service territories, operations and/or regulatory treatment; will result therefrom; or whether it will be viable and the viability for Houston Electric to continue leasing TEEEF. If it is no longer viable for Houston Electric to lease TEEEF at the same or similar scale at which it currently leases such resources and ERCOT issues a directive requiring TDUs to Load Shed or other conditions occur that could be, or are perceived to have the potential to be, addressed by Houston Electric’s deployment of TEEEF, Houston Electric could be subject to claims, demands, litigation, liability, regulatory scrutiny and loss of reputation. Additionally, while Houston Electric has insurance coverage and indemnity rights for its use of TEEEF resources, if its insurers or indemnitors fail to meet their indemnity obligations, Houston Electric could be liable for personal injury, property damage, or other damage or loss. For further information, see “— Hurricane Beryl caused severe disruptions...,” “— We are involved in numerous legal proceedings...” and “— Our insurance coverage may not...”

On December 19, 2024, In June 2025, Houston Electric announced a proposal entered into the ERCOT Transaction, subject to PUCT approval, to release Houston Electric’s 15 its large 27 MW to 32 MW TEEEF units to the San Antonio area prior ERCOT at CPS Energy facilities to the summer of 2025. The proposal is intended to help ERCOT address a potential energy shortfall and Load Shed risk and to provide additional electric generation capacity to support growing energy demand in serve the greater San Antonio region Under until March 2027 unless terminated earlier pursuant to the proposal, Houston Electric would not receive revenue or profit from provisions of the ERCOT Transaction, reduce its TEEEF fleet capacity and would also not charge Houston-area customers for these reduce its rates to reflect the removal of the large TEEEF units for from its fleet. Following the period they are completion of service in the San Antonio serving ERCOT, which is currently expected to be for a period of up to two years. area, Houston Electric anticipates receiving revenues from that it would complete one or more future transactions after involving its large TEEEF units; because the period the TEEEF units are released would not be available to temporarily serve the energy need in the San Antonio area, and would therefore plan customers during such time, Houston Electric plans to continue to not charge customers for these units for any future periods. As of the date of the filing of this Form 10-K, Further, in November 2025, Houston Electric estimates that the value of the proposed to release its medium TEEEF units to be removed from its TEEEF fleet and remove the rate base as a result of the aforementioned proposal will be approximately $375 million. The proposal has not been finalized and is subject to the negotiation of definitive documentation among the relevant parties, as well as being subject to the approval of ERCOT and other stakeholders. It is not certain that mutually agreeable definitive documentation will be entered into at all or that all approvals will be obtained. Assuming that a definitive agreement is executed and that all necessary transaction approvals are received, this proposal is expected to result in a reduction to Houston Electric’s customers’ bills that associated lease costs from its rates. Houston Electric would propose to the PUCT in the spring of 2025. Nevertheless, also anticipates entering into and receiving revenue from future transactions involving its medium TEEEF units. There can be no assurance that the PUCT will approve the ERCOT Transaction and Houston Electric will be able Electric’s proposal to finalize the proposal. release its medium TEEEF units. If the ERCOT Transaction and/or Houston Electric’s proposal is to release its medium TEEEF units are not finalized, approved, it may have an adverse effect on our reputation business, financial condition, results of operations and customer satisfaction, cash flows, as well as potentially lead to negative consequences from regulatory authorities or other public authorities. Additionally, Suitable future transactions may not be available on terms and conditions we find acceptable, or the expected benefits of Houston Electric’s proposal to release of its 15 large 27 MW to 32 MW and medium TEEEF units to San Antonio or any completed future transactions may not be realized fully or at all, or may not be realized in the anticipated timeframe, which could adversely impact our business, reputation, financial condition, results of operations and cash flows. Finally, if such transactions are successful and thereby result in Houston Electric having fewer TEEEF units to deploy in its own service territory, and if ERCOT issues a directive requiring TDUs to Load Shed or other conditions occur that could be or are perceived to have the potential to be addressed by Houston Electric’s deployment of TEEEF, Houston Electric could be subject to claims, demands, litigation, liability, regulatory scrutiny and loss of reputation. Increases in the cost or reduction in supply of solar energy system components due to tariffs or trade restrictions imposed by the U.S. government may have an adverse effect on our business, financial condition and results of operations.

As noted above, Despite the legislation allowing TDUs recovery of certain TEEEF costs in the past, there can be no assurance that Houston Electric will seek to lease or be able to recover certain future TEEEF costs or be able to retain those costs previously approved for recovery. For example, in 2024, the TCA filed a complaint with the PUCT requesting that it end the cost recovery and operate TEEEF prescribes specific and limited use for TEEEF, and return on investment on Houston Electric’s large and medium TEEEF have limited generation capacity, such that in future events customers could still units as previously approved, and these proceedings remain ongoing. See Note 7 to the consolidated financial statements for further information. If Houston Electric is unable to recover or must return any or certain of its TEEEF costs, our business, financial condition, results of operations and cash flows may be without power despite deployment adversely affected. Additionally, while Houston Electric has insurance coverage and indemnity rights for its use of TEEEF resources, if its insurers or indemnitors fail to meet their indemnity obligations, Houston Electric could be liable for personal injury, property damage, or other damage or loss. Further, TEEEF resources are subject to various environmental regulations and permitting requirements, which could have an impact on Houston Electric’s … with them could subject Houston Electric to additional liability as well as challenges to its use of TEEEF in general. Despite the recovery of certain TEEEF costs in the past, there can be no assurance that Houston Electric will seek to or be able to recover certain future TEEEF costs or be able to retain those costs previously approved for recovery. For example, on August 28, 2024, Houston Electric announced its proposal to forego approximately $110 million of profit related to its storm hardening and TEEEF efforts, which would be represented in part by Houston Electric not filing, beginning in 2028, for approximately $40 million in anticipated equity profit associated with Load Shed orientated TEEEF leased by Houston Electric through the remaining regulatory life of the leases in 2032 as new dispatchable generation is likely to come online in the state of Texas as a result of the Texas Energy Fund. Additionally, as noted above, legislation has been proposed in Texas to disallow recovery of costs associated with such disallowed leases and implement a process to refund ratepayers the charges paid for the leasing of certain TEEEF. If Houston Electric is unable to recover or must return any or certain of its TEEEF costs our financial condition, results of operations and cash flows may be adversely affected. For further information, see “— Rate regulation of Registrants’ Electric...”, “— Our insurance coverage may not...” and “— We are subject to operational...”

Access to natural gas supplies and pipeline transmission and storage capacity are essential components of reliable service for our natural gas business customers.

Natural Gas depends We depend on third-party service providers to maintain an adequate supply of natural gas and for available storage and intrastate and interstate pipeline capacity to satisfy its our customers’ needs, all of which are critical to system reliability. Substantially all of Natural Gas’ our natural gas supply is purchased on intrastate and interstate pipelines. If Natural Gas is we are unable to secure an independent natural gas supply of its our own or if third-party service providers fail to timely deliver natural gas to meet Natural Gas’ our requirements, the resulting decrease in natural gas supply in Natural Gas’ our service territories could have an adverse effect on its our business, financial condition, results of operations and cash flows. and reputation. Additionally, a significant disruption, whether through reduced intrastate and interstate pipeline transmission or storage deliveries or other events affecting natural … winter weather conditions, wildfires, acts of terrorism, human error or cyberattacks or changes in legislative or regulatory requirements, could also adversely affect Natural Gas’ have a negative impact on our businesses, financial condition, results of operations and cash flows. Further, to the extent that Natural Gas’ our natural gas requirements cannot be met through access to or continued use of existing natural gas infrastructure or if additional … facilities, gathering and processing systems and pipeline and storage capacity is not constructed at a rate that satisfies demand, then Natural Gas’ our operations could be negatively affected.

Natural Gas is We are subject to fluctuations in natural gas prices, which could affect the ability of its our suppliers and customers to meet their obligations or may impact its our operations, which could adversely affect CERC’s our business, financial condition, results of operations and cash flows.

Natural Gas is We are subject to risk associated with changes in the price of natural gas. The regional and other markets in which we purchase natural gas are competitive and can be subject to significant pricing volatility as a result of many factors, including inflation, adverse weather conditions, supply and demand changes, availability of competitively priced alternative energy sources, political and geopolitical instability, commodity production levels and storage capacity, energy and environmental legislation and regulations and economic and financial market conditions. The natural gas market has been, and may continue to be, volatile due to growing domestic demand, increased natural gas exports, weather and other factors. Significant increases in natural gas prices, such as those experienced during the February 2021 Winter Storm Event, might affect Natural Gas’ our ability to collect balances due from customers and could create the potential for uncollectible accounts expense to exceed the recoverable … a sustained period of high natural gas prices could (i) decrease demand for natural gas in the areas in which Natural Gas operates, we operate, thereby resulting in decreased sales and revenues and (ii) increase the risk that Natural Gas’ our suppliers or customers fail or are unable to meet their obligations. An increase in natural gas prices would also increase working capital requirements by increasing the investment that must be made to maintain natural gas inventory levels.

Our natural gas businesses must compete with alternate energy sources, which could result in less natural gas delivered and have an adverse impact on CenterPoint Energy’s and CERC’s our business, financial condition, results of operations and cash flows.

Our natural gas competes businesses compete primarily with alternate energy sources such as electricity and other fuel sources. In some areas, intrastate pipelines, other natural gas distributors and natural gas marketers also compete directly with Natural Gas us for natural gas sales to end users. In addition, as a result of federal regulatory changes affecting interstate pipelines, natural gas marketers operating on these pipelines may be able to bypass Natural Gas’ our facilities and market, sell and/or transport natural gas directly to commercial and industrial customers. Any reduction in the amount of natural gas delivered by Natural Gas us as a result of competition with alternate energy sources may have an adverse impact on CenterPoint Energy and CERC’s our business, financial condition, results of operations and cash flows.

Rate regulation of the Registrants’ electric and natural gas businesses may delay or deny their ability to earn an expected return and fully and timely recover their costs.

… third-party intervention and appeal, and the timing of a general base rate proceeding may be out of the Registrants’ control. Houston Electric and CERC, with respect to its Ohio gas territory, each filed rate cases during 2024. The Registrants can make no assurance that their or their subsidiaries respective base rate proceedings will result in requested or … return for utilities or below recently approved return levels for other utilities in their respective jurisdictions. For instance, in the 2019 2024 Houston Electric general rate case, Houston Electric filed a base rate case seeking approval for revenue increases of approximately $194 $60 million and a 10.4% ROE, but after entering into a Stipulation and pursuant to the final settlement agreement filed with the PUCT, Houston Electric received an overall revenue requirement increase decrease of approximately $13 $47 million to current revenues and a 9.4% 9.65% ROE relative to the initial filing. To the extent the regulatory process does not allow the Registrants to make a full and timely recovery of appropriate costs, their businesses, financial condition, results of operations and cash flows could be adversely affected. Further, the Registrants or their subsidiaries might be … rate case proceeding. Such additional measures may adversely impact the Registrants’ businesses and could have an adverse effect on their businesses, financial condition, results of operations and cash flows.

… and may be exaggerated in the future under certain circumstances, such as increased capital investments that are recovered in arrears. like those experienced in 2022, 2023 and early 2024. For example, the MPUC ordered extraordinary gas costs incurred in the February 2021 Winter Storm Event be recovered over a … the Registrants and their subsidiaries to reduce the effects of regulatory lag (for example, CSIA, DCRF, DRR, DSMA, GRIP, RCRA, RRA, RSP, TCOS and TDSIC), such adjustment mechanisms are subject to the applicable regulatory body’s approval, which we cannot assure would be … and are subject to certain limitations that may reduce or otherwise impede the Registrants’ or their subsidiaries ability to adjust its their rates or result in rates below those requested. Therefore, the Registrants can make no assurance filings for such mechanisms will … adjustments to rates or in full cost recovery. Further, from time to time, the Registrants’ regulators approve the issuance of system restoration bonds or securitization bonds in order to recover facilitate the recovery of certain qualified costs, including costs incurred as a result of severe weather or to recover stranded asset costs. For example, Houston Electric is currently seeking to recover system restoration costs associated with Hurricane Beryl and certain other significant storms through the issuance and sale of non-recourse system restoration bonds. The issuance of these system restoration bonds or securitization bonds may be delayed due to regulatory or other actions outside of our control. If the issuance of system restoration bonds or securitization bonds is delayed, we may not be able to recover our costs in a timely manner, which could have an adverse effect on CenterPoint Energy’s, CERC’s, and Houston Electric’s businesses, financial condition, results of operations and cash flows.

Inherent in the regulatory process is some level of risk that jurisdictional regulatory authorities may challenge the reasonableness or prudency of operating expenses incurred or capital investments made by the Registrants or their subsidiaries and deny the full recovery of their cost of service in rates. For example, concerns about customer affordability could cause regulators to approve lesser amounts in ratemaking or cost recovery proceedings. From time to time, these reviews and investigations have caused in certain instances, and in the future could cause, the Registrants to recover their costs … adjustment mechanisms, the regulatory process by which rates are determined is subject to change as a result of legislative processes, rulemakings or rulemakings, litigation, as the case may be, and may not always be available or result in rates that will produce recovery of the Registrants’ or their subsidiaries’ costs or enable them to earn their authorized return. For example, New legislation has been proposed could be adopted in Texas to require the PUCT to review TEEEF leased by TDUs, disallow any leases that do not conform to the terms of the proposed legislation states in which include, among other things, requirements relating to we operate that could alter the speed with which TEEEF may be deployed), disallow regulatory framework and prevent us from getting timely recovery of our costs associated with such disallowed leases, and implement a process to refund ratepayers the charges paid for the leasing of certain TEEEF. There can be no assurances that Houston Electric will seek to or be able to recover certain future TEEEF costs or be able to retain those costs previously approved for recovery. For more information regarding TEEEF-related risks, see “— Houston Electric’s use of TEEEF ...” investments. Additionally, changes to the rate case or interim adjustment mechanisms (including the termination of such mechanisms) could result in an increase in regulatory lag or otherwise impact the Registrants’ ability to recover their costs in a timely manner. Additionally, Decisions from regulators are typically subject to appeal, and any such appeal could further exacerbate regulatory lag and lead to … associated with rate case proceedings. The regulatory process may also be adversely affected by the political, regulatory and economic environment and customer affordability concerns in the states in which we operate. We are also affected by the actions of numerous advocacy groups, and success by any such groups in directly or indirectly influencing legislators and regulators could have a material adverse effect on our business, financial condition, results of operations and cash flows. To the extent the regulatory process does not allow the Registrants to make a full and timely recovery of appropriate costs, their businesses, financial condition, results of operations and cash flows could be adversely affected. For further information on rate case proceedings and …

The regulated utility businesses, and the energy industry as a whole, have experienced a period of rising costs and investments and an upward trend in spending, especially with respect to infrastructure investments (including those that have already been approved by a regulator). For example, Houston Electric’s SRP, which was approved by the PUCT in November 2025, includes twenty-seven resiliency measures totaling approximately $2.68 billion in capital investments and an estimated $185 million in operations and maintenance expense. Rising costs and investments and the upward trend in spending is likely to continue in the foreseeable future and could result in more frequent rate cases and requests for, and the continuation of, cost recovery mechanisms, all of which could result in adverse cost recovery determinations and/or face resistance from customers and other stakeholders, especially in a rising cost environment, whether due to inflation, customer affordability concerns, tariffs or changes to governmental policies and programs, high fuel prices or otherwise, and/or in periods of economic decline or hardship. Significant increases in costs could increase financing needs and otherwise adversely affect our business, financial position, condition, results of operation or operations and cash flows.

Houston Electric, Indiana Electric and CERC own, develop, construct, manage and operate electric transmission, distribution and generation transmission and distribution facilities or natural gas distribution facilities, as applicable. A key component of our growth is our ability to construct and … and enforcement actions with regards to certain of our projects, which have caused delays to our projects in the past. Our projects, such as in the case of Houston Electric’s proposed 765 kV and other transmission projects, have faced and may in the future face opposition from individuals, community organizations, environmental and other activist groups, and other public-interest entities. In the future, these approvals may not be granted in a timely manner (including due to potential staffing issues at U.S. regulatory agencies) or at all or may be modified, rescinded or fail to be extended for a variety of reasons, including due to legal or regulatory changes or political, public and community relations pressure. Should we in the future be unsuccessful in obtaining necessary licenses or permits on acceptable terms or resolving third-party challenges … enforcement actions or impose related penalties or disallowances, our future net income and cash flows could be reduced and our business, financial condition and results of operations could be impacted. Any failure to negotiate successful project development agreements for new facilities with third parties could also have adverse effects. Additionally, our projects have faced and may in the future face opposition from individuals, community organizations, environmental and other activist groups, and other public-interest entities.

Customers’, investors’, legislators’, regulators’, creditors’, rating agencies’ and creditors’ other stakeholders’ opinions of us are affected by many factors, including actual or perceived system reliability and safety, the speed of our response to service interruptions, rates and customer affordability, our ability to successfully execute our capital plan, media coverage and actions by third parties, and negative opinions developed by such stakeholders could harm our reputation and have an adverse impact on our business, financial condition, results of operations and cash flows. and financial condition.

Our results are influenced by the expectations of our customers, investors, legislators, regulators, creditors, rating agencies and creditors. other stakeholders. Those expectations are based, in part, on the actual or perceived reliability, safety and affordability of our utility services. The speed with which we are able Our actual or perceived ability to prevent, mitigate, prepare for and timely respond effectively to electric outages, natural gas leaks or events and related accidents and similar interruptions caused by severe weather, physical or … as well as our own or third parties’ actions or failure to act, can affect customer, regulator and legislator satisfaction or potentially subject us to regulatory action and litigation. For example, CenterPoint Energy, CenterPoint Energy Service Company, LLC and Houston Electric are subject to litigation and claims arising out of Hurricane Beryl and various federal, state and local governmental and regulatory agencies and other entities have called for or are conducting conducted inquiries and investigations into Hurricane Beryl and the efforts made by Houston Electric to prepare for, and respond to, this event, including the associated electric service outage issues. CenterPoint Energy Ongoing and Houston Electric are also subject future inquiries, investigations and proposed legislation regarding Hurricane Beryl could adversely affect our business, financial condition, results of operations and cash flows, including with respect to current and potential future litigation and claims arising out our recovery of costs incurred as a result of Hurricane Beryl or future severe weather events; the assessment of financial penalties; changes to Houston Electric’s system, service territories, operations and/or regulatory treatment; and the viability for more information regarding Hurricane Beryl-related risks, see “— Hurricane Beryl caused severe disruptions...” Houston Electric to continue leasing TEEEF. The level of rates and actual or perceived affordability of our services, the timing and magnitude of rate increases, and the volatility of rates can also affect customer satisfaction. the opinions of customers, legislators, regulators and other political figures of us. For example, in 2025, the Governor of Indiana directed the commissioner of the OUCC to evaluate utilities’ profits and find cost-saving measures to ease the financial burden on customers. Our ability to successfully execute our capital plan may also affect customers’, investors’, legislators’, regulators’, creditors’, rating agencies’ and creditors’ other stakeholders’ opinions and actions. Opinions of us can also additionally be affected by media coverage, including social media, which may include information, whether factual or not, that damages our brand and reputation. Our efforts to secure permits and/or acquire land and easements (including through eminent domain) for infrastructure investments, including with respect to Houston Electric’s proposed 765 kV and other transmission projects, as well as execute on and/or obtain regulatory approvals for transmission, generation and other facilities can also affect opinions of us. We are also subject to adverse publicity related to actual or perceived environmental practices or impacts, including in relation to climate change and our ability to timely achieve our energy transition goals, as well as negative opinions regarding the appropriateness of our climate-related goals. If customers, investors, legislators, regulators, creditors, rating agencies or creditors other stakeholders have or develop a negative opinion of us or our utility services, this could result in, among other things, less favorable legislative and regulatory outcomes (including but not limited to failure to obtain requested approvals on capital investments) or increased regulatory oversight, negative effects on our access to, and the cost of, capital, project delays or cancellations, increased litigation and negative public perception. The foregoing may harm our reputation and have adverse effects on our business, financial condition, results of operations and cash flow and financial condition. flows.

… a wide-ranging policy and regulatory debate, at the state level, nationally and internationally, regarding the possible means for their regulation. The trend in environmental regulation in previous years has been to place more restrictions and limitations on activities that may impact the environment. On April 22, 2021, Although the United States announced new goals withdrew from the Paris Agreement in 2026, and more recently the United Nations Framework Convention on Climate Change, and the current federal administration has revised and is expected to further revise compliance requirements under a number of 50% federal environmental regulatory programs, many states and localities continue to pursue their own climate policies, and differences in energy policy priorities adopted by future federal administrations could result in additional GHG reduction of economy-wide GHG emissions and 100% carbon-free electricity by 2035, which formed the basis of requirements in the United States. commitments announced in Glasgow, Scotland. These renewed climate commitments coming out of the 2021 United Nations Climate Change Conference held in Glasgow and certain executive orders resulted in the development of additional regulations and changes to existing regulations. For example, in May 2023, the EPA proposed regulations setting new GHG emission reduction targets for coal and gas-fired electric generating units that could potentially require additional operating costs or operating restrictions related to operation of Indiana Electric’s natural-gas fired units. On April 25, 2024, the EPA released its New Source Performance Standards for Greenhouse Gas Emissions From New, Modified, Reconstructed Fossil Fuel-Fired Units; Emission Guidelines for Greenhouse Gas Emissions From Existing Fossil Fuel-Fired Electric Generating Units; and Repeal of the Affordable Clean Energy Rule. CenterPoint Energy is currently reviewing this rule. As a distributor and transporter of natural gas and electricity, and a generator of electricity in Indiana, the Registrants’ revenues, … affected as a result of any regulatory action that would require installation of new control technologies or a modification of its their operations or that would have the effect of reducing the consumption of natural gas or electricity or prevent the use of certain fuel types. Nevertheless, on January 20, 2025, President Trump signed an executive order to withdraw the United States from the Paris Agreement, marking a significant shift in U.S. climate policy. Pursuant to the terms of the Paris Agreement, the withdrawal will take effect on January 27, 2026. Additionally, in January 2025, President Trump signed executive orders that, among other things, direct federal executive departments and agencies to initiate a regulatory freeze for certain rules that have not taken effect, pending review by the newly appointed agency head, and call upon the EPA to submit a report on the continuing applicability of its endangerment finding for GHGs under the Clean Air Act and issue guidance on the “social cost of carbon” to consider whether such metric should be eliminated. There can be no assurance as to the amount or timing of future expenditures for environmental compliance or remediation, and actual future expenditures may be greater than the amounts we currently anticipate, which could adversely affect our business, financial condition, results of operations and cash flows. Likewise, incentives to conserve energy or use energy sources other than natural … result in a decrease in demand for our services. For further discussion, see “Business—Environmental Matters” in Item 1 and “ —Our natural gas businesses must compete with…”

Evolving investor sentiment related to the use of fossil fuels and initiatives to restrict continued production of fossil fuels may have substantial impacts on CenterPoint Energy’s and CERC’s our electric generation and natural gas businesses. For example, because Indiana Electric currently relies on coal for a portion of its … CenterPoint Energy due to CenterPoint Energy’s and CERC’s use of fossil fuels. Also, certain cities in CenterPoint Energy’s and CERC’s Natural Gas operational footprint have discussed the adoption of initiatives to prohibit the construction of new natural gas facilities that would provide … natural gas-fired appliances in new homes, which could affect consumer use of natural gas. Should such bans be enacted within Natural Gas’ CenterPoint Energy’s and CERC’s operational footprint, they could adversely affect consumer demand for natural gas. Any such initiatives and legislation could adversely affect CenterPoint Energy’s and CERC’s businesses, financial condition, results of operations and cash flows.

Further, certain investors, lenders, regulators and other stakeholders are focusing on issues related to environmental justice, which may result in increased scrutiny of our applicable regulatory processes and additional costs of compliance or may adversely affect our reputation. While President Trump in January 2025 signed an executive order calling to terminate all environmental justice offices and positions in the federal government, as well …

CenterPoint Energy is subject to operational, financial and financial other risks and potential liabilities associated with its our sustainability and related activities, including the implementation of and efforts to achieve its GHG emissions reduction our energy transition goals.

In September 2021, CenterPoint Energy announced has adopted energy transition goals and its net zero emission goals for Scope 1 and certain Scope 2 emissions by 2035 and a 20-30% reduction in certain Scope 3 emissions by 2035 as compared to 2021 levels. CenterPoint Energy’s analysis and plan plans for execution requires require it to make a number of assumptions. These goals and underlying assumptions involve risks and uncertainties and are not guarantees, and our ability to achieve these goals will ultimately be driven by the needs of our business, the needs and desires of the customers, jurisdictions and other stakeholders we serve and our performance for our shareholders. In addition, forecasting is inherently speculative and the trajectory of the greater energy transition is uncertain. Should one or more of CenterPoint Energy’s underlying assumptions require updating, its our actual results and ability to make progress towards and achieve its net zero our energy transition goals and GHG emissions reduction goals by 2035 the timing thereof could differ materially from its expectations, and CenterPoint Energy may elect to modify or update such goals. Further, there can be no guarantee that CenterPoint Energy will sustain or achieve these goals. Certain of the assumptions that could impact CenterPoint Energy’s ability to meet its net zero and GHG emissions reduction our energy transition goals and the timing thereof include, but are not limited to: GHG emission levels, service territory size, and capacity needs and customer demand remaining in line with Company CenterPoint Energy’s expectations when such goals were announced, including with respect to demand for our services and in relation to the announced recent sale of CenterPoint Energy’s Louisiana and Mississippi natural gas LDC businesses and the announced sale of CenterPoint Energy’s Ohio natural gas LDC business; the ability to appropriately estimate and effectively manage business opportunities from and maintain reliability in connection with new customers and load growth resulting from, among other things, expansion of data centers (associated with, among other things, increasing demand for AI), energy export facilities, including hydrogen facilities, electrification of industrial processes refining and transport exports, advanced manufacturing and logistics in our service territories; regulatory approvals related to Indiana Electric’s generation transition plan and our ability to obtain such approvals; the ability to execute anticipated divestitures, portfolio optimizations or other strategic transactions; interconnection delays in the footprints of regional transmission organizations and/or interconnection costs; impacts on cost and affordability of customer rates and related concerns; customer demand for GHG emission free or lower GHG emissions energy; impacts of future regulations, legislation or legislation, other governmental action, including those related to our operation of certain generating facilities (including the U.S. Department of Energy’s December 2025 emergency 202(c) order directing Indiana Electric to continue operating F.B. Culley Unit 2 through March 23, 2026), the environment and tax (including the effects of the OBBBA, Executive Order 14315, the IRA and any further changes to or the repeal of the renewable energy tax credits enacted in the IRA); federal and state executive, legislative and regulatory actions (including regulatory uncertainty resulting from changes in federal energy policy) and support for certain types of generation; impacts of future carbon pricing regulation or legislation, including a future carbon tax; price, availability and regulation of carbon offsets; price of fuel, such as natural gas; cost and technological development/innovation, adoption and commercialization of energy generation technologies, such as wind and solar, natural gas and storage solutions, adoption of and alternative energy, by the public, including adoption of electric vehicles; rate of technology innovation with regards to alternative energy resources; CenterPoint Energy’s our ability to implement its our modernization plans for its pipelines and facilities; the ability to complete and timely implement and maintain system reliability during and after transitioning to generation alternatives such as solar and wind generation, to Indiana Electric’s coal generation; and execution of the retirement or fuel conversion dates of Indiana Electric’s coal facilities by 2035; on anticipated timelines or at all; the ability to construct and/or permit new natural gas pipelines; the ability to procure resources needed to build at a … lack of or scarcity of resources and labor, any project cancellations, construction delays or overruns (including as a result of tariffs, legislation, bans, retaliatory changes in U.S. or foreign trade measures taken against the United States or related governmental action) policies) and the ability to appropriately estimate costs of new generation; impact of any supply chain disruptions; changes in applicable standards, metrics, methodologies or frameworks; and enhancement of energy efficiencies. Our businesses have in the past and may in the future face increased scrutiny from investors, governmental authorities and other stakeholders related to our sustainability and practices, including our human capital management activities, including as well as the goals, targets, and objectives we announce, our methodologies and timelines for pursuing them, our progress towards achieving them and related disclosures. We could also face challenges with managing conflicting requirements and our various stakeholders’ expectations. If We may be unable to satisfy all of our stakeholders, and to the extent our sustainability practices (including our human capital management activities) do not align with investor or other stakeholder expectations and standards, which continue to evolve, vary, and sometimes conflict, our businesses, including our reputation, our ability to attract or retain employees, and our attractiveness as an investment or business partner could be negatively affected and we could be exposed to enforcement actions and litigation. Similarly, our failure or perceived failure to pursue, fulfill or demonstrate meaningful progress towards our sustainability-focused goals, targets and objectives, … or at all, could adversely affect our business or reputation, as well as expose us to government enforcement actions and private litigation. • provisions of relevant securities laws and our ability to obtain required regulatory authorization for issuances of securities.

… that we believe any of these costs are recoverable in rates, cost recovery could be resisted by our regulators and the public, and our regulators might attempt to deny or defer timely recovery of these costs. Moreover, we cannot predict the ultimate impact of achieving our emissions reduction goals, or the various implementation aspects, on our system reliability or our business, financial condition, and results of operations and cash flows.

We are subject to regulatory compliance and proceedings, extensive regulation, which could result in higher costs for system improvements, as well as fines or other sanctions.

… the Texas RE, a Texas non-profit corporation, and for reliability in the portion of MISO that includes Indiana Electric to ReliabilityFirst Reliability First Corporation, a Delaware non-profit corporation. Compliance with mandatory reliability standards may subject Houston Electric and Indiana Electric to higher operating costs and may result in increased capital expenditures, which may not be fully recoverable in rates. While Houston Electric and Indiana Electric have received minor fines in the past for noncompliance. If Houston Electric or Indiana Electric were to be found to be in noncompliance with applicable mandatory reliability standards again, they would be subject to additional sanctions, including potential monetary penalties, which could range as high as over a million dollars per violation per day, and non-monetary penalties, such …

Additionally, compliance with existing and potential new regulations related to CERC’s operation and maintenance of natural gas infrastructure could result in significant costs. The PHMSA is responsible for administering the DOT’s national regulatory program to assure the safe transportation of natural gas, petroleum and other hazardous materials by pipelines. The PHMSA continues to develop regulations and other approaches to risk management to assure safety in design, construction, testing, operation, maintenance … infrastructure. We have programs in place to comply with regulations related to CERC’s operation and maintenance of natural gas infrastructure, such as leak detection surveys and corrosion and critical valve inspections, and we systematically monitor and renew infrastructure over time; however, CERC has received minor fines failed to maintain compliance with applicable regulations in the past and has received fines for past noncompliance. and A significant incident or material finding of non-compliance in the future could result in enforcement action, penalties, and higher costs of operations and adverse impacts on our regulatory proceedings, any of which could have an adverse effect on our business, financial condition, results of operations and cash flows.

Our businesses may be adversely affected by the intentional misconduct of our employees, consultants, contractors, suppliers and vendors.

We are committed to living our core values of safety, integrity, accountability, initiative and respect and complying with all applicable laws and regulations. Despite that commitment and efforts to prevent misconduct, it is possible for employees, consultants, contractors, suppliers and vendors to engage in intentional misconduct, fail to uphold our core values, and violate laws and regulations for individual gain through contract or procurement fraud, misappropriation, bribery or corruption, fraudulent related-party transactions and serious breaches of our Ethics and Compliance Code Codes and other policies. If such intentional misconduct by employees, consultants, contractors, suppliers and vendors should occur, it could result in substantial liability, higher costs, increased regulatory scrutiny and negative public perceptions, any of which could have an adverse effect on our business, financial condition, results of operations and cash flows. From time to time, including as part of our Ethics and Compliance program’s efforts to detect misconduct, we become aware of and expect to continue to become aware of instances of employee misconduct by employees, consultants, contractors, suppliers and vendors, which we investigate, remediate and disclose as appropriate and proportionate to the incident.

Disruptions to the global supply chain, inflation, labor shortages and scarcity of certain materials may lead to higher prices for goods and services and impact our operations, which could have an adverse impact on our ability to execute our capital plan and on our business, financial condition, results of operations and cash flows.

The global supply chain has experienced and may continue to experience significant disruptions due to a multitude of factors, such as geopolitical and economic uncertainty, regulatory and policy instability, import tariffs and changes in U.S. and foreign trade agreements, policy, changes in laws (including tax laws), executive orders, the COVID-19 pandemic, labor shortages, resource availability, long lead time, times, manufacturer production limitations, delivery delays, inflation, severe weather events and disruptions to internal or international shipping, including as a result … have adversely impacted the utility industry. We, as well as other companies in our industry, have experienced supply chain disruptions, as well as increased prices, and we may continue to experience this in the future. For example, President Trump has expressed a desire to impose substantial new or increased tariffs and, in February 2025, imposed tariffs on several countries (the effectiveness of tariffs imposed on certain countries was subsequently delayed until March 2025) and certain imports into the United States. On February 6, 2025, the EPC contractor for Indiana Electric’s proposed natural gas combustion turbines provided a notice to Indiana Electric that the EPC contractor was identifying the impacts of the proposed tariffs on the project and intended to seek an equitable adjustment to the contract price for the project. These tariffs, as well as any new legislation, tariffs, bans, potential retaliatory trade measures taken against the United States or related governmental action, could increase or cause volatility in the cost of and negatively impact our ability to procure materials, supplies (such as natural gas) or services necessary for our business and capital plan, lead to a scarcity of resources and labor necessary for our business and capital plan, further extend lead time or otherwise negatively impact the supply chain. Examples of materials necessary for the transmission and distribution of power we and our industry have experienced difficulties in procuring include transformers, wires, cables, meters, poles and solar panels. If the supply chain disruption persists or worsens, we may experience difficulties in procuring these resources and others necessary to operate our businesses in the future. As a result, we may not be able to procure the resources, including labor, needed to timely perform storm restoration activities, fully execute on our ten-year capital plan and/ or achieve our net zero emission and GHG emissions reduction goals. Moreover, inflation and high interest rates have contributed, and may continue to contribute, to increased prices for materials and services experienced by us and other companies in our industry. We have also faced, and may continue to face, a shortage of experienced and qualified personnel in certain positions, which has resulted in increased competition for skilled labor and wage inflation. Additionally, increased demand for materials necessary for our business has resulted, and may continue to result, in greater competition for and scarcity of such materials. For example, the increase in demand for electricity across the United States has contributed to large demand increases for transformers, which has caused and may continue to cause supply shortages for transformers. Examples of materials necessary for our business that we and our industry have experienced difficulties in procuring include transformers, wires, cables, meters, poles, electronic components, steel, aluminum and solar panels. If such conditions continue, they the supply chain disruption, inflation, labor shortages and scarcity of certain materials persist or worsen, we and the third parties that we contract with may have adverse effects experience difficulties in procuring the resources and labor necessary to operate our businesses in a timely and cost-efficient manner or at all, which could adversely impact, among other things, our ability to perform storm restoration activities, execute on our business, results of operations, cash flow and financial condition. 10-year capital plan, execute Indiana Electric’s generation transition plan and/or achieve our energy transition goals. Even if we are able to procure the necessary resources and labor, we might not be able to do so at a reasonable cost or in a timely manner, which could result in project cancellations or scope changes, delays, cost overruns, and under-recovery of costs, customer affordability concerns and challenges to our ability to remain in compliance with applicable laws, regulations and policies. If we are unable to fully execute on capital plans, our business, financial condition, results of operations and cash flows may be adversely affected.

If we are unable to arrange future financings on acceptable terms, our ability to finance our capital expenditures and operations or refinance outstanding indebtedness could be limited.

Our businesses are capital intensive, with significant and increasing capital spending expected in future periods. We rely on various sources to finance our capital expenditures and operations. For example, we depend on (i) long-term debt, (ii) borrowings through our revolving credit facilities and, for CenterPoint Energy and … (iii) if market conditions permit, issuances of additional shares of common stock or shares of preferred stock by CenterPoint Energy, including through our at-the-market program. We may also use such sources to refinance any outstanding indebtedness as it matures. Additionally, from time to time, our … Electric and CERC, may rely on intercompany borrowings from CenterPoint Energy that may be sourced from CenterPoint Energy’s external financings. These arrangements could expose us to risks, including exposure to losses upon the occurrence of certain events related to the development, construction, operation or financing of applicable projects. As of December 31, 2024, 2025, CenterPoint Energy had $21 nearly $23 billion of outstanding indebtedness on a consolidated basis, which included $324 $714 million of non-recourse Securitization Bonds. For information on outstanding indebtedness of CenterPoint Energy, Houston Electric and CERC as well as future maturities, see Note 12 to the consolidated financial statements. In addition, external sources of capital may not be adequate or available on reasonable terms. If we are unable to arrange future financings on acceptable terms, our ability to finance our operations and capital expenditures, including our ten-year 10-year capital plan announced in 2025 and increased in February 2026 (through which has increased CenterPoint Energy plans to nearly $47.5 invest at least $65.5 billion through 2030), 2035), or refinance our outstanding indebtedness could be limited. Any of these outcomes could have a material adverse effect on our business, financial condition, results of operations and cash flows. Our future financing activities may be significantly affected by, among other things:

• general economic and capital market conditions, including inflation and recession;

• investor confidence in us, our regulatory environment, our industry and the markets in which we operate;

• timing and adequacy of future cost recovery, including securitizations, by jurisdictions in which we operate; and

CenterPoint Energy derives all of its operating income from, and holds substantially all of its assets through, its subsidiaries. Similarly, as a result of the Restructuring, CERC derives a significant portion of its operating income from and holds a significant portion of its assets through its … CERC, and their respective subsidiaries could agree to contractual restrictions on their ability to make payments or other distributions. Further, ring-fencing measures, such as part of the agreement resulting from those adopted by Houston Electric’s Electric in connection with its 2019 base rate case, Houston Electric filed a base rate proceeding in 2024. Further ring-fencing measures could be imposed on Houston Electric subsidiaries of CenterPoint Energy and CERC in the future through legislation or PUCT state commission rules or orders. While current ring-fencing measures have not impacted Houston Electric’s ability to pay dividends to CenterPoint Energy, The imposition of any additional measures impacting CenterPoint Energy’s or CERC’s ability to receive dividends from Houston Electric their respective subsidiaries could adversely affect CenterPoint Energy’s cash flows, credit quality, business, financial condition, and results of operations and cash flows. Any such adverse effect on CenterPoint Energy could also adversely affect Houston Electric’s and/or CERC’s cash flows, credit quality, business, financial condition, and results of operations and cash flows as CenterPoint Energy may not be able to financially support Houston Electric and/or CERC if and when necessary.

… these parental guarantees to date but may be required to do so in the future. For further information, see Note 14(c) 14(b) to the consolidated financial statements.

If CenterPoint Energy redeems the ZENS prior to their maturity in 2029, its ultimate tax liability and redemption payments would may result in significant cash payments, which would adversely impact its cash flows and liquidity. Similarly, a significant amount of exchanges of ZENS by ZENS holders could adversely impact CenterPoint Energy’s cash flows and liquidity.

CenterPoint Energy has approximately $828 million principal amount of ZENS outstanding as of December 31, 2024. 2025. CenterPoint Energy owns shares of ZENS-Related Securities equal to approximately 100% of the reference shares used to calculate its obligation … the ZENS at any time at a redemption amount per ZENS equal to the higher of the contingent principal amount per ZENS $9 of less than $0.1 million in the aggregate, or $0.62 less than $0.01 per ZENS, as of December 31, 2024, 2025, or the sum of the current market value of the reference shares attributable to one ZENS at the time of … the ZENS, in addition to the redemption amount, it would be required to pay deferred taxes related to the ZENS, to the extent such taxes were not currently offset by net operating loss carryforwards or CAMT carryforwards. CenterPoint Energy’s ultimate tax liability related to the ZENS and ZENS-Related Securities continues to increase by the amount of the tax benefit realized each year. If the ZENS had been redeemed on December 31, 2024, 2025, deferred taxes of approximately $802 $897 million would have been payable in 2024, 2025, based on 2024 2025 tax rates in effect, and disregarding the availability of net operating loss carryforwards and CAMT carryforwards. In addition, if all the shares of ZENS-Related Securities had been sold on December 31, 2024 2025 to fund the aggregate redemption amount, capital gains taxes of approximately $84 $72 million would have been payable in 2025, disregarding the availability of net operating loss carryforwards and CAMT carryforwards. As of December 31, 2025, CenterPoint Energy had both net operating loss carryforwards and CAMT carryforwards available from its filed 2024 federal income tax return that can be applied to largely offset the cash tax outflow that would result from a retirement or exchange of ZENS. Similarly, a significant amount of exchanges of ZENS by ZENS holders could adversely impact CenterPoint Energy’s cash flows and liquidity, subject to the availability of net operating loss carryforwards or CAMT carryforwards. This could happen if CenterPoint Energy’s creditworthiness were to drop, the market for the ZENS were to become illiquid, or … exchanges result in a cash outflow because tax deferrals related to the ZENS and ZENS-Related Securities shares would typically be disposed reversed when ZENS are exchanged and ZENS-Related Securities shares are sold, subject to the availability of net operating loss carryforwards or CAMT carryforwards to reduce the cash taxes payable in the year of exchange or sale.

Our business, financial condition, results of operations and cash flows depend, in part, on our management’s ability to implement our business strategies successfully and realize the anticipated benefits therefrom. In 2021, 2025, we announced our strategic goals for CenterPoint Energy, including our ten-year new 10-year capital plan. and net zero and GHG emissions reduction goals. Our strategic goals are subject to the risks described in this section and various assumptions. These assumptions may require updating … goals in a timely manner or at all. If we are unable to execute on our strategic goals, including our ten-year 10-year capital plan, the benefits therefrom may not be fully realized, if at all, and our reputation may be adversely affected.

From time to time we have made, and may continue to make, acquisitions or divestitures of, or other similar transactions involving, businesses and assets, such as our announced sale of our Louisiana and Mississippi Ohio natural gas LDC businesses, business, Houston Electric’s proposed release of its 15 large 27 MW to 32 MW TEEEF units to the San Antonio area and other potential future releasing and subleasing of TEEEF, and our completed sale of our Energy Systems Group business, form joint ventures or undertake restructurings, such as the Restructuring. However, suitable acquisition candidates or potential buyers may not continue … do not perform as anticipated, our future growth may be adversely affected. Further, any completed or future acquisitions, dispositions or similar other strategic transactions involve substantial risks, including the following:

• acquisitions, dispositions or similar other strategic transactions, or the pursuit of such transactions, including any separation or disentanglement efforts or requirements, such as the provision of … disrupt our ongoing businesses, distract management, divert resources and make it difficult to maintain current business standards, controls and procedures; and

• we may not receive regulatory approvals necessary to complete an acquisition, disposition or similar transaction in a timely manner or at all; and

On February 19, 2024, October 20, 2025, CenterPoint Energy, through its subsidiary CERC Corp., entered into the LAMS Asset Ohio Securities Purchase Agreement to sell its Louisiana and Mississippi Ohio natural gas LDC businesses. business. The transaction is expected to close in the first fourth quarter of 2025. 2026, subject to the satisfaction of customary closing conditions. For further information, see Note 4 to the consolidated financial statements. We can make no assurances regarding the completion of this sale, which could be subject to delays or otherwise may not ultimately be consummated.

Changing demographics, poor investment performance of pension plan assets and other factors adversely affecting the calculation of pension liabilities could unfavorably impact our business, financial condition, results of operations and liquidity. cash flows.

… calculate the present value of future plan obligations, or government regulations that increase minimum funding requirements or the pension liability. In 2023 and 2022, CenterPoint Energy had a settlement expense for its pension plans as a result of an increase in eligible employee retirements and pension plan distributions. See Note 8 to the consolidated financial statements for further information. In addition to affecting CenterPoint Energy’s funding requirements, these factors could adversely affect our business, financial condition, results of operations and liquidity. cash flows.

Our businesses are impacted by U.S. federal income tax policy. The TCJA, CARES Act, and the IRA and OBBBA significantly changed the U.S. Internal Revenue Code, including taxation of U.S. corporations, by among other things, reducing the federal corporate income tax rate, limiting interest deductions, altering the expensing of capital expenditures, enacting a new CAMT, and expanding phasing out previously expanded federal tax credits for cleaner energy production. Based on guidance available as of December 31, 2024, the date of the filing of this Form 10-K, the Registrants will continue to be subject to the CAMT included in the IRA.

The interpretive guidance issued by the IRS and state tax authorities, as well as related federal executive orders, may be inconsistent with our interpretation and the legislation could be subject to amendments, which could lessen or increase certain … addition, while certain regulators have allowed the Registrants to recover certain costs associated with the CAMT in the past, the retail regulatory treatment of the expanded tax credits and CAMT could impact the Registrants’ future cash flows, and this legislation could …

Further changes in federal tax reform legislation including or guidance, or uncertainties regarding the repeal, continuation or interpretation of such tax legislation proposed by the new presidential administration, or guidance, could be enacted that may significantly change the federal income tax laws applicable to domestic businesses, including changes that may impact investment incentives and deductions for depreciation and interest, among other deductions. While the details of the Trump Administration’s potential tax reform have not been announced as of the date of the filing of this Form 10-K, during his 2024 presidential campaign, President Trump outlined several intended reforms, including reducing the corporate tax rate for domestic oil and gas production, repealing or revising the IRA, extending certain provisions of the TCJA and imposing new tariffs. In January 2025, President Trump signed an executive order that, among other things, pauses the disbursement of funds appropriated through the IRA. In February 2025, President Trump imposed tariffs on various countries (the effectiveness of tariffs imposed on certain countries was subsequently delayed until March 2025) and certain imports into the United States. Additional new federal tax reform legislation and the implementation of new or increased tariffs could lead to increases in market interest rates, a decrease in U.S. economic growth, and/or recession. Additionally, In addition, interpretations, regulations, amendments, or technical corrections that affect the change in administration amount and the expiring timing of income tax cuts in the TCJA payments could result in the repeal of or changes to the IRA, including renewable energy tax credits enacted in the IRA, and these changes could impact CenterPoint Energy’s net zero and GHG emissions reduction goals. adversely affect our liquidity. While CenterPoint Energy and its subsidiaries cannot assess the overall impact of any such potential legislation or other actions on our businesses, it is possible that our business, financial condition, results of operations or and cash flows could be negatively impacted. Furthermore, with any enacted federal tax reform legislation, it is uncertain how state commissions … in our revenue requirements. As such, potential regulatory actions in response to any enacted tax legislation could adversely affect our business, financial condition, results of operations and cash flows.

… Although the Registrants have insurance coverage for many potential incidents, depending upon the nature and severity of any incident, they have in the past and could in the future experience financial loss, claims and litigation, damage to their reputation, and negative consequences from regulatory authorities or other public authorities. … of violence, actual violence and other concerns may result in employees and third parties supporting the work of the Registrants sustaining serious injuries and being unable or unwilling to complete critical functions, which could adversely affect our businesses, financial condition, and results of operations and cash flows, and could make it harder to, among other things, recruit and retain certain employees.

We are subject to cyber and physical security risks related to our information technology systems, operational technology, network infrastructure and other technology and facilities used to conduct almost all of our businesses. The operation of our electric transmission, distribution and generation transmission and distribution systems is dependent on the physical interconnection of our facilities, as well as communications among the various components of our systems and third-party the systems of supply chain stakeholders (such as vendors, contractors and suppliers). Further, certain of the various internal systems we use to conduct our businesses are highly integrated. Consequently, a cyberattack or … by man-made events, such as cyberattacks or acts of terrorism, may disrupt our ability to conduct operations and control assets, lead to operational interruptions and negatively impact our business.

… cybersecurity incident response plan, may be insufficient. In addition, new technology that could result in greater operational efficiency, such as our use of AI and cloud-based infrastructure, may further expose our computer systems to the risk of cybersecurity incidents. Also, remote working arrangements could increase our data security risks, including loss of data related to sensitive customer, employee, financial and operating system information, through insider or outsider actions. Cyberattacks, including deep fakes (which are increasingly more difficult to identify as fake), phishing, smishing, vishing or quishing attacks and threats from the use of malware, ransomware and viruses or malicious code, and unauthorized access could also result … infrastructure data or security breaches of other information technology systems that could disrupt operations and critical business functions, adversely affect our reputation, impact our customers, increase costs and subject us to possible legal claims and liability. While we have implemented and … exploit new, unknown vulnerabilities (e.g., zero-day vulnerabilities) and vulnerabilities where a patch or other remediation measure is not yet available. The data that we disclose to, and services we receive from, third parties may be subject to cybersecurity risks associated with threats to third-party systems. These risks include security compromises, vulnerabilities or failures related to the technologies and systems used by service providers, other supply chain stakeholders and/or governmental entities. The potential impact of such threats depends in part on the criticality of the third-party services and/or extent of access these third parties have to our confidential information and/or systems. We have experienced an increase in the number of attempts by external parties to access our networks or our company … and expect to continue to experience, cyber intrusions and attacks to our information systems and those of third parties, including vendors, suppliers, contractors supply chain stakeholders and quasi government entities who perform certain services for us or administer and maintain our sensitive information. These prior intrusions and attacks have not had a material impact on our business, financial condition, results of operations or financial condition. and cash flows. Because technology is increasingly complex and cyberattacks are increasingly sophisticated and more frequent, there is a risk such incidents could … a cybersecurity breach or ransomware attack, has increased as attempted attacks have advanced in sophistication and number around the world. Our Although CenterPoint Energy currently maintains cybersecurity insurance, this insurance is limited in scope and subject to exceptions, conditions and coverage limitations and may not be sufficient to cover all the costs associated with potential cybersecurity threats or incidents, and there is no guarantee that the insurance that CenterPoint Energy currently maintains will continue to be available at rates we believe are reasonable.

Our continued efforts to integrate, consolidate and streamline our operations have also resulted in increased reliance on current and recently completed projects for technology systems and may increase potential vulnerabilities and points of failure in our information and operations systems. A failure to maintain and enhance existing information technology systems, or the failure of new technology systems to be implemented as designed, could adversely affect our operations. Procedures we implement to protect our systems may be insufficient to protect and safeguard against …

… process, transmit and store electronic information, including information and operational technology we use to safely operate our energy transportation systems. Companies in our industry face a heightened risk of exposure to and have experienced acts of terrorism and vandalism. Our electric and gas physical infrastructure may be targets of physical security threats or terrorist activities. Further, recent escalation with respect to geopolitical conflicts may increase the likelihood that facilities within the United States, including natural gas distribution systems or electric transmission, distribution or generation systems that we own or on which we rely, will be targeted by strikes, acts of terrorism or cyberattacks. Security breaches, attacks on our infrastructure and facilities, including against the Registrants or as a means to harm a third-party third party by disrupting the transmission and distribution of energy, or acts of terrorism, including by foreign or domestic actors, and vandalism could expose our business to a risk of loss, misuse or interruption of critical physical assets or information and functions … to our assets, public or personal safety incidents, impacts to our customers, damage to the environment, reputational harm, competitive disadvantage, increased regulation and regulatory enforcement actions, litigation and a potential adverse effect on our operations, business, financial condition, results of operations and cash flows. There is no certainty that costs incurred related to actual or thwarted cyberattacks, or for the safeguarding against such security threats, will be recoverable through rates.

Cyberattacks are becoming more sophisticated, and U.S. government warnings have indicated infrastructure assets, including pipelines and electric generation and infrastructure, may be specifically targeted by certain groups. Regulators have adopted numerous rules and regulations regarding cybersecurity. As a result, CenterPoint Energy continues to take measures to comply … or failure in our cybersecurity protective measures may result in enforcement actions which may have an adverse effect on our reputation, business, financial condition, results of operations and cash flows.

In connection with our businesses, we and our third parties (vendors, suppliers, and contractors) supply chain stakeholders collect and retain personal information (for example, information of our customers, shareholders, suppliers and employees), and there is an expectation that we and such third parties supply chain stakeholders will adequately protect that information. The regulatory environment surrounding information security and data privacy continues to evolve and is increasingly … and the systems we have implemented to manage and protect personal information cannot prevent all privacy breaches. We and some of our third parties supply chain stakeholders that maintain personal information have experienced, and expect to continue to experience, data privacy incidents and breaches; however, to date, … legal requirements, could adversely impact our reputation and could result in significant costs, fines and penalties and liabilities for us. Additionally, if we acquire a company that has violated or is not in compliance with applicable data protection privacy, we may incur significant liabilities and penalties as a result.

… risks involved in developing and deploying AI, and ineffective or inadequate development or deployment of AI practices by us or our third-parties (vendors, suppliers, and contractors) supply chain stakeholders could result in unintended consequences. We contract with third-parties supply chain stakeholders that use AI in products and services they provide, and we may not have full control or visibility over the … services or be beneficial to our business, including with respect to the efficiency and resiliency of our systems. For example, our AI-related efforts by us or supply chain stakeholders may give rise to risks related to harmful content, accuracy, bias, discrimination, intellectual property infringement or misappropriation, defamation, data privacy, and cybersecurity, among others, which could lead to operational interruptions or otherwise adversely affect our business, reputation or financial results. In addition, the adoption of AI may subject us to new or enhanced governmental or regulatory scrutiny, new or amended laws, rules, directives, and regulations governing the use of AI (which may be conflicting), litigation, ethical concerns, negative consumer perceptions as to automation and AI, or other complications that could adversely affect our business, reputation, or financial results. Developing, testing and deploying resource-intensive AI systems may also require additional investment and increase costs. We may not be able to recover our investments in AI technology through our regulatory proceedings, and our use of, or our third parties’ supply chain stakeholders’ use of, AI may subject us to legal liability. Similarly, as AI continues to evolve, we may not be able …

Houston Electric’s, Indiana Electric’s and Natural Gas’ Our revenues and results of operations are subject to seasonality, weather conditions and other changes in electricity and natural gas usage, … certain past years, unusually mild weather in the warmer months could diminish Houston Electric’s results of operations and harm its business, financial condition and cash flows. Conversely, as in certain past years, extreme warm weather conditions could increase Houston Electric’s results of operations in a manner … seasonal weather conditions could increase Indiana Electric’s results of operations in a manner that would not likely be annually recurring. Revenues in our Natural Gas revenues reportable segment are customarily higher during the winter months. As in certain past years, unusually mild weather in the winter months could diminish Natural Gas’ our results of operations and harm its our business, financial condition, results of operations and cash flows. Conversely, as occurred in certain past years, extreme cold weather conditions could increase its our results of operations in a manner that would not likely be annually recurring. For additional risks related to the February 2021 Winter Storm Event, see Note 7 to the consolidated financial statements for further information.

Severe weather events, natural disasters and other climate-related impacts could adversely impact our businesses, financial condition, results of operations and cash flows. We operate businesses that require sophisticated data collection, processing systems, software and other technology. Some of the technologies supporting the industries we serve are changing rapidly and increasing in complexity. New technologies will emerge or grow evolve that may be deliver superior capabilities to, or may not be compatible with, some of our existing technologies, and may require us to make significant investments and expenditures so that we can continue to provide cost-effective and reliable methods for technology solutions to support energy production and delivery. Among such technological advances are distributed generation resources (e.g., private solar, microturbines, fuel cells), energy storage devices and more energy-efficient buildings and products designed to reduce energy consumption, emissions attributable to our operations and waste. As these technologies become a more cost-competitive option over time, whether through cost effectiveness or government incentives and subsidies, such as under the IRA, certain customers may choose to meet their own energy needs and subsequently decrease usage of our systems and services, including Indiana Electric’s generating facilities becoming less competitive and economical. Further, certain regulatory and legislative bodies have introduced or are considering requirements and incentives to reduce energy consumption by certain dates. Just as high inflation and rising interest rates incentivize our customers to consume less energy, technological advances driven by federal laws mandating new levels of energy efficiency in end-use electric and natural gas devices or other improvements in or applications of technology could lead to declines in per capita energy consumption. Our future success will depend, in part, on our ability to anticipate, and adapt to, these integrate and implement technological changes in a timely and cost-effective manner, to offer, on a timely basis, reliable services that meet customer demands and evolving industry standards and to recover all, or a significant portion of, any unrecovered investment, in including obsolete assets. Accordingly, we periodically implement new or enhanced technology, including information systems. Implementation of such new technology, including information systems, can, and pursuant to certain projects included in our 10-year capital plan, will, require the commitment of significant, sufficiently skilled personnel, engagement of third parties, substantial capital investment and additional administration and operating expenses, and entails risks to our business operations. If the integration or implementation of technology, including information systems, as designed is delayed or unsuccessful, we may not realize anticipated productivity improvements or cost efficiencies and may experience interruptions in service and operational difficulties, which could adversely affect our business, financial condition, results of operations and cash flows. Our 10-year capital plan additionally calls for example, an expansion the rapid integration and implementation of data centers, energy export facilities, including hydrogen facilities, electrification of industrial processes and transport and logistics, among others, could generate a significant increase in demand for electric power in CenterPoint Energy’s service territories, which may require us to rapidly adopt new technologies and make significant transmission and distribution investments, including such as advanced grid infrastructure, which increases exposure to overall potential grid instability and technology obsolescence. If we fail to successfully adapt successfully to, any integrate and implement a technological change, or obsolescence, fail to obtain access to important technologies, or incur significant expenditures in adapting to technological change, or if implemented technology does not operate as anticipated, our regulatory recovery could be negatively impacted and our businesses, financial condition, results of operations and cash flows could be adversely affected.

A changing climate creates uncertainty and could result in broad changes, both physical and financial in nature, to our service territories and our business. If climate changes occur that result in warmer temperatures than normal in Our service territories, financial results facilities and operations face physical risks from our businesses could be adversely impacted. For example, where natural gas is used to heat homes and businesses, warmer weather might result in less natural gas being used, adversely affecting us. Another possible result of climate change is more frequent and more severe weather events, Weather-related incidents natural disasters and other climate-related conditions, which have become more prevalent, frequent, unpredictable and severe as a result of climate change or other factors. Severe weather events, natural disasters and other climate-related conditions impact our service territories, primarily when hurricanes and remnants of hurricanes, tornadoes, floods, severe winter weather conditions, including ice storms, wildfires, thunderstorms, high winds, hail, derecho events, microbursts, drought, excess humidity or extreme temperatures (high heating/cooling days) occur, which can impact our operations and our ability to serve our customers, including resulting in operational interruptions and large-scale and/or prolonged outages. To the extent the frequency and severity of extreme weather events, increases, natural disasters and climate-related conditions such as rising sea level and coastal erosion continue to increase, our costs of providing service may increase, including the costs and availability of procuring insurance related to such impacts, and those costs may not be recoverable. In addition, our insurance may not be sufficient or effective under all circumstances and against all related hazards or liabilities to which we may be subject. Any losses for which we are not fully insured or that are not covered by insurance at all could adversely affect our business, financial condition, results of operations and cash flows. A delay or failure in recovering amounts for storm restoration costs incurred, inability to securitize future storm restoration costs, or loss of revenues as a result of severe weather could have a material impact on us, including lower credit ratings and, thus, higher costs for future debt issuances, as well as limitations on our ability to fund other investments to address customer needs. The implementation of budget and spending cuts to federal government agencies and programs could also impact our operations and our ability to serve customers when such weather events, natural disasters and other climate conditions occur, including increasing our costs. Further, events of extreme weather and natural disasters could make it unsafe or hinder the effectiveness of our employees to fix, maintain and restore power to affected areas … Event and Hurricane Beryl, and could experience similar events in the future, which could have an adverse impact on our business, financial condition, results of operations and cash flows. Further, if climate changes occur that result in fewer heating degree days than normal in our service territories, which has occurred in certain past years, financial results from our businesses could be adversely impacted. For example, where natural gas is used to heat homes and businesses, warmer weather might result in less natural gas being used, adversely affecting us.

Wildfires also have the potential to negatively affect communities our service territories Severe weather events, natural disasters and the surrounding areas, as well as our electric effects of climate change have increased the duration of wildfire season and natural gas infrastructure, including Houston Electric’s and Indiana Electric’s vast network of electric transmission and distribution lines and facilities and CERC’s natural gas distribution systems. may further exacerbate the possibility of wildfires and the risk risks related thereto, including that we may be held liable for damages incurred as a result of wildfires, reputational harm, damage to our network, facilities and systems resulting therefrom. may be exacerbated by severe weather events and the effects of climate change. The continued expansion of the wildland-urban interface has also increased wildfire risk to communities in our service territories. While we proactively take steps to mitigate wildfire risk in the areas of our electrical and natural gas assets, wildfire … reputational harm if it was determined that they were caused by or enhanced due to any fault of CenterPoint Energy. Wildfires could also jeopardize our electric and natural gas infrastructure, including Houston Electric’s and Indiana Electric’s vast network of electric transmission and distribution lines and facilities and CERC’s natural gas distribution systems, and third-party property and result in temporary or prolonged power outages and shortages in our service territories. Wildfires also have the potential to negatively affect communities in our service territories and the surrounding areas, and the continued expansion of the wildland-urban interface has increased this wildfire risk. In addition, while we maintain wildfire insurance, our insurance may not be sufficient to cover all losses we may incur as a result of wildfires. Wildfires could also lead to significant financial distress, credit rating downgrades and further increased costs for wildfire insurance or lack of availability thereof. Insufficient wildfire insurance coverage, increased wildfire insurance costs and a lack of wildfire insurance availability could adversely impact our business, financial condition, results of operations and cash flows. Furthermore, any damage caused to our assets, loss of service to our customers, or liability imposed, credit rating downgrades or regulatory recovery risk occurring as a result of wildfires could negatively impact our business, financial condition, results of operations and cash flows.

During and in the aftermath of the February 2021 Winter Storm Event, the Texas legislature revised applicable statutes and granted the PUCT and ERCOT additional regulatory authority, both oversight and enforcement, that focuses on ensuring ERCOT market participants, including power generation facilities and TDUs (like Houston Electric), have adopted sufficient winterization standards and protection. Houston Electric believes it is in compliance with the requirements applicable We are subject to it. If any additional protections are required in the future transition risk relating to climate change, as a result of additional extreme weather events or other causes, complying with these new protections may increase the cost of electricity, which could adversely affect Houston Electric’s results of operations. Any potential decreases in customer usage due to higher electricity prices charged by REPs may not result in increased base rates charged by Houston Electric for its services until its next general base rate proceeding. For further information on Houston Electric’s regulatory proceedings, see “— Rate regulation of Registrants’ Electric...” well. In the long term, climate change could also cause shifts in population, including customers moving away from our service territories. When we cannot deliver electricity or natural gas … us by among other things, causing permitting and construction delays, project cancellations or increased project costs passed on to us. For further information on these initiatives, see “— We are subject to operational…” Finally, we also may be subject to climate change litigation, which could result in substantial fines, penalties or damages and restrictions on our … its marketing and use of fossil fuels and attributing climate change to emissions resulting from the use of fossil fuels. For more information, see “— CenterPoint Energy is While we have pursued and executed, and continue to pursue and execute, on plans to accelerate investments to enhance the resiliency of our systems to better withstand severe weather, natural disasters, and other climate-related impacts, these plans are generally subject to operational approval by regulators and may not be approved in full or at all. Certain accelerated resilience plans of the Registrants have received regulatory approval for a limited scope and duration, generally at levels less than those proposed to the regulators. We may not be able to successfully execute such plans and projects in the time and manner planned and there are risks regarding the ability to demonstrate the efficacy of the accelerated resilience investments in mitigating storm impacts, as well as in seeking and obtaining regulatory approval for additional accelerated resilience plans and projects that may be necessary. The need for this investment and these expenditures could cause execution, liquidity, capital or other financing-related risks as well as result in upward pressure on our customer rates, which, particularly when combined with upward pressure resulting from the recovery of the costs of recent and future storms, may result in adverse actions by applicable regulators or effectively limit our ability to make other planned capital or other investments. The occurrence of extreme weather events, including winter storms and record hot temperatures, or other causes could also lead to additional reforms to the Texas electric market, some measure of which, if implemented, could have an adverse impact on Houston Electric. For example, during and in the aftermath of the February 2021 Winter Storm Event, the Texas legislature revised applicable statutes and granted the PUCT and ERCOT additional regulatory authority, both oversight and enforcement, that focuses on ensuring ERCOT market participants, including Houston Electric, have adopted sufficient winterization standards and protection. If any additional protections are required in the future as a result of additional extreme weather events or other causes, complying with these new protections may increase the cost of electricity, which could adversely affect Houston Electric’s business, financial risks...” condition, results of operations and cash flows.

We are exposed to risks related to changes in demand and energy consumption that could adversely impact our business, financial results from our businesses and our condition, results of operations and cash flows.

Hurricane Beryl caused severe disruptions to Our operations, customers and markets in certain of our service territories and could have a material adverse impact on our financial condition, results of operations, cash flows and liquidity. Additionally, our operations businesses are also affected by new customers and load growth. We anticipate a high level of load growth and an increase in demand for example, electric power in certain of our service territories, including from the expansion of data centers (associated with, among other things, increasing demand for artificial intelligence), AI), energy export facilities, including hydrogen facilities, electrification of industrial processes refining and transport exports, advanced manufacturing and logistics, among others, could lead to an unprecedented increase in demand for electric power and a significant portion of the planned investments in our service territories. As we evaluate business opportunities presented by 10-year capital plan is intended to support such development in our service territories, expected growth. Nevertheless, significant uncertainty exists. We are subject to potential challenges including in accurately forecasting such load growth and predicting future electric power needs due to, among other things, rapidly changing technology and market dynamics, changes in industry practice and the possibility that new large customers will be transitory and exit our service territory or otherwise delay or cancel their planned projects. We are subject to potential challenges in capitalizing on opportunities presented by these developments (including if such opportunities do not materialize to the degree expected), managing the potential power demand, generation sources, and transmission capabilities to meet potential load growth, financing the capital investment needed to build and maintain the necessary infrastructure to support such development on satisfactory terms and conditions and consistent with the maintenance of satisfactory credit ratings, executing on such build and maintenance of the necessary infrastructure to support such development on acceptable timelines and in a cost-effective manner while maintaining affordability for customers, managing the possible environmental impact of the potential increased power demand, achieving our net zero and GHG emissions reduction energy transition goals on expected timelines and evaluating and complying with evolving regulations related to such development. These challenges, and our efforts to predict and address these challenges them, could have a material impact on us, including if we fail to capitalize on the opportunities relating to these developments or fully realize anticipated benefits from significant capital investments and expenditures made to address such development, which could adversely affect our ability to execute our 10-year capital plan, cause us to incur additional expenses to terminate or redeploy any underutilized assets or infrastructure, or fail to fully recover our capital expenditures, all of which could have an adverse effect on our business, financial condition, results of operations and cash flows. For example, our failure to capitalize on the opportunities presented by these developments or potential large load customers delaying or cancelling their planned projects could lead to delays or the cancellation of projects included in our 10-year capital plan. Further, regulators may investigate the prudence of costs in our rates and examine, among other things, the reasonableness or prudence of our level of expenditures (including costs associated with our capital projects supporting new customers and load growth). In addition, volatility in stock prices of perceived significant energy customers, such as technology companies involved with data centers, AI or cryptocurrency, or other significant developments with such companies, could cause increased volatility in stock prices of certain companies in our industry.

Our businesses are also affected by reduction in energy consumption due to factors including economic, climate and market conditions in our service territories, energy efficiency efficiency/reduction initiatives, advances in technology and use of alternative technologies and changes in our customers’ perceptions regarding natural gas usage as a result of incidents of … additional delivery facilities. Customer growth and customer usage are affected by a number of factors outside our control, such as mandated energy efficiency measures, efficiency/reduction initiatives, bans on or further regulation of natural gas-fired appliances, demand-side management goals, technological advances (e.g., distributed generation resources, energy storage devices and more energy efficient buildings and products) and economic and demographic conditions, including population changes, job and income growth, housing starts, changes in rate designs, new business formation and the overall level of economic activity. For example, certain regulatory and legislative bodies have introduced or are considering requirements and incentives to reduce energy consumption by certain dates. Declines in demand for electricity and natural gas in our service territories due to pipeline incidents of other utilities, increased … could result in lower growth and reduced demand for and usage of electricity and natural gas in such service territories. Further, deregulation or other changes in law in our service territories could allow third-party suppliers to contract directly with customers for their natural gas and electric supply requirements. In addition, legislation or regulation that supports distributed energy technologies or that allows third party sales from such technologies could result in further competition. Some or all of these factors could result in a lack of growth or decline in customer demand for electricity … failure to fully realize anticipated benefits from significant capital investments and expenditures, which could have an adverse effect on our business, financial condition, results of operations and cash flows.

We have risks associated with aging infrastructure assets, including the failure of equipment or processes and potential breakdowns due to such aging. These risks have in the past and may continue to be driven by threats such as, but not limited to, electrical faults, mechanical failure, internal and external corrosion, ground movement and stress corrosion and/or cracking. The age of certain of our assets, including each of Indiana Electric’s coal generating facilities, which were constructed in 1973 and 1966, respectively, have in the past resulted and may continue to result in a need for replacement, or higher level of maintenance costs, reduced generation output and unscheduled outages because of, among other things, our risk based risk-based federal and state compliant integrity management programs. The failure to operate our assets as desired could result in interruption of service, safety concerns, major component failure at generating facilities and electric substations, events such as gas leaks, and an inability to meet service and compliance obligations, which could adversely impact revenues, and could also result in increased capital expenditures and maintenance costs. As part of our long-term capital plan GHRI and the SRP, various plans and projects thereunder, we continue to make upgrades to our aging infrastructure assets to enhance the reliability of our infrastructure. Failure to achieve … and could result in increased capital expenditures or expenses. In addition, the nature of information available on aging infrastructure assets, which in some cases is incomplete, may make operation of the infrastructure, inspections, maintenance, upgrading and replacement of the assets particularly challenging. Missing or incorrect infrastructure data may lead to difficulty properly locating facilities, which can result in excavator damage and operational or emergency response issues; configuration and control risks associated with the modification of system operating pressures in connection with turning off or turning on service to customers, which can result in unintended outages or operating pressures; and other potential risks related to missing or incorrect infrastructure data. Also, additional maintenance and inspections are required in some instances to improve infrastructure information and records and address emerging regulatory or risk management requirements, resulting in increased costs. Our ability to successfully maintain or replace our aging infrastructure has been and may continue to be delayed or be at a greater cost than anticipated due to supply chain disruptions. Further, issues or governmental actions. For example, while Indiana Electric’s 2025 IRP (similar to previous IRPs) preferred portfolios included the retirement of F.B. Culley Unit 2 by the end of 2025, a coal-fired generation unit, the U.S. Department of Energy issued emergency order 202(c) in December 2025 directing Indiana Electric to continue operating the unit through March 23, 2026. Additionally, with respect to our natural gas operations, if certain pipeline replacements (for example, cast-iron or bare steel pipe) are not completed timely or successfully, … caused by a failure to timely complete equipment replacements. Insufficient insurance coverage and increased insurance costs could adversely impact our business, financial condition, results of operations and cash flows. Finally, aging infrastructure may complicate our utility operations ability to address severe weather, natural disaster and climate change concerns and efforts to enhance resiliency and reliability. See “— Disruptions to the global supply...”

Our business, financial condition, results of operations and cash flows may be adversely affected if we are unable to successfully operate our facilities or perform certain corporate functions.

Our performance depends on the successful operation of our facilities. Operating these facilities involves many risks inherent in the transmission, distribution and generation transmission and distribution of electricity and in the delivery of natural gas that could result in substantial losses or other damages. From time …

• operator error or failure of equipment or processes, including natural gas ignition events or associated incidents, pipeline high-pressure or over-pressure events or ruptures, or failure to follow appropriate safety protocols for, among others, the transmission and distribution of electricity and in the delivery of natural gas, including operations of our storage and peak shaving facilities;

• information technology or financial and billing system failures, including those due to the implementation and integration or failure of new technology (including AI technology), that impair our information technology infrastructure, reporting systems or disrupt normal business operations, • information technology failure, including failure of AI technology, that affects affect our ability to access customer information or causes cause us to lose confidential or proprietary data that adversely affects our reputation or exposes us to legal claims; and

• failure to obtain in a timely manner and at reasonable prices the necessary fuel, such as coal and natural gas, building materials or other items needed to operate our facilities; and

• catastrophic events such as fires, earthquakes, explosions, leaks, floods, droughts, hurricanes, tornados, derecho events, ice storms, terrorism, cybersecurity incidents, wildfires, pandemic public health events, emergencies (including pandemics), acts of war, military invasions, civil unrest, geopolitical conflict or other similar occurrences, including any environmental impacts related thereto, which catastrophic events may require participation in mutual …

Such events may result in a decrease or elimination of revenue from our facilities, an increase in the cost of operating our facilities, environmental or property damage, delays in cash collections, harm to our reputation, legal proceedings, less favorable legislative and regulatory outcomes, changes to policies, laws and regulations or increased regulatory oversight, any of which could have an adverse effect on our business, financial condition, results of operations …

Our businesses will continue to have to adapt to, integrate and implement technological change and may not be successful implementing such technological change as designed or may have to incur make significant expenditures investments to adapt to and integrate technological change.

We currently have insurance in place, such as general liability, excess liability and property insurance, to cover, among other things, certain of our facilities and third-party bodily injury in amounts that we consider appropriate. Such policies are subject to certain limits and deductibles and do not include business … our facilities may not be sufficient to fully cover or restore the loss or damage without negative impact on our business, financial condition, results of operations and cash flows. Certain types of damages, expenses or claimed costs, such as fines and penalties, have been in the past and may in the future be excluded under the policies. In addition, insurers providing insurance to us have in the past and may in the future dispute and raise defenses to coverage under the terms and conditions of the respective insurance policies, which can result in a denial of coverage or limit the amount of insurance proceeds available to us. Any losses for which we are not fully insured or that are not covered by insurance at all could adversely affect our business, financial condition, results of operations and cash flows. Costs, damages and other liabilities related to recent events and incidents that …

… bonds or a change in its regulated rates or otherwise. In the future, any such recovery may not be granted. For example, Houston Electric is seeking to recover the system restoration costs associated with Hurricane Beryl and certain other significant storms through the issuance and sale of non-recourse system restoration bonds. Although Houston Electric expects to receive the net proceeds from its offering of system restoration bonds on February 26, 2026, there can be no assurance that the system restoration costs will be recovered in the amounts expected or on the expected timeline. Therefore, Houston Electric may not be able to restore any loss of, or damage to, any of its transmission and distribution properties without negative impact on its business, financial condition, results of operations and cash flows.

Global or regional health pandemics, epidemics or similar public health threats could negatively impact our business, outlook, financial condition, results of operations and liquidity. cash flows.

Like many companies, we experienced the above and other impacts during the COVID-19 pandemic. These and other impacts of global or regional health pandemics, epidemics or similar Public health threats, including pandemics and epidemics, and any third-party actions taken to contain the spread and mitigate the public health threats, have had and may in the future have widespread impacts on the global economy, our supply chain and our employees, customers and supply chain stakeholders. Any future health threat could also have potentially material impacts on our business, financial condition, results of operations and cash flows. The effect ultimate impact of heightening many of the other risks described in this section public health threats on our business depends on factors beyond our knowledge or control and the other reports we file from time to time with the SEC. we might not be able to predict or respond to all impacts on a timely basis to prevent near- or long-term adverse impacts to our operations, business, financial condition, and liquidity. The ultimate impact of public health threats on our business depends on factors beyond our knowledge or control, including the duration and severity of the outbreak as well as third-party actions taken to contain the spread and mitigate the public health effects. Any of these factors could have a negative impact on our business, outlook, financial condition and results of operations which impact could be material. and cash flows.

Failure to attract, motivate and retain an appropriately qualified workforce, identify and develop top talent to succeed senior management and maintain good labor relations could adversely impact the operations of our facilities and our business, financial condition, results of operations and cash flows.

Our businesses and ability to implement our strategies are dependent on recruiting, retaining and motivating employees, including senior executive officers and other key personnel. Like many companies in the utilities industry and other industries, we have experienced higher than normal turnover of employees as a result of a number of factors, including a tightening labor market, increasing remote working opportunities, employees shifting industries, individuals deciding not to work and a maturing workforce. Of our employee population, not including employees of Energy Systems Group prior to its divestiture on June 30, 2023 or temporary employees, 17.1%, 18.2%, and 18.7% and 19.3% were retirement eligible as of December 31, 2025, 2024, and 2023, and 2022, respectively. Certain circumstances, such as an aging workforce without appropriate replacements, a mismatch of existing skillsets to future needs, increased … of knowledge or a lengthy time period associated with skill development. Our costs, including costs to replace employees, productivity costs, health care costs and safety costs, may rise and may not be recoverable in rates. Failure to hire and adequately train replacement employees, including the transfer of significant internal historical knowledge and expertise to the new employees, or the future availability and cost of sufficiently skilled contract labor may lead to safety concerns and adversely affect the ability to manage and operate our businesses, particularly the specialized skills and knowledge required to construct and operate generation facilities, a technology-enabled power grid and transmission and distribution infrastructure, among other facilities. Additionally, further tightening of the labor market and increasing wages may adversely affect our ability to attract, transition and retain key personnel, which could, in turn, negatively impact our ability to identify, motivate and develop talent to succeed senior management. If we are unable to successfully attract and retain an appropriately qualified workforce and conduct appropriate senior management succession planning, our ability to execute on our 10-year capital plan and our business, financial condition, results of operations and cash flows could be negatively affected.

Furthermore, the operations of our facilities depend on good labor relations with our employees, and several of our businesses have in place collective bargaining agreements with different various labor unions, comprising approximately 39% 42% of our workforce. We have several separate bargaining units, each with a unique collective bargaining agreement described further in Note 8(j) to the consolidated financial statements, which information is incorporated herein by reference. The collective bargaining agreements with Gas Workers Union Local 340, IBEW Local 949 Locals 1393 and OPEIU Local 12 USW Locals 12213 & 7441 related to CERC Indiana Gas employees, in Minnesota, as well as with IBEW Local 702 66 related to SIGECO Houston Electric employees, are scheduled to expire in April 2025, December 2025, December 2025 2026 (IBEW Local 1393 & USW Locals 12213 & 7441) and June 2025, respectively, May 2026 (IBEW Local 66), and negotiations of these agreements are expected to be completed before the respective expirations. The collective bargaining agreement with OPEIU Local 12 related primarily to CERC employees in Minnesota expired in December 2025 and negotiations are ongoing. Any failure to reach an agreement on new labor contracts or to negotiate these labor contracts might result in strikes, boycotts or other labor disruptions. These potential labor disruptions could have an adverse effect on our businesses, financial condition, results of operations and/or and cash flows. Labor disruptions, strikes or significant negotiated wage and benefit increases, whether due to union activities, employee turnover or otherwise, could have an adverse effect on our businesses, financial condition, results of operations and cash flows.

Business

New
18 paragraphs
Gone
12 paragraphs
Reworded
63 paragraphs
Word for word as before
114 of 229

34 more differ only in a number or a date, and are not shown.

New in this report

TEEEF

Generating capability 1,071

(1) Total reflects long-term and short-term capacity contracts secured to meet MISO planning requirements.

Power Type Counterparty Location

Date in Service/Expected Date in Service

Wind

NextEra Energy, Inc.

Tama County, Iowa

Purchased in 2025

Wind

Salt Creek Wind, LLC

Tama County, Iowa

Net sales (2) 2

On March 31, 2025, CenterPoint Energy, through its subsidiary CERC Corp., completed the sale of its Louisiana and Mississippi natural gas LDC businesses. On October 20, 2025, CenterPoint Energy, through its subsidiary CERC Corp., entered into the Ohio Securities Purchase Agreement to sell all of the issued and outstanding equity interests in CEOH for total consideration of approximately $2.62 billion, which is comprised of the following: (i) $1.42 billion in cash payable to CERC Corp. upon closing of the transaction, subject to adjustments as set forth in the Ohio Securities Purchase Agreement, including adjustments based on net working capital, regulatory assets and liabilities and capital expenditures at closing of the transaction; and (ii) a 364-day seller promissory note, in the original principal amount of $1.2 billion, to be issued by NFGC at the closing of the transaction and payable to CERC Corp. as provided by the terms and conditions of the Seller Note Agreement. The transaction is expected to close in the fourth quarter of 2026, subject to the satisfaction of customary closing conditions. For further information, see Note 4 to the consolidated financial statements.

The FPA also provides that, whenever the Secretary of the U.S. Department of Energy determines that an emergency exists by reason of a sudden increase in the demand for electric energy, or a shortage of electric energy or of facilities for the generation or transmission of electric energy, then the Secretary of the U.S. Department of Energy has the authority to require by order such temporary connections of facilities and such generation, delivery, interchange or transmission of electric energy as in the Secretary’s judgment will best meet the demands of the emergency and serve the public interest.

January 20, 2025, President Trump signed an executive order to withdraw the United States from the Paris Agreement (which took effect on January 27, 2026), marking a significant shift in U.S. climate policy; on January 7, 2026, it was announced that the United States will withdraw from the United Nations Framework Convention on Climate Change, a treaty that underpins international efforts on global climate; and on February 12, 2026, the EPA announced the finalization of a rule repealing the Endangerment Finding (defined below) as it relates to new motor vehicles. Accordingly, our obligations associated with GHG emissions and climate change-related matters change as administrations change and as legislatures and regulators pass new laws and regulations and amend existing ones.

Jesus Soto, Jr.

Jesus Soto, Jr. has served as Executive Vice President, Chief Operating Officer of CenterPoint Energy since August 2025. Previously, he served as Executive Vice President, Utility Performance Solutions of Quanta Services, Inc., a publicly-traded energy infrastructure services company, from October 2023 to August 2025. He previously served as the Chief Operating Officer for Mears Group, Inc., a wholly-owned subsidiary of Quanta Services, Inc., from September 2019 to September 2023, and as Senior Vice President of Gas Operations for PG&E Corporation, a publicly traded electric utility holding company serving customers in Northern and Central California through its subsidiary Pacific Gas and Electric Company, from May 2012 to July 2019. Prior to joining PG&E Corporation, he served as Vice President of Operations Services and Vice President of Engineering and Construction for the Pipeline Group of El Paso Corporation, a former publicly traded natural gas and related energy products provider. Mr. Soto earned his bachelor's degree from the University of Texas at El Paso, his master's degree in civil engineering from Texas A&M University, and his master's degree in business administration from the University of Phoenix. Mr. Soto serves on the Board of Directors of GTI Energy, an energy technology development and training company, and as Chair of the Industry Pipeline Safety Management Systems Team of the American Petroleum Institute.

No longer in the report

From the report of the year before. A paragraph is listed here when most of its words are nowhere in this year’s business.

Temporary Generation.

Generating capability 720

(1) Indiana Electric procured bi-lateral capacity contracts starting in the 2023-2024 MISO planning year. These contracts were procured before MISO moved to a seasonal construct, which allowed several generating units to receive accreditation in the summer season that would not have received any accreditation under MISO's previous annual construct. This resulted in a reserve margin that is higher than normal in the summer, but was limited to the summer season.

Net sales (2) —

(2) Represents intervals when sales to the MISO were in excess of purchases from the MISO. Net sales were insignificant during 2024 primarily due to the retirement of SIGECO’s A.B. Brown coal generating facilities in 2023 and SIGECO’s exit from joint operations in the Warrick 4 coal generating facility on January 1, 2024.

On March 6, 2024, the SEC adopted final rules that require the Registrants to disclose certain climate-related information in registration statements and annual reports. Litigation challenging the new rule was filed by multiple parties in multiple jurisdictions, which have been consolidated and assigned to the U.S. Court of Appeals for the Eighth Circuit. On April 4, 2024, the SEC announced that it is voluntarily delaying the implementation of the climate disclosure regulations while the U.S. Court of Appeals considers the litigation. While a majority of the reporting requirements would have been applicable to the Registrants in the fiscal year beginning in 2025, with the addition of assurance reporting for GHG inventories starting in 2029 for large accelerated filers, as of April 12, 2024, the effective date of the final rules has been delayed indefinitely and the SEC has indicated that it will publish a document in the Federal Register at the conclusion of the stay addressing a new effective date for the final rules. On February 11, 2025, the SEC notified the U.S. Court of Appeals of a statement issued by the SEC’s Acting Chairman regarding, among other things, the fact that the majority of current SEC Commissioners had previously voted against adopting the rules, and requested that the U.S. Court of Appeals not schedule the case for argument to provide time for the SEC to deliberate and determine the appropriate next steps in the cases. The Registrants continue to evaluate the impact of the final rules on their respective …

Darin M. Carroll

Senior Vice President, Electric Business

Richard C. Leger

Senior Vice President, Natural Gas Business

Darin M. Carroll has served as Senior Vice President, Electric Business of CenterPoint Energy since July 2024. He previously served as Senior Vice President, Natural Gas Business from January 2023 to July 2024; as Senior Vice President, Operations Support from January 2022 to January 2023; and as Vice President, Operations Support from February 2019 to January 2022. Prior to Vectren’s acquisition by CenterPoint Energy, Mr. Carroll served as Director, Operations from February 2014 to February 2019 of Vectren. He earned his bachelor’s degree from the University of Southern Indiana. Mr. Carroll currently serves on the Executive Committee and Board of Directors of the Junior Achievement of Southeast Texas and as a member of the Research Advisory Committee of the Electric Power Research Institute. He has also previously been on the Board of Directors of the American Gas Association, the Southern Gas Association, and the Guardianship Services of Southwestern Indiana, as well as a trustee of the American Gas Foundation. Mr. Carroll has also served as a member of the Indiana Energy Association Gas Operations Committee, Midwest Energy Association Electric Operations Steering Committee, and American Gas Association Field Operations Committee. He earned a bachelor’s degree from the University of Southern Indiana in Evansville, Indiana.

Richard C. Leger has served as Senior Vice President, Natural Gas Business of CenterPoint Energy since January 2025. Mr. Leger previously served in various positions of increasing responsibilities at CenterPoint Energy since 2001, including as Interim Senior Vice President, Natural Gas Business from July 2024 to December 2024; as Senior Vice President, Indiana Electric from January 2022 to July 2024; as Vice President of Gas Operations, Indiana and Ohio from February 2019 to January 2022; as Director, District Operations for Little Rock, Arkansas from November 2015 to February 2019; as Director, Regulatory Affairs from August 2011 to November 2015; and as Manager, Sales and Conservation Improvement Program from August 2010 to August 2011. Mr. Leger currently serves as a board member for the American Gas Association, Southern Gas Association, United Way of Southwestern Indiana and Golf Gives Back. He is also a trustee of the American Gas Foundation and a former chair of the Southeast Energy Efficiency Alliance. In addition, Mr. Leger served six years in the Louisiana Army National Guard. He earned two bachelor’s degrees in accounting and marketing from McNeese State University.

Reworded

Each paragraph as it reads now, with the words that are new this year marked and the words that were taken out struck through. A long stretch that did not change is left out (…).

… Resources Corp. Information contained herein relating to any individual Registrant is filed by such Registrant solely on its own behalf. Each No Registrant makes no any representation as to information relating exclusively to the other Registrants or the subsidiaries of CenterPoint Energy, Inc. other than itself or its subsidiaries. Except as discussed …

… are used as abbreviated references to CenterPoint Energy, Inc. together with its consolidated subsidiaries, including Houston Electric and CERC, unless otherwise stated. otherwise.

As of December 31, 2024, 2025, CenterPoint Energy’s indirect, wholly-owned operating subsidiaries included:

• Houston Electric, which provides electric transmission service to transmission service customers in the ERCOT region and distribution service to REPs serving the Texas Gulf Coast area that includes the city of Houston. Bond Company IV is a wholly-owned, bankruptcy-remote entity formed solely for the purpose of purchasing and owning transition property through the issuance of Securitization Bonds;

• CERC Corp., which (i) directly owns and operates natural gas distribution systems in Louisiana, Minnesota Mississippi and Texas, (ii) indirectly, through Indiana Gas and CEOH, owns and operates natural gas distribution systems in Indiana and Ohio, …

On June 30, 2023, March 7, 2025, SIGECO acquired 100% of the equity interests in Posey Solar, which was constructing a 191 MW solar array in Posey County, Indiana, for approximately $357 million. On March 31, 2025, CenterPoint Energy, through its subsidiary CERC Corp., completed the sale of its indirect subsidiary, Energy Systems Group, to an unaffiliated third party. Louisiana and Mississippi natural gas LDC businesses for approximately $1.2 billion. On February 19, 2024, October 20, 2025, CenterPoint Energy, through its subsidiary CERC Corp., entered into the LAMS Asset Ohio Securities Purchase Agreement to sell its Louisiana all of the issued and Mississippi natural gas LDC businesses. outstanding equity interests in CEOH for total consideration of approximately $2.62 billion, which is comprised of the following: (i) $1.42 billion in cash payable to CERC Corp. upon closing of the transaction, subject to adjustments as set forth in the Ohio Securities Purchase Agreement, including adjustments based on net working capital, regulatory assets and liabilities and capital expenditures at closing of the transaction; and (ii) a 364-day seller promissory note, in the original principal amount of $1.2 billion, to be issued by NFGC at the closing of the transaction and payable to CERC Corp. as provided by the terms and conditions of the Seller Note Agreement. The transaction is expected to close in the first fourth quarter of 2025. 2026, subject to the satisfaction of customary closing conditions. For further information, see Note 4 to the consolidated financial statements. On February 19, 2024, CenterPoint Energy, through its subsidiary CERC Corp., entered into the LAMS Asset Purchase Agreement to sell its Louisiana and Mississippi natural gas LDC businesses. The transaction was approved by final orders issued by the MPSC on December 3, 2024 and by the LPSC on December 17, 2024. The transaction is expected to close in the first quarter of 2025. For further information, see Note 4 to the consolidated financial statements.

The Registrants’ principal executive offices are located at 1111 Louisiana Street, Houston, Texas 77002 (telephone number: 713-207-1111).

• the charters of the Audit, Corporate Governance and Nominating, Human Capital and Compensation, Governance, Environmental and Sustainability, and Safety and Operations committees of our Board. of Directors.

Houston Electric is a transmission and distribution electric utility that operates wholly within the state of Texas. Houston Electric does not make direct retail or wholesale sales of electric energy or own or operate any power generating facilities other than leased TEEEF.

As allowed by a law enacted by the Texas legislature after the February 2021 Winter Storm Event and amended in 2023, Houston Electric is leasing has entered into contractual arrangements to facilitate access to TEEEF units, both on a long-term basis and, to a limited extent, on a month-to-month basis, that can aid in restoring power to customers during certain significant power outages that are impacting its distribution system. On December 19, 2024, In June 2025, Houston Electric announced a proposal entered into definitive documentation (the “ERCOT Transaction”), subject to PUCT approval, with relevant parties to release certain of Houston Electric’s its 15 large 27 MW to 32 MW TEEEF units to the San Antonio area prior until March 2027 unless terminated earlier pursuant to the summer provisions of 2025 for a period of up to two years, the ERCOT Transaction, during which Houston Electric would will not receive revenue or profit from ERCOT and would will also not charge Houston-area customers for these TEEEF units while they are in the San Antonio area serving ERCOT. In November 2025, Houston Electric proposed to release its five medium (5.7 MW) TEEEF units and to remove the associated lease costs from its rates effective January 1, 2026. On February 13, 2026, Houston Electric requested continued abatement until February 27, 2026 due to continued settlement discussions. As of December 31, 2024, 2025, Houston Electric leased 505 519 MW of TEEEF on a long-term basis. For more information, see “Management’s Discussion and Analysis of Financial Condition and Results of Operations — Executive Summary — Significant Events — May 2024 Storm Events and Hurricane Beryl” in Item 7 of Part II of this report, as well as Note 7 and Note 19 to the consolidated financial statements.

Houston Electric has special purpose subsidiaries consisting of VIEs, including Transition Bond Company IV and Restoration Bond Company II, which are consolidated. The Bond Companies, which it consolidates. These consolidated special purpose subsidiaries VIEs are wholly-owned, bankruptcy-remote, special purpose entities that were formed solely for the purpose of purchasing and owning securitizing transition property or system restoration property through the issuance of Securitization transition bonds or system restoration bonds, and conducting activities incidental thereto. The Securitization Bonds issued by Bond Company IV were are repaid through charges imposed on customers in Houston Electric’s service territory. Restoration Bond Company repaid in full its last outstanding system restoration bonds at maturity on August 15, 2022, and was subsequently dissolved in 2024. On October 15, 2024, Transition Bond Company IV repaid in full its last outstanding transition bonds at maturity. For further discussion of the Securitization Bonds issued by Bond Company IV and the outstanding balances as of December 31, 2025 and 2024, and 2023, see Note 12 to the consolidated financial statements.

Total load and the related reserve margin at the time of the system summer peak on August 29, 2024, June 25, 2025 is presented below in MW, except for reserve margin at peak:

Power Type Counterparty Location Expected Date in Service Capacity (MW) Term (in Years)

Solar Clenera, LLC Warrick Origis Knox County, Indiana 2026 100 25 Solar Oriden Vermillion County, Indiana 2026 185 15 150 20

… suppliers are those that account for greater than 10% of Indiana Electric’s coal purchases. For the year ended December 31, 2024, 2025, Sunrise LLC accounted for 88% 100% of Indiana Electric’s coal purchases. with the remaining 12% being purchased from other suppliers.

SIGECO has a special purpose subsidiary, VIE, SIGECO Securitization Subsidiary, which it consolidates. is consolidated. This consolidated special purpose subsidiary VIE is a wholly-owned, bankruptcy-remote, special purpose entity that was formed solely for the purpose of facilitating the securitization financing of qualified costs. The obligations of the … Indiana Electric’s service territory. For further discussion of the SIGECO Securitization Bonds and the outstanding balance as of December 31, 2024, 2025, see Note 12 to the consolidated financial statements.

CenterPoint Energy’s and CERC’s natural gas distribution businesses engage in regulated intrastate natural gas sales to, and natural gas transportation and storage for, residential, commercial, industrial and transportation customers. CenterPoint Energy’s and CERC’s natural gas distribution businesses provide permanent pipeline connections through interconnects with various interstate and intrastate pipeline companies through CEIP. CenterPoint Energy’s and CERC’s natural gas distribution businesses also provided services in Minnesota consisting of residential appliance repair and maintenance services along with HVAC equipment sales. Additionally, CenterPoint Energy and CERC’s natural gas distribution businesses provided home repair protection plans to natural gas customers in Indiana, Mississippi, Ohio and Texas through a third party as of December 31, 2024. 2025.

The table below reflects the number of CenterPoint Energy’s and CERC’s natural gas distribution business customers by state as of December 31, 2024: 2025:

The largest metropolitan areas served in each state were Houston, Texas; Minneapolis, Minnesota; Shreveport, Louisiana; Biloxi, Mississippi; Evansville, Indiana; and Dayton, Ohio.

The demand for natural gas sales to residential customers and natural gas sales and transportation for commercial and industrial customers is seasonal and affected by variations in weather conditions. In 2024, 2025, approximately 64% 68% and 65% 69% of the total throughput for CenterPoint Energy’s and CERC’s natural gas total throughput distribution businesses, respectively, occurred in the first and fourth quarters. respectively. These patterns reflect the higher demand for natural gas for heating purposes during the colder months.

In 2024, 2025, CenterPoint Energy’s natural gas distribution businesses purchased virtually all of its their natural gas supply pursuant to contracts with remaining terms varying from a few months to three years. Major suppliers are those that account for greater than 10% of CenterPoint Energy’s or CERC’s annual natural gas supply purchases.

CenterPoint Energy’s and CERC’s natural gas transports distribution businesses transport their natural gas supplies through various intrastate and interstate pipelines under contracts with remaining terms, including extensions, varying from one to fifteen years. CenterPoint Energy’s and CERC’s natural gas anticipates distribution businesses anticipate that these gas supply and transportation contracts will be renewed or replaced prior to their expiration.

CenterPoint Energy’s and CERC’s natural gas distribution businesses actively engage in commodity price stabilization pursuant to annual gas supply plans presented to and/or filed with each of its their state regulatory authorities. These price stabilization activities include use of storage gas and contractually establishing structured prices (e.g., fixed price, costless collars and caps) with CenterPoint Energy’s and CERC’s natural gas distribution business’ physical gas suppliers. Their gas supply plans generally call for 50–75% 50–70% of normal winter supplies to be stabilized in some fashion.

The regulations of the states in which CenterPoint Energy’s and CERC’s natural gas distribution businesses operate allow them to pass through changes in the cost of natural gas, including savings and costs of financial derivatives …

CenterPoint Energy’s and CERC’s natural gas distribution businesses use various third-party storage services or owned natural gas storage facilities to meet peak-day requirements and to manage the daily changes in demand due to changes in weather. CenterPoint Energy’s and CERC’s natural gas distribution businesses may also supplement contracted supplies and storage from time to time with stored LNG and propane-air plant production.

On an ongoing basis, CenterPoint Energy’s and CERC’s natural gas distribution businesses enter into contracts to provide sufficient supplies and pipeline capacity to meet their customer requirements. However, it is possible for …

CenterPoint Energy’s and CERC’s natural gas distribution businesses continue to utilize AMAs associated with their utility distribution service in Indiana, Louisiana, Minnesota Mississippi and Texas. Generally, AMAs are contracts between CenterPoint Energy’s and CERC’s natural gas distribution businesses and an asset manager that are intended to transfer the working capital obligation and maximize the utilization of the assets. In these agreements, CenterPoint Energy’s and CERC’s natural gas agrees distribution businesses agree to release transportation and storage capacity to other parties to manage natural gas storage, supply and delivery arrangements for CenterPoint Energy’s and CERC’s natural gas distribution businesses and to use the released capacity for other purposes when it is not needed for CenterPoint Energy’s and CERC’s natural gas distribution businesses. CenterPoint Energy’s and CERC’s natural gas distribution businesses may receive compensation from the asset manager through payments made over the life of the AMAs. CenterPoint Energy’s and CERC’s natural gas has distribution businesses have an obligation to purchase their winter storage requirements that have been released to the asset manager under these AMAs. The … the longest of which expires in 2029. Pursuant to the provisions of the agreements, CenterPoint Energy’s and CERC’s natural gas distribution businesses either sells sell natural gas to the asset manager and agrees agree to repurchase an equivalent amount of natural gas throughout the year at the same cost, or simply purchases its full natural gas requirements at each delivery point from the asset manager. For Each of CenterPoint Energy and CERC had no amounts outstanding under these AMAs see Note 12 to the consolidated financial statements. as of December 31, 2025 and 2024.

CenterPoint Energy’s and CERC’s natural gas distribution businesses compete primarily with alternate energy sources such as electricity and other fuel sources. In some areas, intrastate pipelines, other gas … interstate pipelines, natural gas marketers operating on these pipelines may be able to bypass CenterPoint Energy’s and CERC’s natural gas distribution business’ facilities and market, sell and/or transport natural gas directly to commercial and industrial customers.

In almost all communities in which CenterPoint Energy’s and CERC’s natural gas provides distribution businesses provide natural gas distribution services, they operate under franchises, certificates or licenses obtained from state and local authorities. The original terms of the franchises, with various expiration dates, typically range from 20 10 to 30 years. CenterPoint Energy’s and CERC’s natural gas expects distribution businesses expect to be able to renew expiring franchises. In most cases, franchises to provide natural gas utility services are not exclusive. In almost all communities in which CenterPoint Energy’s and CERC’s natural gas distribution businesses provide natural gas distribution services, they operate under franchises, certificates or licenses obtained from state and local authorities. The original terms of the franchises, with various expiration dates, typically range from 10 to 30 years. CenterPoint Energy’s and CERC’s natural gas distribution businesses expect to be able to renew expiring franchises. In most cases, franchises to provide natural gas utility services are not exclusive.

CenterPoint Energy’s Corporate and Other reportable segment consists of corporate support operations that support CenterPoint Energy’s business operations and also includes office buildings and other real estate used for business operations. CenterPoint Energy’s Corporate and Other reportable segment also consisted of energy performance contracting and sustainable infrastructure services by Energy Systems Group through June 30, 2023, the date …

For further information on climate change trends and uncertainties, a discussion of the Registrants’ ongoing regulatory proceedings, see “Management’s Discussion and Analysis of Financial Condition and Results of Operations — Liquidity and Capital Resources — Regulatory Matters” — Climate Change Trends and Uncertainties” in Item 7 of Part II of this report, which discussion is incorporated herein by reference.

… is already reflected in the base distribution rate, a TEEEF mechanism for recovery of costs associated with leasing and operating certain TEEEF, a TCRF mechanism for recovery of approved wholesale transmission cost changes billed by a transmission service provider, a nuclear …

The energy and capacity secured from Indiana Electric’s available generation resources are utilized primarily to serve the needs of retail electric customers residing within Indiana Electric’s franchised service territory. Costs of The expenses and capital investments associated with operating Indiana Electric’s generation facilities are recovered through IURC-approved base rates as well as periodic rate recovery mechanisms including the … system. Proceeds from the sales of energy from Indiana Electric’s generation facilities that exceed the requirements of retail customers are shared by Indiana Electric and provided to retail electric customers.

… Operations of Indiana Electric’s generation facilities are subject to regulation by the EPA and the IDEM as it pertains to the discharge of constituents water quality, waste disposal and air emissions from the generation facilities. For further discussion, see “Our Business — Environmental Matters” below.

Substantially all of CenterPoint Energy’s and CERC’s natural gas is distribution businesses are subject to cost-of-service rate regulation by the relevant state public utility commissions and, in Texas, by those municipalities that have retained original jurisdiction. In certain of the jurisdictions in which they operate, CenterPoint Energy’s and CERC’s natural gas distribution businesses have annual rate adjustment mechanisms that provide for changes in rates dependent upon certain changes in invested capital earned returns on equity or actual margins realized.

For a discussion of certain of CenterPoint Energy’s and CERC’s natural gas distribution businesses’ ongoing regulatory proceedings, see “Management’s Discussion and Analysis of Financial Condition and Results of Operations — Liquidity and Capital Resources — Regulatory Matters” in Item 7 of Part II of this report, which discussion is incorporated herein by reference.

… federal safety standards for the transportation of hazardous liquids by pipeline. Every four years PHMSA is up for reauthorization by the U.S. Congress and with that reauthorization comes changes to the legislative requirements that the U.S. Congress sets forth for the oversight of natural gas and hazardous liquid pipelines. In 2020, the PIPES Act was enacted. …

CenterPoint Energy and CERC anticipate that compliance with PHMSA’s regulations, performance of the remediation activities by CenterPoint Energy’s and CERC’s natural gas distribution businesses and intrastate pipelines, and verification of records on maximum allowable operating pressure will continue to require increases in both capital …

Increasingly, environmental regulation has resulted in more restrictions Our obligations associated with these requirements change as administrations change and limitations as legislatures and regulators pass new laws and regulations and amend existing ones. Therefore, it is difficult to project future costs of compliance and their impact on activities that may impact the environment. competition. There can be no assurance as to the amount or timing of future expenditures for environmental compliance or remediation and …

… facts or conditions will not cause them to incur significant costs. The following is a discussion of material current environmental and safety issues, laws and regulations that relate to the Registrants’ operations. The Registrants believe that they are in substantial compliance with these environmental laws and regulations.

Greenhouse Gas GHG Emissions and Climate Change-Related Regulation and Compliance (CenterPoint Energy)

There is increasing attention being paid in the United States and worldwide to The issue of climate change has received focus at the state, federal and international level. As a result, from time to time, regulatory agencies have considered the modification of existing laws or regulations or the adoption of new laws or regulations addressing the emissions of GHG and other climate change-related matters on the state, federal or international level. On The EPA released its initial GHG regulation for fossil fuel-fired electric generating units in 2015. Since then, various iterations of GHG regulations have been promulgated, withdrawn and litigated, and the current rule applicable to fossil fuel-fired electric generating units was finalized in April 2024. In April 2024, the EPA finalized the current New Source Performance Standards for Greenhouse Gas Emissions from New, Modified, Reconstructed … 2024, the U.S. Supreme Court declined to stay the implementation of the rule while the rule is on judicial review. However, on February 19, 2021, June 17, 2025, the United States formally rejoined the Paris Agreement, which drove EPA proposed a renewed regulatory push rule to require further repeal GHG emission reductions standards for fossil fuel-fired electric generating units, or in the alternative, to repeal a narrower set of requirements, including the emission guidelines for existing fossil fuel-fired steam electric generating units, the carbon capture and sequestration/storage (CCS)-based standards for coal-fired steam generating units undertaking a large modification and the CCS-based standards for new base load stationary combustion turbines. Additionally, the IRA established the Methane Emissions Reduction Program, which imposes a charge on methane emissions from certain natural gas transmission facilities, the energy sector, and led negotiations at the global climate conference in Glasgow, Scotland. rules for which were finalized on April 22, 2021, the United States announced goals of 50% reduction of economy-wide GHG emissions, and 100% carbon-free electricity by 2035 from a 2021 baseline, which formed the basis of the U.S. commitments announced in Glasgow. Nevertheless, November 18, 2024. However, on January 20, 2025, President Trump signed an executive order to withdraw the United States from the Paris Agreement, marking a significant shift in U.S. climate policy. Pursuant to the terms of the Paris Agreement, the withdrawal will take effect on January 27, 2026. Additionally, in January March 14, 2025, President Trump signed a series Congressional Review Act resolution disapproving the EPA’s final rule, thereby prohibiting the rule from taking effect, and the OBBBA postponed the imposition of executive orders that, among other things, (i) call upon the methane emissions charge to 2034. On September 16, 2025, the EPA proposed a rule to submit a report end the Greenhouse Gas Reporting Program (“GHGRP”) for all sectors except petroleum and natural gas systems (excluding reporting for natural gas distribution, which would also be eliminated under the proposed rule). Reporting for petroleum and natural gas systems under the GHGRP would be deferred until 2034 under the proposal. On February 12, 2026, the continuing applicability EPA announced the repeal of its the 2009 “Endangerment Finding” for GHGs under the Clean Air Act, which found that GHG emissions endanger the public health and issue guidance welfare of current and future generations and that emissions of GHGs from motor vehicles contribute to GHG pollution. The repeal calls into question the EPA’s authority to regulate GHG emissions, as well as the EPA’s prior scientific assessment of climate change risks. Litigation regarding the repeal is anticipated and it is unclear how the repeal will impact the EPA’s regulation of GHG emissions going forward. On March 6, 2024, the “social cost SEC adopted final rules to require disclosure of carbon” certain climate-related information in registration statements and annual reports. Litigation challenging the rule was filed by multiple parties in multiple jurisdictions, which have been consolidated and assigned to consider whether such metric should be eliminated, (ii) direct federal executive departments and agencies the U.S. Court of Appeals for the Eighth Circuit. On September 12, 2025, the U.S. Court of Appeals issued an order to initiate a regulatory freeze for certain hold the petitions challenging the climate disclosure rules that have not taken effect, in abeyance pending review further action by the newly appointed agency head, (iii) temporarily halt certain federal government agencies from issuing approvals, permits and loans for onshore wind projects pending the completion of certain assessments and reviews and (iv) pause the disbursement of funds appropriated through the IRA and the Infrastructure Investments and Jobs Act. SEC.

In September 2021, CenterPoint Energy announced its net zero emissions has adopted energy transition goals. for both Scope 1 emissions and certain Scope 2 emissions by 2035 as well as a goal to reduce certain Scope 3 emissions by 20% to 30% by 2035 from a 2021 baseline. Because Texas is an unregulated market, CenterPoint Energy’s Scope 2 emissions estimates do not take into account Texas electric transmission … EIA-176 reports and do not take into account the emissions of transport customers and emissions related to upstream extraction. These emission energy transition goals are expected to be used to position CenterPoint Energy to comply with anticipated future regulatory requirements from any future administrations to further reduce GHG emissions. For more information regarding CenterPoint Energy’s net zero and GHG emissions reduction energy transition goals and their related risks, see “Risk Factors — Risk Factors Affecting Regulatory, Environmental and Legal Risks — CenterPoint Energy is subject to operational and financial risks ...” CenterPoint Energy’s and CERC’s revenues, operating costs and capital requirements could be adversely affected as a result of any regulatory action that would require installation of new control technologies or a modification of their operations or would have the effect of reducing the consumption of natural gas. The IRA established the Methane Emissions Reduction Program, which imposes a charge on methane emissions from certain natural gas transmission facilities, the rules for which were finalized on November 18, 2024, and the EPA published final, new regulations targeting reductions in methane emissions on March 8, 2024, which may increase costs related to production, transmission and storage of natural gas. CenterPoint Energy’s net zero emissions energy transition goals are aligned with Indiana Electric’s generation transition plan and are expected to position Indiana Electric to comply with anticipated future regulatory requirements related to GHG emissions reductions. Houston Electric, in contrast to some electric utilities including Indiana Electric, does … or to use energy sources other than natural gas could result in a decrease in demand for the Registrants’ services. For example, Minnesota has enacted the Natural Gas Innovation Act that seeks to provide customers with access to renewable energy resources and innovative technologies, with the goal of reducing GHG emissions. Further, certain local government bodies have introduced or are considering requirements and/or incentives to reduce energy consumption by certain specified dates. For example, Minneapolis has adopted carbon emission reduction goals in an effort to decrease reliance on natural gas. Additionally, cities in Minnesota within CenterPoint Energy’s Natural Gas operational footprint are considering initiatives to eliminate natural gas use in buildings and focus on electrification. Also, Minnesota cities may consider seeking legislative authority for the ability to enact voluntary enhanced energy standards for all development projects. These initiatives could have a significant impact on CenterPoint Energy and its operations, and this impact could increase if other cities and jurisdictions in its service area enact similar initiatives. Further, our third-party suppliers, vendors and partners may also be impacted by climate change laws and regulations, which could impact …

Compliance costs and other effects associated with climate change, reductions in GHG emissions and obtaining renewable energy sources remain uncertain. Significant changes in policy due to administration change can create regulatory uncertainty. For example, the repeal of the Endangerment Finding could lead to a patchwork of conflicting state superfund laws and state regulation relating to climate change and GHG emissions. Although the amount of compliance costs remains uncertain, any new regulation or legislation relating to climate change will likely result in an increase in compliance costs. For example, CenterPoint Energy’s and CERC’s revenues, operating costs and capital requirements could be adversely affected as a result of any regulatory action that would require installation of new control technologies or a modification of their operations or would have the effect of reducing the consumption of natural gas. While the requirements of a federal or state rule remain uncertain, CenterPoint Energy will continue to monitor regulatory activity regarding GHG emission standards that may affect its business. Currently, CenterPoint Energy does not purchase carbon credits. In connection with its net zero and GHG emissions energy transition goals, CenterPoint Energy expects to purchase carbon credits in the future; however, CenterPoint Energy does not currently expect the number of credits, or cost for those credits, to be material.

In April 2020 the EPA proposed a new set of rules that sought to clarify the Clean Water Act’s jurisdiction over “waters of the United States,” but that set of rules was later vacated by decisions in the U.S. federal district courts in New Mexico and Arizona. On December 30, 2022, the EPA and the U.S. Army Corps of Engineers announced the final “Revised Definition of ‘waters of the United States”’ rule, which was published on January 18, 2023 and became effective on March 20, 2023. However, On May 25, 2023, the U.S. Supreme Court issued a decision limiting the scope of federal jurisdiction over wetlands in … case of Sackett v. Environmental Protection Agency , and on August 29, 2023, the EPA issued a final rule that seeks sought to conform with the U.S. Supreme Court decision. As a result of ongoing rulemaking litigation, the Registrants’ operations in all … consistent with the Supreme Court decision in Sackett , while operations in Minnesota fall under the 2023 rule, as amended. However, on November 17, 2025, the EPA announced a proposed rule that seeks to further clarify the definition of “Waters of the United States.” CenterPoint Energy is unable to predict the outcome of current or future litigation or regulatory proceedings, but does not expect …

… April 25, 2024, the EPA released its final Supplemental ELG and Standards for the Steam Electric Generating Point Source Category, and on December 31, 2025, the EPA published its final rule further extending the applicable compliance deadlines. The Registrants currently anticipate that they will be in compliance with the Supplemental ELG Guidelines and any extensions thereto at the Culley facility due to previous wastewater treatment upgrades.

… installation of “best technology available” to mitigate impingement and entrainment of aquatic species in cooling water intake structures. Indiana Electric is currently completing has completed the required ecological studies and anticipates timely compliance at its F.B. Culley facility in 2025. accordance with deadlines to be established by IDEM.

In 2015, the EPA finalized the CCR Rule. Indiana Electric has historically operated three ash ponds, two at the F.B. Culley facility (Culley East and Culley West) and one at the A.B. Brown facility; these ash ponds are no longer in 2015, the EPA finalized its CCR Rule, which regulates coal ash as non-hazardous material under the RCRA. The final rule allows beneficial reuse of ash, and the majority of the ash generated by Indiana Electric’s remaining generating units will continue to be beneficially reused. Indiana Electric is required to perform integrity assessments, including ground water monitoring, at its F.B. Culley and A.B. Brown generating stations. The ground water studies were necessary to determine the remaining service life of the ponds and whether a pond must be retrofitted with liners or closed in place. Groundwater monitoring indicates potential groundwater impacts adjacent to Indiana Electric’s ash impoundments, and further analysis is ongoing. The CCR Rule required companies to complete location restriction determinations by October 18, 2018. Indiana Electric completed its evaluation and determined that one F.B. Culley pond (Culley East) and the A.B. Brown pond failed the aquifer placement location restriction. As a result of this failure, Indiana Electric was required to cease disposal of new ash in the ponds and commence closure of the ponds by April 11, 2021. Indiana Electric filed timely requests for extensions available under the CCR Rule that would allow Indiana Electric to continue to use the ponds through October 15, 2023. On January 22, 2021, Indiana Electric received letters from the EPA for both the F.B. Culley and A.B. Brown facilities that determined Indiana Electric’s extension submittals complete and extended the compliance deadline of April 11, 2021 until the EPA issues a final decision on the extension requests. On October 5, 2022, SIGECO received a proposed conditional approval of its extension request for the A.B. Brown facility. operation. Both the Culley East and A.B. Brown facility have been taken out of service in a timely manner per the commitments made to the EPA in the extension requests filed for both ponds. and closure activities continue. The Culley West pond was closed under CCR provisions applicable to inactive ponds, and closure activities were completed in December 2020. For further discussion about Indiana Electric’s ash ponds, see Note 14(d) 14(c) to the consolidated financial statements.

… Indiana for further evaluation. For further discussion about Indiana Electric’s sites identified pursuant to the CCR Legacy Rule, see Note 14(d) 14(c) to the consolidated financial statements.

For information about preexisting environmental matters, see Note 14(d) 14(c) to the consolidated financial statements.

CenterPoint Energy believes its employees are its greatest asset, and their unique skills, knowledge, experience and backgrounds are critical to safely and reliably delivering electricity and natural gas to CenterPoint Energy’s customers across its service territories. and seeks to create an open and safe work environment. CenterPoint Energy’s core values—safety, integrity, accountability, initiative and respect—guide how it makes decisions and provide the foundation for a strong culture of ethics where employees are responsible for upholding these values and following CenterPoint Energy’s Ethics and Compliance Code.

(1) Employees in the Corporate and Other reportable segment provide services to the Electric and Natural Gas reportable segments and the costs of these services have been charged directly to the Electric and Natural Gas reportable segments using assignment methods that management believes are reasonable. For further information, see Note 18 to the consolidated financial statements.

Talent Attraction, Development and Retention. CenterPoint Energy’s human capital priorities include attracting, retaining and developing high performing talent through its talent management activities. CenterPoint Energy endeavors to attract quality candidates through its recruitment and selection processes. CenterPoint Energy recruits seeks to recruit qualified employees regardless of race, gender, color, sexual orientation, age, religion, national origin, or physical or mental disability. The CenterPoint Energy talent acquisition team actively promotes CenterPoint Energy on engages with college campuses to create awareness of our offerings to opportunities in engineering, finance and technical occupations, and maintains relationships with student organizations at many institutions throughout our footprint. across CenterPoint Energy’s service territories. CenterPoint Energy also maintains internship and apprenticeship programs that are designed to provide real-world experience, training and mentoring to interns and apprentices. Additionally, CenterPoint Energy works with other energy utility companies, associations, unions, educators and business partners to support workforce readiness and long-term talent development in the energy industry.

CenterPoint Energy takes a strategic approach to attracting, retaining, and developing its workforce. CenterPoint Energy’s strategy to attract, retain and develop its employees combines talent discussions and succession planning along with internal talent development as essential elements of overall workforce planning and development. To support its commitment to delivering electricity and natural gas safely and reliably, CenterPoint Energy focuses on the continuous continued development of its greatest assets, its employees, to build a sustainable leadership pipeline. To meet the business's business’ future needs, CenterPoint Energy’s goal is to create great leaders capable of developing their employees, while supporting the business’ goals and maintaining a high-performing workforce through employee engagement and workplace culture. CenterPoint Energy has a number of tools for leadership and employee development that expand opportunities available to employees. For example, CenterPoint Energy maintains a corporate university that offers a variety of content and resources to employees, including instructor-led and on-demand learning, to help meet employees’ needs for professional, leadership and business unit-specific development. Additionally, CenterPoint Energy conducts regular talent discussions, including succession planning with all various levels of leadership, to provide business continuity and identify its future leaders and opportunities. CenterPoint Energy invests in employee development throughout the year to align individual performance to business needs, drive development planning and contribute to support career progression. CenterPoint Energy’s processes and progress are is reviewed regularly for continuous continued improvement.

Engagement. CenterPoint Energy is dedicated to advancing an ethical open and high performance high-performing work environment where business results are achieved through the experience, skills, abilities and talents of the whole workforce. CenterPoint Energy … where every employee is engaged, aligned with our values, strategy, goals and priorities, and understands how each person contributes to the Company’s CenterPoint Energy’s long-term performance. In 2024, 2025, CenterPoint Energy’s senior leadership team conducted an employee engagement survey and held quarterly town hall meetings with employees to share key company updates, with employees across the Company CenterPoint Energy participating in person or via video conference.

Chair of the Board, President and Chief Executive Officer

Executive Vice President and Chief Operating Officer Jason P. Wells has served as Chair of the Board since October 8, 2025, and as President and Chief Executive Officer of CenterPoint Energy and a member of the Board of Directors of CenterPoint Energy since January 5, 2024. Previously he served as President and Chief Operating Officer of CenterPoint Energy from May 2023 to … his bachelor’s degree and master’s degree in accounting, both from the University of Florida. He is a certified public accountant (inactive). Mr. Wells serves on the Executive Committee and Board for the Greater Houston Partnership, the Advisory Board of the Kinder Institute for Urban Research at Rice University, and the Boards of Central Houston, Inc., and M.D. Anderson Cancer Center, Performing Arts Houston and the United Way of Greater Houston.

… Foundation in 2021 and served until December 2024. She currently serves as a member of the Board of Directors of Nextpower Inc. and the Houston Zoo.

… He was appointed to the Texas Diabetes Council by Texas Governor Perry in 2013 for a term ending in 2019, and he was has since been reappointed by Texas Governor Abbott twice (most recently in 2019 2025 for a term ending in 2025. 2031). Mr. Ryan earned his bachelor’s degree from the Texas McCombs School of Business and juris doctorate from the University of … Ryan currently serves on the boards of the Lone Star Flight Museum and the Association of Electric Companies of Texas. and on the advisory board of the Strategic AI Program at Houston Christian University. He also serves on the executive committee of the legal committee of the American Gas Association.

Two reports are compared by their words, not by their layout: a paragraph that only moved, or that runs over a page in one report and not the other, counts as unchanged. Tables of figures are left out. The discussion of the year’s results is not compared, since it is written anew each year.